10600 S JUNIPER ST 90002
Certificate Information: 10600 S JUNIPER ST 90002
- Application / Permit
- 20010-10000-04776
- Plan Check / Job No.
- B20LA22963
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 1-STORY SINGLE FAMILY DWELLING with ATTACHED 2 CAR GARAGE
- Permit Issued
- Issued on 11/23/2021
- Issuing Office
- Current Status
- CofO Issued on 12/29/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/23/2020 | LARRY LEE |
| Corrections Issued | 12/31/2020 | LARRY LEE |
| Quality Review Completed | 1/6/2021 | SAI KHUM |
| Plan Check Approved | 11/10/2021 | LARRY LEE |
| Issued | 11/23/2021 | APPLICANT |
| Building Plans Picked Up | 12/1/2021 | APPLICANT |
| CofO in Progress | 12/29/2022 | JOHN KLARIN |
| CofO in Progress | 12/29/2022 | JOHN KLARIN |
| CofO Issued | 12/29/2022 | ANSON MAGLASANG |
| Permit Finaled | 12/29/2022 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 3/10/2021 | WALLIE JONG |
| Permit | Cleared | 3/10/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 3/11/2021 | WALLIE JONG |
| Sewer availability | Cleared | 3/11/2021 | WALLIE JONG |
| Low Impact Development | Cleared | 8/3/2021 | JORGE MEJIA LEMUS |
| Hydrant and Access approval | Cleared | 9/8/2021 | KURT CORRAL |
| Roof/Waste drainage to street | Cleared | 9/22/2021 | WALLIE JONG |
Contact Information
| Contractor | Ebenezer Construction; Lic. No.: 657529-B | 9214 MANZANAR AVE DOWNEY, CA 90240 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/21/2021 | Partial Approval | EUGENE CASSIDY |
| Footing/Foundation/Slab | 12/21/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Rough | 12/21/2021 | Partial Approval | EUGENE CASSIDY |
| Footing/Foundation/Slab | 1/12/2022 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 3/2/2022 | Approved | JOHN KLARIN |
| Sewer | 3/16/2022 | Approved | JOHN KLARIN |
| Rough-Elec/Plmb/HVAC | 3/29/2022 | Approved | JOHN KLARIN |
| Insulation | 4/12/2022 | Approved | JOHN KLARIN |
| Drywall Nailing | 4/28/2022 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 4/28/2022 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 7/13/2022 | Approved | JOHN KLARIN |
| Final | 7/13/2022 | Conditional Approval | JOHN KLARIN |
| Green Building Final | 7/13/2022 | Approved | JOHN KLARIN |
| Green Building Rough | 7/13/2022 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 7/13/2022 | SGSOV Approved | JOHN KLARIN |
| Service/Power Release | 7/13/2022 | Approved | JOHN KLARIN |
| Smoke Detectors | 7/13/2022 | Approved | JOHN KLARIN |
| Verify Sprinkler Sign Off | 7/13/2022 | Approved | JOHN KLARIN |
| Final | 8/8/2022 | Not Ready for Inspection | JOHN KLARIN |
| Final | 12/29/2022 | OK to Issue CofO | JOHN KLARIN |