4312 S MORGAN AVE 90011
Certificate Information: 4312 S MORGAN AVE 90011
- Application / Permit
- 20010-10000-04642
- Plan Check / Job No.
- B20LA22264
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SINGLE FMAILY DWELLING WITH ATTACHED 4-CAR GARAGE (REAR BLDG)
- Permit Issued
- Issued on 7/19/2021
- Issuing Office
- Current Status
- CofO Issued on 2/17/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/3/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/10/2020 | CARLOS MONTES |
| Corrections Issued | 12/14/2020 | CARLOS MONTES |
| Quality Review Completed | 12/21/2020 | WING SUEN |
| Applicant returned to address corrections | 4/9/2021 | CARLOS MONTES |
| Plan Check Approved | 7/12/2021 | CARLOS MONTES |
| Issued | 7/19/2021 | APPLICANT |
| CofO in Progress | 2/16/2022 | JOAQUIN GREENOUGH |
| CofO Issued | 2/17/2022 | DEROLD HAUFF |
| Permit Finaled | 2/17/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/12/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 1/12/2021 | RENZ SORIANO |
| Highway dedication | Cleared | 1/12/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 1/13/2021 | RENZ SORIANO |
| Frnt yard landscape/Water mgmt | Cleared | 1/21/2021 | TERRI OSBORNE |
| Hydrant and Access approval | Cleared | 1/29/2021 | ROBERT DUFF |
| Low Impact Development | Cleared | 4/1/2021 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 4/5/2021 | CELINA MORENO |
| Permit | Cleared | 6/3/2021 | RENZ SORIANO |
| Trees in Parkway | Cleared | 6/28/2021 | JOHN KIM |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/31/2021 | Approved | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 9/29/2021 | Partial Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2021 | Partial Approval | JOAQUIN GREENOUGH |
| Underground Mechanical | 10/4/2021 | Partial Approval | JOAQUIN GREENOUGH |
| Insulation | 10/5/2021 | Partial Approval | RUBEN SALAS |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2021 | Partial Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 11/2/2021 | Approved | JOAQUIN GREENOUGH |
| HVAC-Rough | 11/10/2021 | Not Ready for Inspection | HORACE FULTZ |
| PLUMBING-Rough | 11/10/2021 | Corrections Issued | HORACE FULTZ |
| ELECTRICAL-Rough | 11/12/2021 | Approved | JOAQUIN GREENOUGH |
| Green Building Rough | 11/12/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 11/12/2021 | Approved | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 11/12/2021 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 11/15/2021 | Approved | JOAQUIN GREENOUGH |
| Green Building Rough | 11/15/2021 | Approved | JOAQUIN GREENOUGH |
| HVAC-Rough | 11/15/2021 | Approved | JOAQUIN GREENOUGH |
| Insulation | 11/18/2021 | Approved | JOAQUIN GREENOUGH |
| Drywall Nailing | 11/30/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 11/30/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Drywall Nailing | 12/3/2021 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 12/3/2021 | Approved | JOAQUIN GREENOUGH |
| Underground Mechanical | 1/6/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Underground Mechanical | 1/7/2022 | Partial Approval | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 1/24/2022 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 1/28/2022 | Approved | JOAQUIN GREENOUGH |
| Final | 1/28/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Final | 1/28/2022 | Approved | JOAQUIN GREENOUGH |
| HVAC-Final | 1/28/2022 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Final | 1/28/2022 | Approved | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 1/28/2022 | SGSOV Approved | JOAQUIN GREENOUGH |
| Service/Power Release | 1/28/2022 | Approved | JOAQUIN GREENOUGH |
| Underground Mechanical | 1/28/2022 | Approved | JOAQUIN GREENOUGH |
| Final | 2/15/2022 | OK to Issue CofO | JOAQUIN GREENOUGH |