LOT 3: SFD W ATTACHED GARAGE PER VTT - 82550 - SL 3 OF 7
Permit Issued
Issued on 3/19/2022
Issuing Office
Current Status
CofO Issued on 1/21/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/22/2021 APPLICANT
Assigned to Plan Check Engineer 2/10/2021 SAM CHANG
Corrections Issued 2/23/2021 SAM CHANG
Quality Review Completed 3/1/2021 EUGENE BARBEAU
Building Plans Picked Up 3/9/2021 APPLICANT
Applicant returned to address corrections 8/18/2021 SAM CHANG
Applicant returned to address corrections 8/20/2021 SAM CHANG
Applicant returned to address corrections 9/22/2021 SAM CHANG
Applicant returned to address corrections 3/9/2022 SAM CHANG
Applicant returned to address corrections 3/15/2022 SAM CHANG
Plan Check Approved 3/16/2022 SAM CHANG
Issued 3/19/2022 APPLICANT
CofO in Progress 1/21/2026 BRENDAN MORELLI
Permit Finaled 1/21/2026 DEROLD HAUFF
CofO Issued 1/21/2026 DEROLD HAUFF
Permit Finaled 1/21/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/18/2021 WALLIE JONG
Permit Cleared 6/18/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 7/8/2021 WALLIE JONG
Highway dedication Cleared 7/15/2021 WALLIE JONG
Sewer availability Cleared 8/9/2021 WALLIE JONG
Hydrant and Access approval Cleared 9/22/2021 MATTHEW CRAIG
Low Impact Development Cleared 10/18/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 10/19/2021 WALLIE JONG
"Q" conditions Cleared 11/18/2021 RICHARD REASER
Miscellaneous Cleared 11/18/2021 RICHARD REASER
Miscellaneous Cleared 11/18/2021 RICHARD REASER
Miscellaneous Cleared 11/18/2021 RICHARD REASER
Miscellaneous Cleared 11/18/2021 RICHARD REASER
Work Adjacent to Public Way Cleared 2/24/2022 ARMEN SARKISIAN
Grading Pre-Inspection Cleared 3/16/2022 SAM CHANG
Green Code Cleared 3/16/2022 SAM CHANG
Haul Route Cleared 3/16/2022 SAM CHANG

Contact Information

Architect Stone,, Tracy Anne; Lic. No.: C20219 2041 BLAKE AVENUE      LOS ANGELES, CA 90039
Contractor C M G Development; Lic. No.: 1083438-B 385 E MARKLAND DR      MONTEREY PARK, CA 91755
Engineer Zhang,, Jiefu; Lic. No.: S5270 1205 SOUTH 4TH ST      ALHAMBRA, CA 91801
Geologist Hollingsworth,, Robert Alan; Lic. No.: EG1265 31129 VIA COLINAS SUITE 707      WESTLAKE VILLAGE, CA 91362

