1 S LMU DR 90045
Certificate Information: 1 S LMU DR 90045
- Application / Permit
- 20010-10000-04651
- Plan Check / Job No.
- B20LA22351
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (21) Theater
- Work Description
- Open AIV stage at LMU Campus on Lawton Plaza. Out door practice stage and classroom due to Covid
- Permit Issued
- Issued on 5/7/2021
- Issuing Office
- Current Status
- CofO Issued on 12/14/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/4/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/7/2021 | HERNAN ARREOLA |
| Corrections Issued | 1/13/2021 | HERNAN ARREOLA |
| Quality Review Completed | 1/28/2021 | ALLEN MANALANSAN |
| Building Plans Picked Up | 2/2/2021 | APPLICANT |
| Disabled Access Plans Picked Up | 2/2/2021 | APPLICANT |
| Plan Check Approved | 5/7/2021 | HERNAN ARREOLA |
| Issued | 5/7/2021 | APPLICANT |
| TCO Issued (Expire Date: 05-03-2022) | 11/4/2021 | HENRY BAGHDASSARIAN |
| CofO in Progress | 12/14/2021 | NICK LAROCCA |
| Permit Finaled | 12/14/2021 | DAVID TSAU |
| CofO Issued | 12/14/2021 | DAVID TSAU |
| Permit Finaled | 12/14/2021 | DAVID TSAU |
Permit Application Clearance Information
| Green Code | Cleared | 12/22/2020 | AARON COSTA |
| CPC | Cleared | 2/18/2021 | TERRI OSBORNE |
| Miscellaneous | Cleared | 2/18/2021 | TERRI OSBORNE |
| Miscellaneous | Cleared | 2/18/2021 | TERRI OSBORNE |
| Specific Plan | Cleared | 2/18/2021 | ESTHER AMAYA |
| Tract Map conditions | Cleared | 2/18/2021 | TERRI OSBORNE |
| ZA Case | Cleared | 2/18/2021 | TERRI OSBORNE |
| ZA Case | Cleared | 2/18/2021 | TERRI OSBORNE |
| ZA Case | Cleared | 2/18/2021 | TERRI OSBORNE |
| ZA Case | Cleared | 2/18/2021 | TERRI OSBORNE |
| ZA Case | Cleared | 2/18/2021 | TERRI OSBORNE |
| ZI | Cleared | 2/18/2021 | TERRI OSBORNE |
| Drainage to Storm Drain | Cleared | 2/24/2021 | HISASHI KOBAYAKAWA |
| Highway dedication | Cleared | 2/24/2021 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 2/24/2021 | HISASHI KOBAYAKAWA |
| Address approval | Cleared | 2/25/2021 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 3/1/2021 | HISASHI KOBAYAKAWA |
| Specific Plan | Cleared | 3/3/2021 | PEDRO AYALA |
| Hydrant and Access approval | Cleared | 3/26/2021 | MATTHEW CRAIG |
| Fire Marshall Fire Life Safety | Cleared | 4/26/2021 | OSCAR SALGADO JR |
| Low Impact Development | Cleared | 5/3/2021 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 5/4/2021 | HISASHI KOBAYAKAWA |
| GPI Written Notices | Cleared | 5/7/2021 | HERNAN ARREOLA |
| Grading Pre-Inspection | Cleared | 5/7/2021 | HERNAN ARREOLA |
Contact Information
| Contractor | O'Neil W E Construction Co Of California; Lic. No.: 494031-B | 909 N PACIFIC COAST HWY STE 400 EL SEGUNDO, CA 90245 |
| Engineer | Sarkisian,, Mark Peter; Lic. No.: S4639 | ONE MARITIME PLAZA SAN FRANCISCO, CA 94111 |
Inspector Information
| VASIL MIHALEV, (310) 914-3920 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/12/2021 | Corrections Issued | NICK LAROCCA |
| Excavation/Setback/Form/Re-Bar | 6/10/2021 | Partial Approval | NICK LAROCCA |
| Footing/Foundation/Slab | 6/10/2021 | Partial Approval | NICK LAROCCA |
| METHANE-Barrier | 6/10/2021 | Approved | NICK LAROCCA |
| METHANE-Subgrade | 6/10/2021 | Approved | NICK LAROCCA |
| Deputy Reinf. Concrete | 7/1/2021 | Approved | NICK LAROCCA |
| Footing/Foundation/Slab | 7/9/2021 | Approved | NICK LAROCCA |
| Footing/Foundation/Slab | 7/16/2021 | Partial Approval | NICK LAROCCA |
| Deputy Steel/Welding | 8/10/2021 | Approved | NICK LAROCCA |
| Deputy Steel/Welding | 8/11/2021 | Approved | NICK LAROCCA |
| Deputy Steel/Welding | 8/12/2021 | Approved | NICK LAROCCA |
| Deputy Steel/Welding | 8/13/2021 | Approved | NICK LAROCCA |
| Deputy Steel/Welding | 8/16/2021 | Approved | NICK LAROCCA |
| Deputy Steel/Welding | 8/17/2021 | Approved | NICK LAROCCA |
| Deputy Drilled-In Anchors | 8/18/2021 | Approved | NICK LAROCCA |
| Deputy Drilled-In Anchors | 8/19/2021 | Approved | NICK LAROCCA |
| Deputy Steel/Welding | 8/20/2021 | Approved | JOEY BUCHANAN |
| Deputy Steel/Welding | 8/23/2021 | Approved | NICK LAROCCA |
| Deputy Steel/Welding | 8/24/2021 | Approved | NICK LAROCCA |
| Deputy Steel/Welding | 8/25/2021 | Approved | NICK LAROCCA |
| Deputy Drilled-In Anchors | 8/26/2021 | Approved | NICK LAROCCA |
| Deputy Reinf. Concrete | 8/26/2021 | Approved | NICK LAROCCA |
| Footing/Foundation/Slab | 8/27/2021 | Partial Approval | ALAN NOVAK |
| Wood Frame | 8/27/2021 | Partial Approval | ALAN NOVAK |
| Deputy Reinf. Concrete | 8/30/2021 | Approved | NICK LAROCCA |
| Deputy Reinf. Concrete | 9/1/2021 | Approved | NICK LAROCCA |
| Structural Steel Frame | 9/1/2021 | Partial Approval | NICK LAROCCA |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2021 | Partial Approval | NICK LAROCCA |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2021 | Approved | JOEY BUCHANAN |
| Pre-Inspection | 10/15/2021 | Approved | NICK LAROCCA |
| Green Building Rough | 10/29/2021 | Approved | NICK LAROCCA |
| METHANE-Rough | 10/29/2021 | Approved | NICK LAROCCA |
| Structural Steel Frame | 10/29/2021 | Approved | NICK LAROCCA |
| Verify Sprinkler Sign Off | 10/29/2021 | Approved | NICK LAROCCA |
| Drywall Nailing | 12/13/2021 | Approved | NICK LAROCCA |
| Final | 12/13/2021 | OK to Issue CofO | NICK LAROCCA |
| Footing/Foundation/Slab | 12/13/2021 | Approved | NICK LAROCCA |
| Green Building Final | 12/13/2021 | Approved | NICK LAROCCA |
| Reinforced Masonry Frame | 12/13/2021 | Approved | NICK LAROCCA |
| SGSOV-Seismic Gas S/O Valve | 12/13/2021 | SGSOV No Gas | NICK LAROCCA |
| Smoke Detectors | 12/13/2021 | Approved | NICK LAROCCA |