6100 N WOODLEY AVE 91436
Certificate Information: 6100 N WOODLEY AVE 91436
- Application / Permit
- 20010-10000-04698
- Plan Check / Job No.
- B20LA22716
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (22) Warehouse
- Work Description
- NEW 1-STORY WAREHOUSE AND ACCESSORY OFFICE SPACE NFPA13 THROUGH OUT
- Permit Issued
- Issued on 8/23/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/14/2021 | HERNAN ARREOLA |
| Disabled Access Plans Picked Up | 1/21/2021 | APPLICANT |
| Corrections Issued | 2/8/2021 | HERNAN ARREOLA |
| Quality Review Completed | 2/10/2021 | ALLEN MANALANSAN |
| Green Plans Picked Up | 4/20/2021 | APPLICANT |
| Applicant returned to address corrections | 4/27/2021 | HERNAN ARREOLA |
| Plan Check Approved | 6/18/2021 | HERNAN ARREOLA |
| Issued | 8/23/2022 | APPLICANT |
| CofO in Progress | 6/2/2025 | ROBERT DAVIS |
| Permit Finaled | 7/21/2025 | RICKEY JACKSON |
| CofO Issued | 7/21/2025 | RICKEY JACKSON |
| Permit Finaled | 7/21/2025 | RICKEY JACKSON |
Permit Application Clearance Information
| Address approval | Cleared | 2/25/2021 | LEE GUILBEAUX |
| Highway dedication | Cleared | 2/25/2021 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 2/25/2021 | LEE GUILBEAUX |
| Sewer availability | Cleared | 2/25/2021 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 3/2/2021 | LEE GUILBEAUX |
| Low Impact Development | Cleared | 3/2/2021 | AMMAR ELTAWIL |
| City owned building/parcel | Cleared | 3/10/2021 | DANIEL TARICA |
| Metro Rail approval | Cleared | 4/5/2021 | HERNAN ARREOLA |
| Hydrant and Access approval | Cleared | 4/28/2021 | MATTHEW CRAIG |
| "Q" conditions | Cleared | 5/10/2021 | LOUIS ORTEGA |
| ZA Case | Cleared | 5/10/2021 | LOUIS ORTEGA |
| ZA Case | Cleared | 5/10/2021 | LOUIS ORTEGA |
| ZI | Cleared | 5/10/2021 | LOUIS ORTEGA |
| ZI | Cleared | 5/10/2021 | LOUIS ORTEGA |
| DAS Clearance | Cleared | 5/19/2021 | SHINE LIN |
| Green Code | Cleared | 6/3/2021 | AARON COSTA |
Contact Information
| Architect | Kimm,, Alice Young; Lic. No.: C25438 | 821 TRACTION AVENUE # 107 LOS ANGELES, CA 90013 |
| Contractor | Green Building Corporation; Lic. No.: 919867-B | 6913 ALCOVE AVE NORTH HOLLYWOOD, CA 91605 |
| Engineer | Islam,, Mohammed Saiful; Lic. No.: S4083 | 155 N LAKE AVE SUITE 600 PASADENA, CA 91101 |
Inspector Information
| ROBERT DAVIS, (818) 374-1125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grading Pre-Inspection | 11/10/2022 | Partial Inspection | CAMERON CHABAN |
| Pre-Inspection | 11/10/2022 | Partial Inspection | CAMERON CHABAN |
| Excavation/Setback/Form/Re-Bar | 12/21/2022 | Approved | DANIEL VARNUM |
| Footing/Foundation/Slab | 12/21/2022 | Not Ready for Inspection | DANIEL VARNUM |
| Excavation/Setback/Form/Re-Bar | 2/15/2023 | Corrections Issued | JOHN KITCKO |
| Footing/Foundation/Slab | 2/16/2023 | Partial Approval | CAMERON CHABAN |
