507 N OXFORD AVE 90004
Certificate Information: 507 N OXFORD AVE 90004
- Application / Permit
- 20010-10000-04637
- Plan Check / Job No.
- B20LA22246
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 4 story SFD/GAR (Small Lots Project)
- Permit Issued
- Issued on 1/14/2025
- Issuing Office
- Metro
- Current Status
- Issued on 1/14/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/7/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/17/2020 | JOE VO |
| Corrections Issued | 1/7/2021 | JOE VO |
| Quality Review Completed | 1/21/2021 | KEN GILL |
| Building Plans Picked Up | 1/22/2021 | APPLICANT |
| Applicant returned to address corrections | 4/26/2021 | JOE VO |
| Applicant returned to address corrections | 12/3/2024 | JOE VO |
| Plan Check Approved | 1/2/2025 | JOE VO |
| Issued | 1/14/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 5/18/2021 | THOMAS LANG |
| Highway dedication | Cleared | 5/18/2021 | THOMAS LANG |
| Permit | Cleared | 5/18/2021 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 5/19/2021 | THOMAS LANG |
| Sewer availability | Cleared | 6/2/2021 | THOMAS LANG |
| Trees in Parkway | Cleared | 7/1/2021 | JOHN KIM |
| Hydrant and Access approval | Cleared | 7/16/2021 | MATTHEW CRAIG |
| Driveway location | Cleared | 4/4/2022 | KEVIN ARUCAN |
| Construction near power lines | Cleared | 6/2/2023 | RIDWAN HARDY |
| Low Impact Development | Cleared | 6/11/2024 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 6/13/2024 | JEANIE LAM |
| Green Code | Cleared | 6/28/2024 | JOE VO |
| Miscellaneous | Cleared | 11/15/2024 | YINGSHI HUANG |
| Redevelopment Project Area | Cleared | 11/15/2024 | YASMINE BASHIRI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hwang,, Junho; Lic. No.: S5592 | 2450 W MAIN ST ALHAMBRA, CA 91801 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/9/2025 | Partial Inspection | BRENDAN MORELLI |
| Special/Order Compliance | 10/14/2025 | Corrections Issued | BRENDAN MORELLI |
| Sewer | 12/17/2025 | Conditional Approval | BRENDAN MORELLI |
| Underground Mechanical | 12/17/2025 | Corrections Issued | BRENDAN MORELLI |
| Excavation/Setback/Form/Re-Bar | 2/5/2026 | Corrections Issued | BRENDAN MORELLI |
| Excavation/Setback/Form/Re-Bar | 2/12/2026 | Approved | BRENDAN MORELLI |
| Footing/Foundation/Slab | 2/12/2026 | Approved | BRENDAN MORELLI |
| Pre-Inspection | 5/1/2026 | Partial Inspection | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 5/8/2026 | Corrections Issued | BRENDAN MORELLI |
| Wood Frame | 6/4/2026 | Corrections Issued | BRENDAN MORELLI |