1302 W O'FARRELL ST 90732
Certificate Information: 1302 W O'FARRELL ST 90732
- Application / Permit
- 20010-10000-04785
- Plan Check / Job No.
- B20LA22992
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ONE STORY ADU PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 4/9/2024
- Issuing Office
- South Los Angeles
- Current Status
- Issued on 4/9/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/23/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/30/2020 | SERGIO GUTIERREZ |
| Corrections Issued | 1/5/2021 | SERGIO GUTIERREZ |
| Quality Review Completed | 1/13/2021 | KESETE HAREGOT |
| Building Plans Picked Up | 1/19/2021 | APPLICANT |
| Plan Check Approved | 3/12/2024 | SERGIO GUTIERREZ |
| Issued | 4/9/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 2/19/2021 | CHINH DINH |
| Eng Process Fee Ord 176,300 | Cleared | 4/5/2021 | CHINH DINH |
| Sewer availability | Cleared | 4/5/2021 | CHINH DINH |
| Hydrant and Access approval | Cleared | 1/24/2023 | KURT CORRAL |
| Low Impact Development | Cleared | 3/1/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 3/7/2023 | ERIK BEASLEY |
| GPI Written Notices | Cleared | 7/20/2023 | SERGIO GUTIERREZ |
| Grading Pre-Inspection | Cleared | 7/20/2023 | SERGIO GUTIERREZ |
Contact Information
| Contractor | Alta California Construction Corp; Lic. No.: 1106881-B | 749 W 98TH ST LOS ANGELES, CA 90044 |
| Engineer | Ramirez, Cid, Jose Carlos; Lic. No.: C91046 | 5164 N RATON CIR LONG BEACH, CA 90807 |
| Engineer | Singer,, Joanne Chapin; Lic. No.: C26900 | 40530 KINSALE PL INDIO, CA 92203 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/14/2024 | Approved | EUGENE CASSIDY |
| Deputy Grading | 5/22/2024 | Conditional Approval | ANSON MAGLASANG |
| Excavation/Setback/Form/Re-Bar | 5/23/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| Pre-Inspection | 5/23/2024 | Approved | EUGENE CASSIDY |
| Underground Mechanical | 6/3/2024 | Approved | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 6/17/2024 | Corrections Issued | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 10/11/2024 | Partial Approval | EUGENE CASSIDY |
| ELECTRICAL-Rough | 10/11/2024 | Approved | EUGENE CASSIDY |
| Green Building Final | 10/11/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Rough | 10/11/2024 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 10/11/2024 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 10/11/2024 | Partial Approval | EUGENE CASSIDY |
| PLUMBING-Rough | 10/11/2024 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 10/18/2024 | Approved | JOSEPH MCGARRY |
| Insulation | 10/18/2024 | Approved | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 10/18/2024 | Approved | JOSEPH MCGARRY |
| Drywall Nailing | 10/22/2024 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 11/19/2024 | Approved | JOSEPH MCGARRY |
| Shower Pan | 11/19/2024 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Final | 12/27/2024 | Corrections Issued | JOSEPH MCGARRY |
| Final | 12/27/2024 | Corrections Issued | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 12/27/2024 | Approved | JOSEPH MCGARRY |
| Green Building Final | 12/27/2024 | Approved | JOSEPH MCGARRY |
| HVAC-Final | 12/27/2024 | Approved | JOSEPH MCGARRY |
| PLUMBING-Final | 12/27/2024 | Corrections Issued | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 12/27/2024 | SGSOV Approved | JOSEPH MCGARRY |
| Service/Power Release | 12/27/2024 | Not Required | JOSEPH MCGARRY |
| Smoke Detectors | 12/27/2024 | Approved | JOSEPH MCGARRY |
| Final | 1/2/2025 | Not Ready for Inspection | JOSEPH MCGARRY |