6635 1/2 N LENNOX AVE 91405
Certificate Information: 6635 1/2 N LENNOX AVE 91405
- Application / Permit
- 20010-10000-04663
- Plan Check / Job No.
- B20LA22454
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *ePLAN CHECK* (N) ACCESSORY DWELLING UNIT PER LAMC 12.22A3 (c)-(d)
- Permit Issued
- Issued on 7/28/2021
- Issuing Office
- Current Status
- CofO Issued on 12/17/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/14/2021 | LAMAR DAVIS |
| Corrections Issued | 1/20/2021 | LAMAR DAVIS |
| Quality Review Completed | 2/2/2021 | TU HUA |
| Applicant returned to address corrections | 7/23/2021 | LAMAR DAVIS |
| Plan Check Approved | 7/23/2021 | LAMAR DAVIS |
| Issued | 7/28/2021 | APPLICANT |
| CofO in Progress | 7/21/2022 | RICHARD DOCKUS |
| CofO Issued | 12/17/2022 | MICHAEL SMITH |
| Permit Finaled | 12/17/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 1/27/2021 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 2/3/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 2/3/2021 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 4/1/2021 | KURT CORRAL |
| Low Impact Development | Cleared | 5/30/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 6/2/2021 | DAGOVERTO GUERRERO |
| Miscellaneous | Cleared | 7/23/2021 | LAMAR DAVIS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 8/2/2021 | Corrections Issued | MICHAEL TEMPLE |
| PLUMBING-Rough | 8/6/2021 | Partial Approval | RONALD COWAN |
| Excavation/Setback/Form/Re-Bar | 8/11/2021 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 9/29/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/29/2021 | Partial Approval | JACK KARGODORIAN |
| Green Building Rough | 9/29/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 9/29/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 10/18/2021 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 10/18/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Sewer | 10/18/2021 | Partial Approval | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 10/18/2021 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 10/21/2021 | Not Ready for Inspection | RICHARD DOCKUS |
| HVAC-Rough | 10/21/2021 | Corrections Issued | RICHARD DOCKUS |
| PLUMBING-Rough | 10/21/2021 | Corrections Issued | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 10/27/2021 | Not Ready for Inspection | RICHARD DOCKUS |
| ELECTRICAL-Rough | 10/27/2021 | Approved | RICHARD DOCKUS |
| Green Building Rough | 10/27/2021 | Approved | RICHARD DOCKUS |
| HVAC-Rough | 10/27/2021 | Not Ready for Inspection | RICHARD DOCKUS |
| PLUMBING-Rough | 10/27/2021 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 11/8/2021 | Conditional Approval | RICHARD DOCKUS |
| Interior/Exterior Lathing | 11/8/2021 | Partial Approval | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 11/12/2021 | Approved | RICHARD DOCKUS |
| Insulation | 11/12/2021 | Approved | RICHARD DOCKUS |
| Drywall Nailing | 11/22/2021 | Corrections Issued | MICHAEL TEMPLE |
| Drywall Nailing | 12/1/2021 | Partial Inspection | JACK KARGODORIAN |
| Underground Mechanical | 12/6/2021 | Approved | RICHARD DOCKUS |
| Gas Test | 1/26/2022 | Approved | RICHARD DOCKUS |
| Underground Mechanical | 1/26/2022 | Approved | RICHARD DOCKUS |
| Drywall Nailing | 3/4/2022 | Approved | RICHARD DOCKUS |
| Final | 3/4/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Footing/Foundation/Slab | 3/4/2022 | Approved | RICHARD DOCKUS |
| Green Building Final | 3/4/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 3/4/2022 | SGSOV Not Ready | RICHARD DOCKUS |
| Service/Power Release | 3/4/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Smoke Detectors | 3/4/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Final | 3/31/2022 | No Access for Inspection | RICHARD DOCKUS |
| Green Building Final | 3/31/2022 | No Access for Inspection | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 3/31/2022 | SGSOV Not Ready | RICHARD DOCKUS |
| Service/Power Release | 3/31/2022 | No Access for Inspection | RICHARD DOCKUS |
| Smoke Detectors | 3/31/2022 | No Access for Inspection | RICHARD DOCKUS |
| Final | 4/12/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Green Building Final | 4/12/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 4/12/2022 | SGSOV Not Ready | RICHARD DOCKUS |
| Service/Power Release | 4/12/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Smoke Detectors | 4/12/2022 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Final | 4/21/2022 | Corrections Issued | RICHARD DOCKUS |
| Green Building Final | 4/21/2022 | Approved | RICHARD DOCKUS |
| PLUMBING-Final | 4/21/2022 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 4/21/2022 | SGSOV Approved | RICHARD DOCKUS |
| ELECTRICAL-Final | 5/17/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Final | 5/17/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Service/Power Release | 5/17/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| ELECTRICAL-Final | 6/2/2022 | No Access for Inspection | RICHARD DOCKUS |
| ELECTRICAL-Final | 6/9/2022 | Approved | RICHARD DOCKUS |
| Final | 6/9/2022 | Corrections Issued | RICHARD DOCKUS |
| HVAC-Final | 6/9/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Service/Power Release | 6/9/2022 | Not Required | RICHARD DOCKUS |
| Final | 7/20/2022 | OK to Issue CofO | RICHARD DOCKUS |