1200 W LEIGHTON AVE 90037
Certificate Information: 1200 W LEIGHTON AVE 90037
- Application / Permit
- 20010-10000-04796
- Plan Check / Job No.
- B20LA23036
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 3 STORY SFD (FRONT, 4 HABITABLE ROOMS ONLY)
- Permit Issued
- Issued on 1/10/2022
- Issuing Office
- Current Status
- CofO Issued on 7/8/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/14/2021 | STARR CHEN |
| Corrections Issued | 1/17/2021 | STARR CHEN |
| Quality Review Completed | 1/29/2021 | ALLEN MANALANSAN |
| Building Plans Picked Up | 2/2/2021 | APPLICANT |
| Applicant returned to address corrections | 10/28/2021 | STARR CHEN |
| Applicant returned to address corrections | 10/29/2021 | STARR CHEN |
| Applicant returned to address corrections | 11/18/2021 | STARR CHEN |
| Plan Check Approved | 12/9/2021 | STARR CHEN |
| Issued | 1/10/2022 | APPLICANT |
| CofO in Progress | 6/23/2023 | SABAS ALONSO |
| Permit Finaled | 7/8/2023 | DEROLD HAUFF |
| CofO Issued | 7/8/2023 | DEROLD HAUFF |
| Permit Finaled | 7/8/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Hold | Cleared | 1/14/2021 | JASON SHEETS |
| Address approval | Cleared | 2/24/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 2/25/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 3/11/2021 | CECILIO NAVARRO |
| Hydrant and Access approval | Cleared | 4/24/2021 | MATTHEW CRAIG |
| Permit | Cleared | 5/19/2021 | CECILIO NAVARRO |
| Low Impact Development | Cleared | 7/4/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 7/7/2021 | CECILIO NAVARRO |
| Trees in Parkway | Cleared | 10/6/2021 | ADALBERTO VERA |
| Miscellaneous | Cleared | 10/15/2021 | JASON CHAN |
| Hold | Cleared | 1/20/2022 | JASON SHEETS |
Contact Information
| Contractor | Emerald Builders And Developers; Lic. No.: 1068007-B | 1412 W 22ND STREET LOS ANGELES, CA 90007 |
| Engineer | Elia,, Victor Anthony; Lic. No.: C64803 | 40912 CARLENA LN TEMECULA, CA 92591 |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 2543 E NORMAN AVE WEST COVINA, CA 91791 |
| Landscape Architect | Lee,, Cynthia; Lic. No.: LA2524 | 2029 VERDUGO BLVD STE 1020 MONTROSE, CA 91020 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 2/15/2022 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 2/25/2022 | Approved | HORACE FULTZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/22/2022 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 4/6/2022 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 6/7/2022 | Approved | SABAS ALONSO |
| HVAC-Rough | 6/7/2022 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Rough | 6/7/2022 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 6/17/2022 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Rough | 6/17/2022 | Approved | SABAS ALONSO |
| HVAC-Rough | 6/17/2022 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 6/29/2022 | Approved | SABAS ALONSO |
| Green Building Rough | 6/29/2022 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 6/29/2022 | Approved | SABAS ALONSO |
| Verify Sprinkler Sign Off | 6/29/2022 | Approved | SABAS ALONSO |
| Insulation | 7/6/2022 | Approved | SABAS ALONSO |
| Drywall Nailing | 7/18/2022 | Approved | SABAS ALONSO |
| Final | 3/9/2023 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 3/9/2023 | Corrections Issued | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 3/9/2023 | SGSOV Approved | SABAS ALONSO |
| Smoke Detectors | 3/9/2023 | Approved | SABAS ALONSO |
| Final | 4/12/2023 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 4/12/2023 | Approved | SABAS ALONSO |
| Service/Power Release | 4/12/2023 | Not Required | SABAS ALONSO |
| Final | 5/18/2023 | Corrections Issued | SABAS ALONSO |
| Final | 6/12/2023 | Corrections Issued | SABAS ALONSO |
| Final | 6/22/2023 | OK to Issue CofO | SABAS ALONSO |