10528 S JUNIPER ST 90002

Certificate Information: 10528 S JUNIPER ST 90002

Application / Permit
20010-10000-04773
Plan Check / Job No.
B20LA22956
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 1 STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE
Permit Issued
Issued on 10/21/2021
Issuing Office
Current Status
CofO Issued on 6/22/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/11/2020 APPLICANT
Assigned to Plan Check Engineer 12/23/2020 STARR CHEN
Corrections Issued 12/27/2020 STARR CHEN
Building Plans Picked Up 2/19/2021 APPLICANT
Quality Review Completed 7/23/2021 ALLEN MANALANSAN
Plan Check Approved 10/1/2021 STARR CHEN
Issued 10/21/2021 APPLICANT
CofO in Progress 6/21/2022 JOHN KLARIN
CofO Issued 6/22/2022 DEROLD HAUFF
Permit Finaled 6/22/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/10/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 3/11/2021 WALLIE JONG
Sewer availability Cleared 3/11/2021 WALLIE JONG
Low Impact Development Cleared 6/29/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 8/4/2021 RENZ SORIANO
Hydrant and Access approval Cleared 9/8/2021 RUEL COLE

Contact Information

Contractor Ebenezer Construction; Lic. No.: 657529-B 9214 MANZANAR AVE      DOWNEY, CA 90240
Engineer Dorta,, Michael Rohrs; Lic. No.: C72538 2445 VIA SONOMA      PALOS VERDES ESTATES, CA 90274

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/3/2021 Partial Approval EUGENE CASSIDY
Footing/Foundation/Slab 11/3/2021 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 11/3/2021 Partial Approval EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 11/10/2021 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 1/4/2022 Partial Approval EUGENE CASSIDY
Interior/Exterior Lathing 1/4/2022 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 1/24/2022 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Rough 1/24/2022 Approved ALIZAH MAYAGOITIA
Green Building Rough 1/24/2022 Approved ALIZAH MAYAGOITIA
HVAC-Rough 1/24/2022 Corrections Issued ALIZAH MAYAGOITIA
Interior/Exterior Lathing 1/24/2022 Partial Approval ALIZAH MAYAGOITIA
PLUMBING-Final 1/24/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Rough 1/24/2022 Approved ALIZAH MAYAGOITIA
Verify Sprinkler Sign Off 1/24/2022 Approved ALIZAH MAYAGOITIA
Insulation 2/4/2022 Approved ANSON MAGLASANG
Drywall Nailing 2/10/2022 Approved JOHN KLARIN
Interior/Exterior Lathing 2/10/2022 Approved JOHN KLARIN
Sewer 3/16/2022 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 4/25/2022 SGSOV Not Ready JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 5/18/2022 SGSOV Not Ready ALIZAH MAYAGOITIA
Final 5/24/2022 Corrections Issued ALIZAH MAYAGOITIA
Footing/Foundation/Slab 5/24/2022 Approved ALIZAH MAYAGOITIA
Green Building Final 5/24/2022 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 5/24/2022 SGSOV Approved ALIZAH MAYAGOITIA
Service/Power Release 5/24/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Smoke Detectors 5/24/2022 Approved ALIZAH MAYAGOITIA
Final 6/1/2022 Not Ready for Inspection JOHN KLARIN
Service/Power Release 6/1/2022 Approved JOHN KLARIN
ELECTRICAL-Final 6/17/2022 Approved JOHN KLARIN
Final 6/17/2022 OK to Issue CofO JOHN KLARIN
HVAC-Final 6/17/2022 Approved JOHN KLARIN
PLUMBING-Final 6/17/2022 Approved JOHN KLARIN