4224 S DALTON AVE 90062

Certificate Information: 4224 S DALTON AVE 90062

Application / Permit
20010-10000-04719
Plan Check / Job No.
B20LA22760
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 3-STORY SFD WITH ATTACHED 2 CAR GARAGE AT REAR OF THE LOT.
Permit Issued
Issued on 12/8/2021
Issuing Office
Current Status
CofO Issued on 5/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/9/2020 APPLICANT
Assigned to Plan Check Engineer 1/13/2021 ZAW HAN
Corrections Issued 1/21/2021 ZAW HAN
Quality Review Completed 2/3/2021 GARO TELMI
Applicant returned to address corrections 5/27/2021 ZAW HAN
Plan Check Approved 7/14/2021 ZAW HAN
Issued 12/8/2021 APPLICANT
Building Plans Picked Up 12/17/2021 APPLICANT
CofO in Progress 4/25/2023 SABAS ALONSO
Permit Finaled 5/6/2023 DEROLD HAUFF
CofO Issued 5/6/2023 DEROLD HAUFF
Permit Finaled 5/6/2023 DEROLD HAUFF

Permit Application Clearance Information

Highway dedication Cleared 2/23/2021 JUAN ASHTON
Eng Process Fee Ord 176,300 Cleared 2/24/2021 JUAN ASHTON
Address approval Cleared 3/1/2021 JUAN ASHTON
Address approval Cleared 3/1/2021 JUAN ASHTON
Hydrant and Access approval Cleared 3/22/2021 MATTHEW CRAIG
Permit Cleared 4/5/2021 JUAN ASHTON
Frnt yard landscape/Water mgmt Cleared 4/8/2021 RICHARD REASER
Sewer availability Cleared 4/26/2021 JUAN ASHTON
Low Impact Development Cleared 5/9/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 5/12/2021 THAN WIN

Contact Information

Contractor Emerald Builders And Developers; Lic. No.: 1068007-B 1412 W 22ND STREET      LOS ANGELES, CA 90007
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 2/8/2022 Partial Approval SABAS ALONSO
Footing/Foundation/Slab 2/14/2022 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 2/28/2022 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 3/11/2022 Partial Approval SABAS ALONSO
ELECTRICAL-Rough 4/14/2022 Approved SABAS ALONSO
PLUMBING-Rough 4/14/2022 Conditional Approval SABAS ALONSO
Deputy Wood Construction 4/28/2022 Conditional Approval SABAS ALONSO
BUILDING-Rough-Frame 4/29/2022 Not Ready for Inspection SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 4/29/2022 Approved SABAS ALONSO
Green Building Rough 4/29/2022 Not Ready for Inspection SABAS ALONSO
HVAC-Rough 4/29/2022 Not Ready for Inspection SABAS ALONSO
Verify Sprinkler Sign Off 4/29/2022 Not Ready for Inspection SABAS ALONSO
BUILDING-Rough-Frame 5/3/2022 Approved SABAS ALONSO
Green Building Rough 5/3/2022 Approved SABAS ALONSO
Verify Sprinkler Sign Off 5/3/2022 Approved SABAS ALONSO
Insulation 5/9/2022 Approved SABAS ALONSO
Drywall Nailing 5/16/2022 Not Ready for Inspection SABAS ALONSO
Interior/Exterior Lathing 5/16/2022 Partial Approval SABAS ALONSO
Drywall Nailing 5/19/2022 Approved LILIANA PORTILLO
Final 12/27/2022 Corrections Issued SABAS ALONSO
Green Building Final 12/27/2022 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 12/27/2022 SGSOV Approved SABAS ALONSO
Service/Power Release 12/27/2022 Approved SABAS ALONSO
Smoke Detectors 12/27/2022 Approved SABAS ALONSO
Final 2/21/2023 Corrections Issued SABAS ALONSO
Final 4/21/2023 OK to Issue CofO SABAS ALONSO