156 S KENTER AVE 90049

Certificate Information: 156 S KENTER AVE 90049

Application / Permit
20010-10000-04647
Plan Check / Job No.
B20LA22296
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ADU PER ORDINANCE (1-STORY)
Permit Issued
Issued on 8/29/2022
Issuing Office
Current Status
CofO Issued on 11/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/4/2020 APPLICANT
Assigned to Plan Check Engineer 1/7/2021 CARLOS MONTES
Corrections Issued 1/13/2021 CARLOS MONTES
Quality Review Completed 1/14/2021 TU HUA
Applicant returned to address corrections 8/26/2021 CARLOS MONTES
Applicant returned to address corrections 2/10/2022 CARLOS MONTES
Applicant returned to address corrections 3/8/2022 CARLOS MONTES
Applicant returned to address corrections 5/13/2022 CARLOS MONTES
Applicant returned to address corrections 6/23/2022 CARLOS MONTES
Applicant returned to address corrections 7/26/2022 CARLOS MONTES
Applicant returned to address corrections 7/28/2022 CARLOS MONTES
Applicant returned to address corrections 8/3/2022 CARLOS MONTES
Plan Check Approved 8/23/2022 CARLOS MONTES
Issued 8/29/2022 APPLICANT
CofO in Progress 11/3/2023 KEVIN SARGSYAN
Permit Finaled 11/8/2023 DANIEL ORRANTE
CofO Issued 11/8/2023 DANIEL ORRANTE
Permit Finaled 11/8/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 3/4/2021 DENNIS BRAGIN
Permit Cleared 3/4/2021 DENNIS BRAGIN
Sewer availability Cleared 3/4/2021 DENNIS BRAGIN
Eng Process Fee Ord 176,300 Cleared 3/8/2021 DENNIS BRAGIN
Specific Plan Cleared 3/31/2021 KEVIN ARUCAN
Hydrant and Access approval Cleared 4/25/2021 MATTHEW CRAIG
Construction near power lines Cleared 9/13/2021 RIDWAN HARDY
Grading Pre-Inspection Cleared 5/19/2022 KIRK LINKLATER
Low Impact Development Cleared 6/14/2022 SUNG JOON WON
Roof/Waste drainage to street Cleared 8/17/2022 HISASHI KOBAYAKAWA
GPI Written Notices Cleared 8/23/2022 CARLOS MONTES

Contact Information

Architect Sun,, Wen-Jay Jason; Lic. No.: NA22697       ,
Contractor Owner-Builder       ,
Engineer Liu,, Wen-Young; Lic. No.: C70729 448 LINWOOD AVE      MONROVIA, CA 91016

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/31/2022 Partial Inspection KEVIN SARGSYAN
PLUMBING-Rough 9/28/2022 Partial Approval STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 10/7/2022 Approved ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 11/3/2022 Corrections Issued KEVIN SARGSYAN
Deputy Wood Construction 11/4/2022 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 11/4/2022 Partial Approval KEVIN SARGSYAN
Deputy Wood Construction 12/8/2022 Approved DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 12/8/2022 Corrections Issued DAVID FEILER
BUILDING-Rough-Frame 12/19/2022 Corrections Issued KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 12/19/2022 Partial Approval KEVIN SARGSYAN
HVAC-Rough 12/21/2022 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 12/21/2022 Not Ready for Inspection KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 12/22/2022 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 1/4/2023 Partial Approval KEVIN SARGSYAN
Rough-Elec/Plmb/HVAC 1/11/2023 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 1/12/2023 Corrections Issued KEVIN SARGSYAN
Rough-Elec/Plmb/HVAC 1/18/2023 Approved OGANES TARAKHCHYAN
Wood Frame 1/24/2023 Not Ready for Inspection OGANES TARAKHCHYAN
Shower Pan 1/27/2023 Corrections Issued CARLOS MATAMOROS
Wood Frame 1/27/2023 Not Ready for Inspection CARLOS MATAMOROS
BUILDING-Rough-Frame 1/31/2023 Approved STEPHANIE SWANSON
Green Building Rough 1/31/2023 Approved STEPHANIE SWANSON
Shower Pan 1/31/2023 Corrections Issued STEPHANIE SWANSON
Verify Sprinkler Sign Off 1/31/2023 Approved STEPHANIE SWANSON
Wood Frame 1/31/2023 Approved STEPHANIE SWANSON
Insulation 2/2/2023 Approved OGANES TARAKHCHYAN
Shower Pan 2/2/2023 Approved OGANES TARAKHCHYAN
Drywall Nailing 2/7/2023 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 2/21/2023 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 2/22/2023 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 4/11/2023 Approved CHRISTOPHER WILSON
HVAC-Final 4/11/2023 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Final 4/11/2023 Corrections Issued CHRISTOPHER WILSON
HVAC-Final 4/18/2023 Approved OGANES TARAKHCHYAN
PLUMBING-Final 4/18/2023 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 10/18/2023 SGSOV Not Ready OGANES TARAKHCHYAN
Final 11/2/2023 OK to Issue CofO KEVIN SARGSYAN
Footing/Foundation/Slab 11/2/2023 Approved KEVIN SARGSYAN
Green Building Final 11/2/2023 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 11/2/2023 SGSOV Approved KEVIN SARGSYAN
Service/Power Release 11/2/2023 Approved KEVIN SARGSYAN
Smoke Detectors 11/2/2023 Approved KEVIN SARGSYAN