352-352 1/2 N BREED ST 90033

Certificate Information: 352-352 1/2 N BREED ST 90033

Application / Permit
20010-10000-04779
Plan Check / Job No.
B20LA22969
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 3 STORY DUPLEX BUILDING B (MIDDLE)
Permit Issued
Issued on 4/20/2022
Issuing Office
Current Status
CofO Issued on 10/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/15/2020 APPLICANT
Assigned to Plan Check Engineer 1/14/2021 CARLOS MONTES
Corrections Issued 1/21/2021 CARLOS MONTES
Quality Review Completed 2/5/2021 TU HUA
Applicant returned to address corrections 9/8/2021 CARLOS MONTES
Plan Check Approved 3/25/2022 CARLOS MONTES
Issued 4/20/2022 APPLICANT
Building Plans Picked Up 5/3/2022 APPLICANT
CofO in Progress 8/20/2024 OSVALDO PARAMO
Permit Finaled 10/1/2024 RUBEN SALAS
CofO Issued 10/1/2024 RUBEN SALAS
Permit Finaled 10/1/2024 RUBEN SALAS

Permit Application Clearance Information

Highway dedication Cleared 2/19/2021 CELINA MORENO
Address approval Cleared 2/24/2021 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 2/24/2021 RENZ SORIANO
Permit Cleared 2/25/2021 RENZ SORIANO
Sewer availability Cleared 2/25/2021 RENZ SORIANO
Hydrant and Access approval Cleared 3/11/2021 MATTHEW CRAIG
Trees in Parkway Cleared 3/31/2021 JOHN KIM
Clean Up Green Up Cleared 5/27/2021 RICHARD REASER
ZA Case Cleared 5/27/2021 RICHARD REASER
Frnt yard landscape/Water mgmt Cleared 7/8/2021 TERRI OSBORNE
Low Impact Development Cleared 12/12/2021 TA ANH
Roof/Waste drainage to street Cleared 1/11/2022 TREVOR QUAN
GPI Written Notices Cleared 3/25/2022 CARLOS MONTES
Grading Pre-Inspection Cleared 3/25/2022 CARLOS MONTES

Contact Information

Architect Feagins,, Larry; Lic. No.: C27009 669 N THIRD AVENUE      UPLAND, CA 91786
Contractor Rs Builders Inc; Lic. No.: 1062718-B 325 NORTH 2ND AVENUE SUITE B      UPLAND, CA 91786
Engineer Kaligi,, Sean; Lic. No.: M37797 655 N CENTRAL AVE 17TH FL      GLENDALE, CA 91203
Engineer Pinzon,, Eduardo A; Lic. No.: C74869 821 W SPRUCE ST      WEST COVINA, CA 91790
Geologist , ; Lic. No.: EG2781       ,