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Grading Pre-Inspection 4/18/2022 Corrections Issued ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 7/20/2022 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 7/20/2022 Partial Approval ALEJANDRO DE ARTOLA
Pre-Inspection 7/20/2022 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 7/20/2022 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 7/28/2022 Conditional Approval ALEJANDRO DE ARTOLA
Deputy Reinf. Concrete 8/1/2022 Conditional Approval ALEJANDRO DE ARTOLA
Masonry Wall/Backfill 8/11/2022 Partial Approval ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 8/16/2022 Partial Approval ALEJANDRO DE ARTOLA
Deputy Reinf. Masonry 8/17/2022 Conditional Approval ALEJANDRO DE ARTOLA
Masonry Wall/Backfill 9/8/2022 Partial Approval ALEJANDRO DE ARTOLA
Masonry Wall/Backfill 9/9/2022 Partial Approval ALEJANDRO DE ARTOLA
Deputy Wood Construction 10/18/2022 Conditional Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 10/19/2022 Partial Approval ALEJANDRO DE ARTOLA
Pre-Inspection 10/19/2022 Partial Approval ALEJANDRO DE ARTOLA
Drywall Nailing 10/25/2022 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 11/22/2022 Partial Approval ALEJANDRO DE ARTOLA
Drywall Nailing 11/30/2022 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 12/19/2022 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 1/3/2023 Partial Approval SCOTT FINNILA
Drywall Nailing 1/13/2023 Corrections Issued ALEJANDRO DE ARTOLA
Drywall Nailing 1/20/2023 Corrections Issued ALEJANDRO DE ARTOLA
Drywall Nailing 1/24/2023 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 2/17/2023 Partial Approval ALEJANDRO DE ARTOLA
Drywall Nailing 4/6/2023 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 4/7/2023 Partial Approval ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 4/27/2023 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 4/27/2023 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 4/28/2023 Partial Approval ALEJANDRO DE ARTOLA
PLUMBING-Rough 6/13/2023 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 6/14/2023 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 7/10/2023 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 7/20/2023 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 7/24/2023 Corrections Issued BRENDAN MORELLI
HVAC-Rough 7/31/2023 Approved BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 8/10/2023 Approved BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 12/12/2023 Partial Approval BRENDAN MORELLI
Pre-Inspection 12/12/2023 Partial Approval BRENDAN MORELLI
Interior/Exterior Lathing 12/19/2023 Partial Approval BRENDAN MORELLI
BUILDING-Rough-Frame 12/26/2023 Corrections Issued BRENDAN MORELLI
Green Building Rough 12/26/2023 Approved BRENDAN MORELLI
Verify Sprinkler Sign Off 12/26/2023 Approved BRENDAN MORELLI
BUILDING-Rough-Frame 1/17/2024 Approved BRENDAN MORELLI
Insulation 1/17/2024 Conditional Approval BRENDAN MORELLI
Drywall Nailing 1/31/2024 Approved BRENDAN MORELLI
Shower Pan 2/26/2024 Approved BRENDAN MORELLI
Interior/Exterior Lathing 3/8/2024 Approved SCOTT FINNILA
Underground Mechanical 7/22/2024 Partial Approval BRENDAN MORELLI
Sewer 8/16/2024 Not Ready for Inspection SCOTT FINNILA
Underground Mechanical 9/10/2024 Partial Approval BRENDAN MORELLI
Underground Mechanical 10/8/2024 Partial Approval BRENDAN MORELLI
Interior/Exterior Lathing 10/16/2024 Approved BRENDAN MORELLI
Special/Order Compliance 3/14/2025 Corrections Issued BRENDAN MORELLI
HVAC-Final 7/3/2025 Approved BRENDAN MORELLI
PLUMBING-Final 7/3/2025 Corrections Issued BRENDAN MORELLI
ELECTRICAL-Final 7/10/2025 Corrections Issued BRENDAN MORELLI
PLUMBING-Final 7/10/2025 Not Ready for Inspection BRENDAN MORELLI
Special/Order Compliance 8/21/2025 Corrections Issued BRENDAN MORELLI
Final 9/18/2025 Partial Inspection BRENDAN MORELLI
Footing/Foundation/Slab 9/18/2025 Approved BRENDAN MORELLI
Green Building Final 9/18/2025 Not Ready for Inspection BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 9/18/2025 SGSOV Not Ready BRENDAN MORELLI
Service/Power Release 9/18/2025 Not Ready for Inspection BRENDAN MORELLI
Smoke Detectors 9/18/2025 Not Ready for Inspection BRENDAN MORELLI
ELECTRICAL-Final 11/13/2025 Partial Approval BRENDAN MORELLI
PLUMBING-Final 11/13/2025 Approved BRENDAN MORELLI
Special/Order Compliance 11/13/2025 Corrections Issued BRENDAN MORELLI
ELECTRICAL-Final 11/26/2025 Partial Approval BRENDAN MORELLI
ELECTRICAL-Final 12/9/2025 Approved BRENDAN MORELLI
Final 1/9/2026 Corrections Issued BRENDAN MORELLI
Green Building Final 1/9/2026 Approved BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 1/9/2026 SGSOV Approved BRENDAN MORELLI
Service/Power Release 1/9/2026 Not Ready for Inspection BRENDAN MORELLI
Smoke Detectors 1/9/2026 Approved BRENDAN MORELLI
Final 1/14/2026 Not Ready for Inspection BRENDAN MORELLI
Service/Power Release 1/14/2026 Approved BRENDAN MORELLI
Final 1/21/2026 OK to Issue CofO BRENDAN MORELLI