930 E MONTECITO DR 90031

Certificate Information: 930 E MONTECITO DR 90031

Application / Permit
20010-10000-04800
Plan Check / Job No.
B20LA23040
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW THREE (3)-STORY SINGLE FAMILY DWELLING WITH ATTACHED TWO (2) CAR GARAGE. NFPA-13R REQUIRE. 1 OF 2
Permit Issued
Issued on 12/9/2022
Issuing Office
Metro
Current Status
CofO in Progress on 6/5/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/11/2020 APPLICANT
Assigned to Plan Check Engineer 1/14/2021 ZAW HAN
Corrections Issued 1/21/2021 ZAW HAN
Quality Review Completed 2/3/2021 GARO TELMI
Building Plans Picked Up 2/5/2021 APPLICANT
Applicant returned to address corrections 2/17/2021 ZAW HAN
Applicant returned to address corrections 3/9/2021 ZAW HAN
Applicant returned to address corrections 6/1/2021 ZAW HAN
Applicant returned to address corrections 7/23/2021 ZAW HAN
Applicant returned to address corrections 2/23/2022 ZAW HAN
Applicant returned to address corrections 4/6/2022 ZAW HAN
Applicant returned to address corrections 4/19/2022 ZAW HAN
Applicant returned to address corrections 6/6/2022 ZAW HAN
Applicant returned to address corrections 9/6/2022 ZAW HAN
Plan Check Approved 10/14/2022 ZAW HAN
Issued 12/9/2022 APPLICANT
CofO in Progress 6/5/2026 LILIANA PORTILLO

Permit Application Clearance Information

Disturb/Remove Protected Trees Cleared 2/25/2021 STEPHEN DUPREY
BHO/Hillside ordinance Cleared 3/1/2021 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 3/1/2021 RENZ SORIANO
Address approval Cleared 3/2/2021 RENZ SORIANO
BHO/Hillside ordinance Cleared 3/3/2021 RENZ SORIANO
BHO/Hillside ordinance Cleared 3/3/2021 RENZ SORIANO
BHO/Hillside ordinance Cleared 3/3/2021 RENZ SORIANO
Sewer availability Cleared 3/8/2021 RENZ SORIANO
Trees in Parkway Cleared 3/8/2021 JOHN KIM
Construction near power lines Cleared 5/26/2021 RIDWAN HARDY
Construction within easement Cleared 5/26/2021 RIDWAN HARDY
Hydrant and Access approval Cleared 5/27/2021 MATTHEW CRAIG
BHO/Hillside ordinance Cleared 8/12/2021 RENZ SORIANO
Permit Cleared 8/12/2021 RENZ SORIANO
Low Impact Development Cleared 3/9/2022 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 3/22/2022 AMAAN MALIK
"D" conditions Cleared 5/9/2022 KENTON TRINH
"Q" conditions Cleared 5/9/2022 KENTON TRINH
CPC Cleared 5/9/2022 KENTON TRINH
Frnt yard landscape/Water mgmt Cleared 5/9/2022 KENTON TRINH
ZI Cleared 5/9/2022 KENTON TRINH
Excavation more than 5-ft deep Cleared 6/6/2022 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 6/6/2022 CALOSHA APPROVED
GPI Written Notices Cleared 6/6/2022 ZAW HAN
Grading Pre-Inspection Cleared 6/6/2022 ZAW HAN
Green Code Cleared 6/6/2022 ZAW HAN
Building over 36-ft Cleared 10/14/2022 CALOSHA APPROVED
Building over 36-ft Cleared 10/14/2022 CALOSHA APPROVED

Contact Information

Architect Avanesian,, Haroot; Lic. No.: C23194 6845 PARSONS TRAIL      TUJUNGA, CA 91042
Contractor Owner-Builder       ,
Engineer Behshid,, Farshid; Lic. No.: S4585 4647 ENCINAS DR      LA CANADA, CA 91011
Engineer Hennon,, Robert David; Lic. No.: L5573 601 E GLENOAKS BLVD 208      GLENDALE, CA 91207

