833 W 104TH PL 90044
Certificate Information: 833 W 104TH PL 90044
- Application / Permit
- 20010-10000-04766
- Plan Check / Job No.
- B20LA22917
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ADU ON TOP OF 2-CAR GARAGE W/ LAUNDRY, PER LAMCE 12.22A.33 (c)-(d)
- Permit Issued
- Issued on 1/24/2022
- Issuing Office
- Current Status
- CofO Issued on 8/22/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/11/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/14/2021 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 2/2/2021 | TIEN JEN WANG |
| Corrections Issued | 2/3/2021 | MAHNAZ NOURHASHEMI |
| Building Plans Picked Up | 2/9/2021 | APPLICANT |
| Quality Review Completed | 2/18/2021 | JASON HEALEY |
| Applicant returned to address corrections | 8/13/2021 | MAHNAZ NOURHASHEMI |
| Applicant returned to address corrections | 9/20/2021 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 1/24/2022 | MAHNAZ NOURHASHEMI |
| Issued | 1/24/2022 | APPLICANT |
| CofO in Progress | 8/21/2023 | JAMES CHAVEZ |
| Permit Finaled | 8/22/2023 | ANSON MAGLASANG |
| CofO Issued | 8/22/2023 | ANSON MAGLASANG |
| Permit Finaled | 8/22/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 3/4/2021 | THOMAS LANG |
| Low Impact Development | Cleared | 8/4/2021 | SARAH YOUSSEF |
| Eng Process Fee Ord 176,300 | Cleared | 10/1/2021 | CECILIO NAVARRO |
| Roof/Waste drainage to street | Cleared | 10/19/2021 | CECILIO NAVARRO |
| Permit | Cleared | 11/3/2021 | JEANETTE VONG |
| Sewer availability | Cleared | 11/3/2021 | JEANETTE VONG |
| Hydrant and Access approval | Cleared | 12/19/2021 | ROBERT DUFF |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Dia,, Gil Aroja; Lic. No.: C26172 | 532 E 222ND STREET CARSON, CA 90745 |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/29/2022 | Corrections Issued | JOHN KLARIN |
| Excavation/Setback/Form/Re-Bar | 4/8/2022 | Approved | JOHN KLARIN |
| Footing/Foundation/Slab | 4/8/2022 | Approved | JOHN KLARIN |
| Sewer | 4/8/2022 | Partial Approval | JOHN KLARIN |
| Deputy Wood Construction | 6/14/2022 | Conditional Approval | SHAVONNE ESPINOZA |
| Floor/Roof Diaphrgm/Shear Wall | 7/5/2022 | Partial Approval | JOHN KLARIN |
| BUILDING-Rough-Frame | 7/11/2022 | Partial Approval | ANSON MAGLASANG |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2022 | Partial Approval | ANSON MAGLASANG |
| Green Building Rough | 7/11/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| Verify Sprinkler Sign Off | 7/11/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| Interior/Exterior Lathing | 7/20/2022 | Approved | JOHN KLARIN |
| Insulation | 7/22/2022 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 7/26/2022 | Approved | JOHN KLARIN |
| ELECTRICAL-Rough | 7/26/2022 | Approved | JOHN KLARIN |
| Gas Test | 7/26/2022 | Approved | JOHN KLARIN |
| Green Building Rough | 7/26/2022 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 7/26/2022 | Approved | JOHN KLARIN |
| Verify Sprinkler Sign Off | 7/26/2022 | Approved | JOHN KLARIN |
| Wood Frame | 7/26/2022 | Approved | JOHN KLARIN |
| Drywall Nailing | 8/2/2022 | Approved | JOHN KLARIN |
| Final | 2/7/2023 | Corrections Issued | JAMES CHAVEZ |
| Green Building Final | 2/7/2023 | Corrections Issued | JAMES CHAVEZ |
| SGSOV-Seismic Gas S/O Valve | 2/7/2023 | SGSOV Not Ready | JAMES CHAVEZ |
| Service/Power Release | 2/7/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Smoke Detectors | 2/7/2023 | Approved | JAMES CHAVEZ |
| Final | 3/8/2023 | Corrections Issued | JAMES CHAVEZ |
| Green Building Final | 3/8/2023 | Approved | JAMES CHAVEZ |
| SGSOV-Seismic Gas S/O Valve | 3/8/2023 | SGSOV Approved | JAMES CHAVEZ |
| Service/Power Release | 3/8/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Final | 7/24/2023 | OK to Issue CofO | JAMES CHAVEZ |
| Service/Power Release | 7/24/2023 | Approved | JAMES CHAVEZ |