833 W 104TH PL 90044

Certificate Information: 833 W 104TH PL 90044

Application / Permit
20010-10000-04766
Plan Check / Job No.
B20LA22917
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW ADU ON TOP OF 2-CAR GARAGE W/ LAUNDRY, PER LAMCE 12.22A.33 (c)-(d)
Permit Issued
Issued on 1/24/2022
Issuing Office
Current Status
CofO Issued on 8/22/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/11/2020 APPLICANT
Assigned to Plan Check Engineer 1/14/2021 MAHNAZ NOURHASHEMI
Quality Review Completed 2/2/2021 TIEN JEN WANG
Corrections Issued 2/3/2021 MAHNAZ NOURHASHEMI
Building Plans Picked Up 2/9/2021 APPLICANT
Quality Review Completed 2/18/2021 JASON HEALEY
Applicant returned to address corrections 8/13/2021 MAHNAZ NOURHASHEMI
Applicant returned to address corrections 9/20/2021 MAHNAZ NOURHASHEMI
Plan Check Approved 1/24/2022 MAHNAZ NOURHASHEMI
Issued 1/24/2022 APPLICANT
CofO in Progress 8/21/2023 JAMES CHAVEZ
Permit Finaled 8/22/2023 ANSON MAGLASANG
CofO Issued 8/22/2023 ANSON MAGLASANG
Permit Finaled 8/22/2023 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 3/4/2021 THOMAS LANG
Low Impact Development Cleared 8/4/2021 SARAH YOUSSEF
Eng Process Fee Ord 176,300 Cleared 10/1/2021 CECILIO NAVARRO
Roof/Waste drainage to street Cleared 10/19/2021 CECILIO NAVARRO
Permit Cleared 11/3/2021 JEANETTE VONG
Sewer availability Cleared 11/3/2021 JEANETTE VONG
Hydrant and Access approval Cleared 12/19/2021 ROBERT DUFF

Contact Information

Contractor Owner-Builder       ,
Engineer Dia,, Gil Aroja; Lic. No.: C26172 532 E 222ND STREET      CARSON, CA 90745

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/29/2022 Corrections Issued JOHN KLARIN
Excavation/Setback/Form/Re-Bar 4/8/2022 Approved JOHN KLARIN
Footing/Foundation/Slab 4/8/2022 Approved JOHN KLARIN
Sewer 4/8/2022 Partial Approval JOHN KLARIN
Deputy Wood Construction 6/14/2022 Conditional Approval SHAVONNE ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 7/5/2022 Partial Approval JOHN KLARIN
BUILDING-Rough-Frame 7/11/2022 Partial Approval ANSON MAGLASANG
Floor/Roof Diaphrgm/Shear Wall 7/11/2022 Partial Approval ANSON MAGLASANG
Green Building Rough 7/11/2022 Not Ready for Inspection ANSON MAGLASANG
Verify Sprinkler Sign Off 7/11/2022 Not Ready for Inspection ANSON MAGLASANG
Interior/Exterior Lathing 7/20/2022 Approved JOHN KLARIN
Insulation 7/22/2022 Approved JOHN KLARIN
BUILDING-Rough-Frame 7/26/2022 Approved JOHN KLARIN
ELECTRICAL-Rough 7/26/2022 Approved JOHN KLARIN
Gas Test 7/26/2022 Approved JOHN KLARIN
Green Building Rough 7/26/2022 Approved JOHN KLARIN
PLUMBING-Rough 7/26/2022 Approved JOHN KLARIN
Verify Sprinkler Sign Off 7/26/2022 Approved JOHN KLARIN
Wood Frame 7/26/2022 Approved JOHN KLARIN
Drywall Nailing 8/2/2022 Approved JOHN KLARIN
Final 2/7/2023 Corrections Issued JAMES CHAVEZ
Green Building Final 2/7/2023 Corrections Issued JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 2/7/2023 SGSOV Not Ready JAMES CHAVEZ
Service/Power Release 2/7/2023 Not Ready for Inspection JAMES CHAVEZ
Smoke Detectors 2/7/2023 Approved JAMES CHAVEZ
Final 3/8/2023 Corrections Issued JAMES CHAVEZ
Green Building Final 3/8/2023 Approved JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 3/8/2023 SGSOV Approved JAMES CHAVEZ
Service/Power Release 3/8/2023 Not Ready for Inspection JAMES CHAVEZ
Final 7/24/2023 OK to Issue CofO JAMES CHAVEZ
Service/Power Release 7/24/2023 Approved JAMES CHAVEZ