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/12/2022 Not Ready for Inspection OSVALDO PARAMO
Underground Mechanical 11/9/2022 No Access for Inspection OSVALDO PARAMO
PLUMBING-Rough 12/9/2022 Partial Approval OSVALDO PARAMO
Pre-Inspection 2/8/2023 Corrections Issued OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 3/3/2023 Corrections Issued OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 4/4/2023 Partial Approval OSVALDO PARAMO
PLUMBING-Rough 4/4/2023 Partial Approval OSVALDO PARAMO
METHANE-Rough 4/13/2023 Not Ready for Inspection OSVALDO PARAMO
METHANE-Rough 4/17/2023 Corrections Issued JOSEPH MCGARRY
Excavation/Setback/Form/Re-Bar 4/18/2023 Partial Inspection OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 4/19/2023 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 4/19/2023 Partial Approval OSVALDO PARAMO
Deputy Reinf. Concrete 4/21/2023 Conditional Approval OSVALDO PARAMO
Deputy Reinf. Concrete 4/24/2023 Conditional Approval RUBEN SALAS
Deputy Reinf. Concrete 4/25/2023 Conditional Approval OSVALDO PARAMO
Deputy Reinf. Concrete 4/26/2023 Conditional Approval OSVALDO PARAMO
Deputy Steel/Welding 4/28/2023 Conditional Approval OSVALDO PARAMO
Deputy Steel/Welding 5/1/2023 Conditional Approval OSVALDO PARAMO
Deputy Steel/Welding 5/3/2023 Conditional Approval OSVALDO PARAMO
Deputy Drilled-In Anchors 5/8/2023 Conditional Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 5/8/2023 Not Ready for Inspection OSVALDO PARAMO
Deputy Reinf. Concrete 5/9/2023 Conditional Approval OSVALDO PARAMO
METHANE-Subgrade 5/15/2023 Partial Approval OSVALDO PARAMO
Deputy Reinf. Concrete 5/16/2023 Conditional Approval OSVALDO PARAMO
Deputy Methane Barrier 5/19/2023 Conditional Approval OSVALDO PARAMO
Footing/Foundation/Slab 5/22/2023 Partial Approval OSVALDO PARAMO
METHANE-Barrier 5/22/2023 Approved OSVALDO PARAMO
METHANE-Subgrade 5/22/2023 Approved OSVALDO PARAMO
Deputy Reinf. Concrete 5/23/2023 Conditional Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 6/15/2023 Partial Approval RUBEN SALAS
Floor/Roof Diaphrgm/Shear Wall 6/21/2023 Not Ready for Inspection OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 6/29/2023 Partial Approval OSVALDO PARAMO
Deputy Wood Construction 7/18/2023 Conditional Approval OSVALDO PARAMO
ELECTRICAL-Rough 8/8/2023 Partial Approval OSVALDO PARAMO
METHANE-Rough 8/8/2023 Approved OSVALDO PARAMO
PLUMBING-Rough 8/8/2023 Not Ready for Inspection OSVALDO PARAMO
PLUMBING-Rough 8/14/2023 Corrections Issued ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 8/24/2023 Conditional Approval OSVALDO PARAMO
ELECTRICAL-Rough 9/6/2023 Not Ready for Inspection OSVALDO PARAMO
HVAC-Rough 9/6/2023 Not Ready for Inspection OSVALDO PARAMO
PLUMBING-Rough 9/6/2023 Approved OSVALDO PARAMO
ELECTRICAL-Rough 9/14/2023 Approved OSVALDO PARAMO
HVAC-Rough 9/14/2023 Corrections Issued OSVALDO PARAMO
HVAC-Rough 9/21/2023 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 9/27/2023 Corrections Issued OSVALDO PARAMO
Green Building Rough 9/27/2023 Approved OSVALDO PARAMO
Verify Sprinkler Sign Off 9/27/2023 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 10/2/2023 Approved OSVALDO PARAMO
Shower Pan 10/5/2023 Approved JOSH MEISTER
Interior/Exterior Lathing 10/6/2023 Partial Approval OSVALDO PARAMO
Insulation 10/16/2023 Approved OSVALDO PARAMO
Drywall Nailing 11/1/2023 Not Ready for Inspection OSVALDO PARAMO
Drywall Nailing 11/3/2023 Approved OSVALDO PARAMO
Interior/Exterior Lathing 11/3/2023 Not Ready for Inspection OSVALDO PARAMO
Interior/Exterior Lathing 11/9/2023 Approved OSVALDO PARAMO
Shower Pan 11/9/2023 Approved OSVALDO PARAMO
Sewer 12/19/2023 Approved OSVALDO PARAMO
Underground Mechanical 12/19/2023 Approved OSVALDO PARAMO
Underground Mechanical 1/5/2024 Not Ready for Inspection OSVALDO PARAMO
ELECTRICAL-Final 1/16/2024 Corrections Issued OSVALDO PARAMO
ELECTRICAL-Final 2/7/2024 Corrections Issued OSVALDO PARAMO
Gas Test 2/14/2024 Not Ready for Inspection OSVALDO PARAMO
PLUMBING-Final 2/14/2024 Not Ready for Inspection OSVALDO PARAMO
Gas Test 2/23/2024 Approved OSVALDO PARAMO
PLUMBING-Final 2/23/2024 Partial Inspection OSVALDO PARAMO
Gas Test 3/1/2024 Approved OSVALDO PARAMO
PLUMBING-Final 3/1/2024 Approved OSVALDO PARAMO
HVAC-Final 3/7/2024 Approved OSVALDO PARAMO
ELECTRICAL-Final 6/18/2024 Partial Inspection OSVALDO PARAMO
ELECTRICAL-Final 6/25/2024 Partial Inspection OSVALDO PARAMO
ELECTRICAL-Final 7/1/2024 Approved OSVALDO PARAMO
Service/Power Release 7/1/2024 Approved OSVALDO PARAMO
Final 8/16/2024 OK to Issue CofO OSVALDO PARAMO
Footing/Foundation/Slab 8/16/2024 Approved OSVALDO PARAMO
Green Building Final 8/16/2024 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 8/16/2024 SGSOV Approved OSVALDO PARAMO
Smoke Detectors 8/16/2024 Approved OSVALDO PARAMO