| Deputy Reinf. Concrete | 2/17/2023 | Conditional Approval | CAMERON CHABAN |
| Special/Order Compliance | 2/17/2023 | Conditional Approval | STEVEN LEVITT |
| Deputy Reinf. Concrete | 5/26/2023 | Approved | ROBERT DAVIS |
| Excavation/Setback/Form/Re-Bar | 5/26/2023 | Approved | ROBERT DAVIS |
| Footing/Foundation/Slab | 5/26/2023 | Approved | ROBERT DAVIS |
| Green Building Rough | 6/20/2023 | Not Ready for Inspection | CAMERON CHABAN |
| Structural Steel Frame | 6/20/2023 | Partial Inspection | CAMERON CHABAN |
| Verify Sprinkler Sign Off | 6/20/2023 | Not Ready for Inspection | CAMERON CHABAN |
| Green Building Rough | 7/13/2023 | Partial Inspection | CAMERON CHABAN |
| Structural Steel Frame | 7/13/2023 | Conditional Approval | CAMERON CHABAN |
| Verify Sprinkler Sign Off | 7/13/2023 | Not Ready for Inspection | CAMERON CHABAN |
| Drywall Nailing | 9/1/2023 | Partial Approval | CAMERON CHABAN |
| Deputy Reinf. Concrete | 9/11/2023 | Conditional Approval | JEFFREY DURAN |
| Deputy Reinf. Concrete | 9/12/2023 | Conditional Approval | JEFFREY DURAN |
| Deputy Reinf. Concrete | 9/13/2023 | Conditional Approval | JEFFREY DURAN |
| Deputy Reinf. Concrete | 9/14/2023 | Conditional Approval | JOHN KITCKO |
| Excavation/Setback/Form/Re-Bar | 9/18/2023 | Partial Inspection | ANDREW DORSO |
| Deputy Reinf. Concrete | 9/20/2023 | Conditional Approval | CAMERON CHABAN |
| Deputy Reinf. Concrete | 10/2/2023 | Conditional Approval | CAMERON CHABAN |
| Deputy Reinf. Concrete | 10/3/2023 | Conditional Approval | JEFFREY DURAN |
| Deputy Reinf. Concrete | 10/16/2023 | Conditional Approval | CAMERON CHABAN |
| Drywall Nailing | 11/2/2023 | Not Ready for Inspection | CAMERON CHABAN |
| Interior/Exterior Lathing | 11/2/2023 | Conditional Approval | CAMERON CHABAN |
| Drywall Nailing | 11/29/2023 | Conditional Approval | CAMERON CHABAN |
| Excavation/Setback/Form/Re-Bar | 11/29/2023 | Conditional Approval | CAMERON CHABAN |
| Interior/Exterior Lathing | 1/11/2024 | Partial Approval | STEVEN LEVITT |
| Special/Order Compliance | 2/15/2024 | Partial Inspection | MELVIN GIRTON |
| Wall Anchors | 2/15/2024 | Partial Inspection | ANDREW DORSO |
| T-Bar Ceiling | 3/29/2024 | Approved | ROBERT DAVIS |
| Final | 5/7/2024 | Partial Inspection | CAMERON CHABAN |
| Green Building Final | 5/7/2024 | Partial Inspection | CAMERON CHABAN |
| Green Building Rough | 5/7/2024 | Approved | CAMERON CHABAN |
| Reinforced Masonry Frame | 5/7/2024 | Approved | CAMERON CHABAN |
| SGSOV-Seismic Gas S/O Valve | 5/7/2024 | SGSOV No Gas | CAMERON CHABAN |
| Smoke Detectors | 5/7/2024 | Approved | CAMERON CHABAN |
| Structural Steel Frame | 5/7/2024 | Approved | CAMERON CHABAN |
| Verify Sprinkler Sign Off | 5/7/2024 | Approved | CAMERON CHABAN |
| Final | 6/2/2025 | OK to Issue CofO | ROBERT DAVIS |
| Green Building Final | 6/2/2025 | Approved | ROBERT DAVIS |