15210 W SAN JOSE ST 91345
Certificate Information: 15210 W SAN JOSE ST 91345
- Application / Permit
- 20010-10000-04818
- Plan Check / Job No.
- B20LA23177
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan ADU ADDITION TO (E) GARAGE PER LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 7/5/2021
- Issuing Office
- Current Status
- CofO Issued on 5/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/14/2021 | CRYSTEL MAALOUF |
| Corrections Issued | 1/21/2021 | CRYSTEL MAALOUF |
| Quality Review Completed | 2/2/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 6/18/2021 | CRYSTEL MAALOUF |
| Plan Check Approved | 6/25/2021 | CRYSTEL MAALOUF |
| Issued | 7/5/2021 | APPLICANT |
| CofO in Progress | 4/26/2024 | JENNIFER RABUCHIN |
| Permit Finaled | 5/1/2024 | RUBEN SALAS |
| CofO Issued | 5/1/2024 | RUBEN SALAS |
| Permit Finaled | 5/1/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 2/19/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 2/19/2021 | JOHN TRIANTAFYLLOS |
| Construction near power lines | Cleared | 3/27/2021 | WALTER RAMIREZ |
| Construction within easement | Cleared | 3/27/2021 | WALTER RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/30/2021 | JOHN TRIANTAFYLLOS |
| Hydrant and Access approval | Cleared | 4/23/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 6/9/2021 | YVAINNE GALSIM |
| Roof/Waste drainage to street | Cleared | 6/10/2021 | ABDULLAH SADOZAI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/28/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 12/29/2023 | Partial Approval | JENNIFER RABUCHIN |
| Deputy Drilled-In Anchors | 1/2/2024 | Partial Approval | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 1/4/2024 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 1/17/2024 | Partial Approval | ROBERT GOLD |
| BUILDING-Rough-Frame | 1/25/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 1/25/2024 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Rough | 1/25/2024 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 1/25/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 2/1/2024 | Approved | JENNIFER RABUCHIN |
| Rough-Elec/Plmb/HVAC | 2/1/2024 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 2/12/2024 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 2/12/2024 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 2/12/2024 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 2/12/2024 | Approved | JENNIFER RABUCHIN |
| Wood Frame | 2/12/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Insulation | 2/15/2024 | Conditional Approval | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 2/16/2024 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 2/16/2024 | Approved | JENNIFER RABUCHIN |
| Insulation | 2/16/2024 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 2/21/2024 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 2/21/2024 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 3/28/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 3/28/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 3/28/2024 | Approved | JENNIFER RABUCHIN |
| Green Building Final | 3/28/2024 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 3/28/2024 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Final | 3/28/2024 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 3/28/2024 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Smoke Detectors | 3/28/2024 | Approved | JENNIFER RABUCHIN |
| Final | 4/2/2024 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 4/2/2024 | SGSOV Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 4/15/2024 | Approved | JENNIFER RABUCHIN |
| Final | 4/15/2024 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 4/15/2024 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 4/15/2024 | Approved | JENNIFER RABUCHIN |