847 W 123RD ST 90044
Certificate Information: 847 W 123RD ST 90044
- Application / Permit
- 20010-10000-04736
- Plan Check / Job No.
- B20LA22850
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED 1-STORY A.D.U. TOWARD REAR OF LOT PER LAMC 12.22 A.33(c) AND (d).
- Permit Issued
- Issued on 7/26/2021
- Issuing Office
- Current Status
- CofO Issued on 7/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/18/2020 | LAWRENCE QUIRANTE |
| Corrections Issued | 12/20/2020 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 6/28/2021 | CRISTINA SALAZAR |
| Applicant returned to address corrections | 7/16/2021 | ZAW HAN |
| Plan Check Approved | 7/21/2021 | ZAW HAN |
| Issued | 7/26/2021 | APPLICANT |
| Building Plans Picked Up | 8/5/2021 | APPLICANT |
| CofO in Progress | 6/6/2025 | BEN MOLSTAD |
| CofO in Progress | 6/9/2025 | ANSON MAGLASANG |
| No Progress | 6/9/2025 | ANSON MAGLASANG |
| CofO in Progress | 6/28/2025 | DAVID FEILER |
| Permit Finaled | 7/9/2025 | RICHARD STEINBACH |
| CofO Issued | 7/9/2025 | RICHARD STEINBACH |
| Permit Finaled | 7/9/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 12/31/2020 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 1/4/2021 | ERIK BEASLEY |
| Sewer availability | Cleared | 1/4/2021 | ERIK BEASLEY |
| Low Impact Development | Cleared | 6/16/2021 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 6/16/2021 | ERIK BEASLEY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Carrillo,, Jesus Eduardo; Lic. No.: C77737 | 8207 BROOKGREEN RD DOWNEY, CA 90240 |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/19/2021 | Corrections Issued | EUGENE CASSIDY |
| METHANE-Barrier | 8/19/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| METHANE-Subgrade | 8/19/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Footing/Foundation/Slab | 9/9/2021 | Corrections Issued | EUGENE CASSIDY |
| METHANE-Barrier | 9/9/2021 | Approved | EUGENE CASSIDY |
| METHANE-Subgrade | 9/9/2021 | Approved | EUGENE CASSIDY |
| Footing/Foundation/Slab | 9/22/2021 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 9/27/2021 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2021 | Corrections Issued | EUGENE CASSIDY |
| PLUMBING-Rough | 10/21/2021 | Partial Approval | EUGENE CASSIDY |
| Sewer | 10/21/2021 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 10/25/2021 | Partial Approval | EUGENE CASSIDY |
| Green Building Rough | 10/25/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| METHANE-Rough | 10/25/2021 | Approved | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 10/25/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Insulation | 10/28/2021 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 11/2/2021 | Partial Approval | ANSON MAGLASANG |
| Wood Frame | 1/10/2022 | Partial Approval | EUGENE CASSIDY |
| Rough-Elec/Plmb/HVAC | 3/23/2022 | Corrections Issued | JOHN KLARIN |
| BUILDING-Rough-Frame | 3/31/2022 | Approved | ALIZAH MAYAGOITIA |
| Green Building Rough | 3/31/2022 | Approved | ALIZAH MAYAGOITIA |
| Rough-Elec/Plmb/HVAC | 3/31/2022 | Approved | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 3/31/2022 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 4/5/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 4/5/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| Drywall Nailing | 4/22/2022 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 4/22/2022 | Approved | JOHN KLARIN |
| Final | 11/23/2022 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 11/23/2022 | Corrections Issued | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 11/23/2022 | SGSOV Approved | JOHN KLARIN |
| Service/Power Release | 11/23/2022 | Not Required | JOHN KLARIN |
| Smoke Detectors | 11/23/2022 | Approved | JOHN KLARIN |
| Final | 4/27/2023 | Corrections Issued | JAMES CHAVEZ |
| Green Building Final | 4/27/2023 | Corrections Issued | JAMES CHAVEZ |
| Final | 11/7/2024 | Corrections Issued | BEN MOLSTAD |
| Green Building Final | 11/7/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Final | 12/31/2024 | Corrections Issued | BEN MOLSTAD |
| Green Building Final | 12/31/2024 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Final | 6/6/2025 | Approved | BEN MOLSTAD |
| Final | 6/6/2025 | OK to Issue CofO | BEN MOLSTAD |
| Green Building Final | 6/6/2025 | Approved | BEN MOLSTAD |
| HVAC-Final | 6/6/2025 | Approved | BEN MOLSTAD |
| PLUMBING-Final | 6/6/2025 | Approved | BEN MOLSTAD |
| Special/Order Compliance | 6/10/2025 | Corrections Issued | BEN MOLSTAD |
| Final | 6/28/2025 | OK to Issue CofO | DAVID FEILER |