1302 W O'FARRELL ST 90732

Certificate Information: 1302 W O'FARRELL ST 90732

Application / Permit
20010-10000-04785
Plan Check / Job No.
B20LA22992
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ONE STORY ADU PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 4/9/2024
Issuing Office
South Los Angeles
Current Status
Issued on 4/9/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/23/2020 APPLICANT
Assigned to Plan Check Engineer 12/30/2020 SERGIO GUTIERREZ
Corrections Issued 1/5/2021 SERGIO GUTIERREZ
Quality Review Completed 1/13/2021 KESETE HAREGOT
Building Plans Picked Up 1/19/2021 APPLICANT
Plan Check Approved 3/12/2024 SERGIO GUTIERREZ
Issued 4/9/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 2/19/2021 CHINH DINH
Eng Process Fee Ord 176,300 Cleared 4/5/2021 CHINH DINH
Sewer availability Cleared 4/5/2021 CHINH DINH
Hydrant and Access approval Cleared 1/24/2023 KURT CORRAL
Low Impact Development Cleared 3/1/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 3/7/2023 ERIK BEASLEY
GPI Written Notices Cleared 7/20/2023 SERGIO GUTIERREZ
Grading Pre-Inspection Cleared 7/20/2023 SERGIO GUTIERREZ

Contact Information

Contractor Alta California Construction Corp; Lic. No.: 1106881-B 749 W 98TH ST      LOS ANGELES, CA 90044
Engineer Ramirez, Cid, Jose Carlos; Lic. No.: C91046 5164 N RATON CIR      LONG BEACH, CA 90807
Engineer Singer,, Joanne Chapin; Lic. No.: C26900 40530 KINSALE PL      INDIO, CA 92203

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/14/2024 Approved EUGENE CASSIDY
Deputy Grading 5/22/2024 Conditional Approval ANSON MAGLASANG
Excavation/Setback/Form/Re-Bar 5/23/2024 Not Ready for Inspection EUGENE CASSIDY
Pre-Inspection 5/23/2024 Approved EUGENE CASSIDY
Underground Mechanical 6/3/2024 Approved EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 6/17/2024 Corrections Issued JAMES CHAVEZ
BUILDING-Rough-Frame 10/11/2024 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 10/11/2024 Approved EUGENE CASSIDY
Green Building Final 10/11/2024 Not Ready for Inspection EUGENE CASSIDY
Green Building Rough 10/11/2024 Approved EUGENE CASSIDY
HVAC-Rough 10/11/2024 Approved EUGENE CASSIDY
Interior/Exterior Lathing 10/11/2024 Partial Approval EUGENE CASSIDY
PLUMBING-Rough 10/11/2024 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 10/18/2024 Approved JOSEPH MCGARRY
Insulation 10/18/2024 Approved JOSEPH MCGARRY
Verify Sprinkler Sign Off 10/18/2024 Approved JOSEPH MCGARRY
Drywall Nailing 10/22/2024 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 11/19/2024 Approved JOSEPH MCGARRY
Shower Pan 11/19/2024 Approved JOSEPH MCGARRY
ELECTRICAL-Final 12/27/2024 Corrections Issued JOSEPH MCGARRY
Final 12/27/2024 Corrections Issued JOSEPH MCGARRY
Footing/Foundation/Slab 12/27/2024 Approved JOSEPH MCGARRY
Green Building Final 12/27/2024 Approved JOSEPH MCGARRY
HVAC-Final 12/27/2024 Approved JOSEPH MCGARRY
PLUMBING-Final 12/27/2024 Corrections Issued JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 12/27/2024 SGSOV Approved JOSEPH MCGARRY
Service/Power Release 12/27/2024 Not Required JOSEPH MCGARRY
Smoke Detectors 12/27/2024 Approved JOSEPH MCGARRY
Final 1/2/2025 Not Ready for Inspection JOSEPH MCGARRY