5321-5321 1/2 E OAKLAND ST 90032

Certificate Information: 5321-5321 1/2 E OAKLAND ST 90032

Application / Permit
20010-10000-04627
Plan Check / Job No.
B20LA22185
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 2-STORY DUPLEX WITH ATTACHED 8-CAR GARAGE(REAR BUILDING).
Permit Issued
Issued on 6/15/2021
Issuing Office
Current Status
CofO Issued on 12/21/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/8/2020 APPLICANT
Assigned to Plan Check Engineer 12/17/2020 MICHAEL LOPEZ
Corrections Issued 12/24/2020 MICHAEL LOPEZ
Quality Review Completed 1/6/2021 TU HUA
Building Plans Picked Up 1/13/2021 APPLICANT
Plan Check Approved 6/10/2021 MICHAEL LOPEZ
Issued 6/15/2021 APPLICANT
CofO in Progress 12/13/2022 AMY COLIN
Permit Finaled 12/21/2022 DEROLD HAUFF
CofO Issued 12/21/2022 DEROLD HAUFF
Permit Finaled 12/21/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/27/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 1/28/2021 CECILIO NAVARRO
Hydrant and Access approval Cleared 2/8/2021 ROBERT DUFF
Sewer availability Cleared 4/23/2021 CECILIO NAVARRO
Low Impact Development Cleared 5/16/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 5/18/2021 CELINA MORENO
GPI Written Notices Cleared 6/10/2021 MICHAEL LOPEZ
Grading Pre-Inspection Cleared 6/10/2021 MICHAEL LOPEZ

Contact Information

Contractor Builder Point Construction; Lic. No.: 1059885-B 11445 PARAMOUNT BLVD SUITE H      DOWNEY, CA 90241
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/12/2021 Corrections Issued COREY HUPP
Footing/Foundation/Slab 11/2/2021 Approved COREY HUPP
Footing/Foundation/Slab 11/9/2021 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 11/18/2021 Partial Approval COREY HUPP
Underground Mechanical 11/18/2021 Partial Approval COREY HUPP
Insulation 11/24/2021 Partial Approval JUSTIN HAWLEY
Floor/Roof Diaphrgm/Shear Wall 11/29/2021 Partial Approval KATHRYN BUTTERWORTH
Special/Order Compliance 12/8/2021 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 12/15/2021 Partial Approval COREY HUPP
Floor/Roof Diaphrgm/Shear Wall 2/4/2022 Corrections Issued COREY HUPP
PLUMBING-Rough 2/4/2022 Not Ready for Inspection COREY HUPP
Floor/Roof Diaphrgm/Shear Wall 2/14/2022 Not Ready for Inspection OSVALDO PARAMO
PLUMBING-Rough 2/14/2022 Corrections Issued OSVALDO PARAMO
HVAC-Rough 2/22/2022 Partial Approval COREY HUPP
PLUMBING-Rough 2/22/2022 Approved COREY HUPP
ELECTRICAL-Rough 2/23/2022 Not Ready for Inspection COREY HUPP
HVAC-Rough 2/23/2022 Partial Approval COREY HUPP
ELECTRICAL-Rough 3/1/2022 Approved AMY COLIN
BUILDING-Rough-Frame 3/10/2022 Partial Approval SCOTT FINNILA
Green Building Rough 3/10/2022 Corrections Issued SCOTT FINNILA
Verify Sprinkler Sign Off 3/10/2022 Approved SCOTT FINNILA
BUILDING-Rough-Frame 3/18/2022 Approved AMY COLIN
Green Building Rough 3/18/2022 Approved AMY COLIN
Interior/Exterior Lathing 3/29/2022 Partial Approval AMY COLIN
Drywall Nailing 4/1/2022 Approved RUBEN SALAS
Final 9/20/2022 Corrections Issued AMY COLIN
Gas Test 9/20/2022 Not Ready for Inspection AMY COLIN
PLUMBING-Final 9/20/2022 Not Ready for Inspection AMY COLIN
Verify Rec and Parks Fee Memo 9/20/2022 Not Ready for Inspection AMY COLIN
Gas Test 10/11/2022 Not Ready for Inspection AMY COLIN
PLUMBING-Final 10/11/2022 Not Ready for Inspection AMY COLIN
Verify Rec and Parks Fee Memo 10/11/2022 Not Ready for Inspection AMY COLIN
ELECTRICAL-Final 10/26/2022 Partial Approval AMY COLIN
Verify Rec and Parks Fee Memo 10/26/2022 Corrections Issued AMY COLIN
HVAC-Final 10/31/2022 Corrections Issued AMY COLIN
PLUMBING-Final 10/31/2022 Approved AMY COLIN
ELECTRICAL-Final 11/8/2022 Not Ready for Inspection AMY COLIN
Gas Test 11/8/2022 Approved AMY COLIN
HVAC-Final 11/8/2022 Approved AMY COLIN
PLUMBING-Final 11/8/2022 Approved AMY COLIN
ELECTRICAL-Final 11/16/2022 Approved AMY COLIN
Special/Order Compliance 11/21/2022 Approved AMY COLIN
Green Building Final 12/6/2022 Approved AMY COLIN
Service/Power Release 12/6/2022 Approved AMY COLIN
Smoke Detectors 12/6/2022 Approved AMY COLIN
Final 12/7/2022 Partial Inspection AMY COLIN
SGSOV-Seismic Gas S/O Valve 12/7/2022 SGSOV Approved AMY COLIN
Final 12/13/2022 OK to Issue CofO AMY COLIN