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/4/2023 Partial Inspection AMY COLIN
Piling/Pier/Caisson 5/4/2023 Partial Inspection AMY COLIN
Pre-Inspection 5/4/2023 Partial Inspection AMY COLIN
Deputy Reinf. Concrete 5/18/2023 No Access for Inspection AMY COLIN
Excavation/Setback/Form/Re-Bar 5/18/2023 Partial Approval AMY COLIN
Piling/Pier/Caisson 5/18/2023 Partial Approval AMY COLIN
Deputy Reinf. Concrete 5/31/2023 Conditional Approval AMY COLIN
Excavation/Setback/Form/Re-Bar 8/15/2023 Conditional Approval AMY COLIN
Footing/Foundation/Slab 8/15/2023 Conditional Approval AMY COLIN
Deputy Reinf. Concrete 8/17/2023 Approved AMY COLIN
Excavation/Setback/Form/Re-Bar 9/5/2023 Corrections Issued AMY COLIN
Footing/Foundation/Slab 9/5/2023 Conditional Approval AMY COLIN
Deputy Reinf. Concrete 9/8/2023 Conditional Approval AMY COLIN
Excavation/Setback/Form/Re-Bar 10/20/2023 Approved ROY SPAULDING
Deputy Shotcrete 10/25/2023 Conditional Approval AMY COLIN
Excavation/Setback/Form/Re-Bar 12/21/2023 Approved AMY COLIN
Footing/Foundation/Slab 12/21/2023 Approved AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 1/19/2024 Partial Approval AMY COLIN
Deputy Wood Construction 3/5/2024 Conditional Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 3/8/2024 Partial Approval LILIANA PORTILLO
Verify Sprinkler Sign Off 3/8/2024 Not Ready for Inspection LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 3/28/2024 Corrections Issued JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 4/8/2024 Corrections Issued LILIANA PORTILLO
Pre-Inspection 4/8/2024 Partial Inspection LILIANA PORTILLO
PLUMBING-Rough 4/19/2024 Not Ready for Inspection LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 7/9/2024 Approved LILIANA PORTILLO
PLUMBING-Rough 7/9/2024 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 8/9/2024 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Rough 8/9/2024 Corrections Issued LILIANA PORTILLO
HVAC-Rough 8/9/2024 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Rough 8/9/2024 Approved LILIANA PORTILLO
Verify Sprinkler Sign Off 8/9/2024 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 8/15/2024 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 8/15/2024 Approved LILIANA PORTILLO
HVAC-Rough 8/15/2024 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 8/20/2024 Conditional Approval LILIANA PORTILLO
Green Building Rough 8/20/2024 Approved LILIANA PORTILLO
HVAC-Rough 8/20/2024 Conditional Approval LILIANA PORTILLO
BUILDING-Rough-Frame 8/26/2024 Approved LILIANA PORTILLO
Green Building Rough 8/26/2024 Approved LILIANA PORTILLO
Insulation 8/26/2024 Approved LILIANA PORTILLO
Drywall Nailing 9/4/2024 Approved ANTHONY RAMOS
Shower Pan 9/9/2024 Approved LILIANA PORTILLO
HVAC-Rough 9/11/2024 Approved LILIANA PORTILLO
Interior/Exterior Lathing 9/11/2024 Approved LILIANA PORTILLO
Pre-Inspection 6/18/2025 Partial Inspection LILIANA PORTILLO
Sewer 6/18/2025 Not Ready for Inspection LILIANA PORTILLO
Sewer 7/1/2025 Approved LILIANA PORTILLO
ELECTRICAL-Final 8/7/2025 No Access for Inspection ALIZAH MAYAGOITIA
Service/Power Release 8/7/2025 No Access for Inspection ALIZAH MAYAGOITIA
ELECTRICAL-Final 8/12/2025 Corrections Issued LILIANA PORTILLO
Service/Power Release 8/12/2025 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Final 8/18/2025 Corrections Issued BRENDAN MORELLI
ELECTRICAL-Final 8/20/2025 Approved LILIANA PORTILLO
Gas Test 8/29/2025 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Final 8/29/2025 Not Ready for Inspection LILIANA PORTILLO
Service/Power Release 8/29/2025 Approved LILIANA PORTILLO
Gas Test 9/16/2025 Approved LILIANA PORTILLO
Pre-Inspection 12/2/2025 Partial Inspection LILIANA PORTILLO
Final 4/15/2026 Corrections Issued LILIANA PORTILLO
Green Building Final 4/15/2026 Not Ready for Inspection LILIANA PORTILLO
Reinforced Concrete Frame 4/15/2026 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 4/15/2026 SGSOV Approved LILIANA PORTILLO
Smoke Detectors 4/15/2026 Approved LILIANA PORTILLO
Final 5/26/2026 Corrections Issued LILIANA PORTILLO
Green Building Final 5/26/2026 Approved LILIANA PORTILLO
Final 6/2/2026 Conditional Approval OSVALDO PARAMO
ELECTRICAL-Final 6/4/2026 Approved LILIANA PORTILLO
Final 6/4/2026 OK to Issue CofO LILIANA PORTILLO
HVAC-Final 6/4/2026 Approved LILIANA PORTILLO
PLUMBING-Final 6/4/2026 Approved LILIANA PORTILLO