9313 N EL DORADO AVE 91352

Certificate Information: 9313 N EL DORADO AVE 91352

Application / Permit
20010-10000-04623
Plan Check / Job No.
B20LA22169
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW TWO STORY SINGLE FAMILY RESIDENCE WITH AN ATTACHED 2 CAR GARAGE.
Permit Issued
Issued on 1/26/2022
Issuing Office
Current Status
CofO Issued on 8/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/8/2021 APPLICANT
Assigned to Plan Check Engineer 2/10/2021 JOHNNY WU
Corrections Issued 2/23/2021 JOHNNY WU
Quality Review Completed 3/1/2021 FARUK SEZER
Applicant returned to address corrections 11/19/2021 JOHNNY WU
Applicant returned to address corrections 12/14/2021 JOHNNY WU
Plan Check Approved 12/14/2021 JOHNNY WU
Issued 1/26/2022 APPLICANT
Building Plans Picked Up 2/15/2022 APPLICANT
CofO in Progress 7/29/2024 MATTHEW NELSON
CofO in Progress 7/29/2024 MATTHEW NELSON
CofO in Progress 7/30/2024 MATTHEW NELSON
CofO in Progress 7/30/2024 MATTHEW NELSON
Permit Finaled 8/6/2024 RUBEN SALAS
CofO Issued 8/6/2024 RUBEN SALAS
Permit Finaled 8/6/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/18/2021 ADRIAN CASTRO
Permit Cleared 3/18/2021 ADRIAN CASTRO
Construction near power lines Cleared 7/8/2021 RIDWAN HARDY
Hydrant and Access approval Cleared 8/26/2021 JOHN CONNEALLY
Eng Process Fee Ord 176,300 Cleared 9/9/2021 ROSE MARIE SMITH
Roof/Waste drainage to street Cleared 9/9/2021 ROSE MARIE SMITH
Sewer availability Cleared 9/9/2021 ROSE MARIE SMITH
ZA Case Cleared 9/14/2021 JOE LUCKEY
ZA Case Cleared 9/14/2021 JOE LUCKEY
ZI Cleared 9/14/2021 JOE LUCKEY
Low Impact Development Cleared 9/21/2021 MARCO SANCHEZ
Green Code Cleared 12/28/2021 JOHNNY WU

Contact Information

Contractor Owner-Builder       ,
Engineer Martirossyan,, Armen; Lic. No.: C64223 802 PORTOLA AVE      GLENDALE, CA 91206
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

WILLIAM WREN, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/16/2022 Conditional Approval CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 3/23/2022 Partial Approval CHRISTOPHER DELLEFIELD
Insulation 3/23/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 3/31/2022 Partial Approval JENNIFER RABUCHIN
Insulation 3/31/2022 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 4/20/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 4/21/2022 Approved CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 5/18/2022 No Access for Inspection CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 5/20/2022 Approved CHRISTOPHER DELLEFIELD
Pre-Inspection 5/20/2022 Corrections Issued CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 6/6/2022 Approved CHRISTOPHER DELLEFIELD
HVAC-Rough 6/6/2022 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Rough 6/6/2022 Corrections Issued CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 6/9/2022 Corrections Issued CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 6/9/2022 Approved CHRISTOPHER DELLEFIELD
Gas Test 6/9/2022 Approved CHRISTOPHER DELLEFIELD
Green Building Rough 6/9/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
HVAC-Rough 6/9/2022 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Rough 6/9/2022 Approved CHRISTOPHER DELLEFIELD
Verify Sprinkler Sign Off 6/9/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 6/24/2022 Approved CHRISTOPHER DELLEFIELD
Green Building Rough 6/24/2022 Approved CHRISTOPHER DELLEFIELD
Verify Sprinkler Sign Off 6/24/2022 Approved CHRISTOPHER DELLEFIELD
Insulation 7/5/2022 Conditional Approval CHRISTOPHER DELLEFIELD
Drywall Nailing 7/14/2022 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 7/26/2022 Approved CHRISTOPHER DELLEFIELD
Shower Pan 7/26/2022 Approved CHRISTOPHER DELLEFIELD
Sewer 9/15/2022 Approved WILLIAM WREN
Underground Mechanical 9/15/2022 Approved WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 1/6/2023 SGSOV Not Ready MATTHEW NELSON
Gas Test 6/13/2023 Corrections Issued MATTHEW NELSON
ELECTRICAL-Final 6/23/2023 Not Ready for Inspection MATTHEW NELSON
Final 6/23/2023 Not Ready for Inspection MATTHEW NELSON
Footing/Foundation/Slab 6/23/2023 Not Ready for Inspection MATTHEW NELSON
Green Building Final 6/23/2023 Not Ready for Inspection MATTHEW NELSON
HVAC-Final 6/23/2023 Not Ready for Inspection MATTHEW NELSON
PLUMBING-Final 6/23/2023 Not Ready for Inspection MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 6/23/2023 SGSOV Not Ready MATTHEW NELSON
Service/Power Release 6/23/2023 Not Ready for Inspection MATTHEW NELSON
Smoke Detectors 6/23/2023 Not Ready for Inspection MATTHEW NELSON
ELECTRICAL-Final 12/28/2023 Corrections Issued DAVID ANDERSON
Final 1/12/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Footing/Foundation/Slab 1/12/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Final 1/12/2024 Not Ready for Inspection CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 1/12/2024 SGSOV Not Ready CHRISTOPHER ROJAS
Service/Power Release 1/12/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Smoke Detectors 1/12/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Final 2/13/2024 No Access for Inspection MATTHEW NELSON
Footing/Foundation/Slab 2/13/2024 No Access for Inspection MATTHEW NELSON
Green Building Final 2/13/2024 No Access for Inspection MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 2/13/2024 SGSOV Not Ready MATTHEW NELSON
Service/Power Release 2/13/2024 No Access for Inspection MATTHEW NELSON
Smoke Detectors 2/13/2024 No Access for Inspection MATTHEW NELSON
Final 2/21/2024 Corrections Issued MATTHEW NELSON
Footing/Foundation/Slab 2/21/2024 Approved MATTHEW NELSON
Green Building Final 2/21/2024 Corrections Issued MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 2/21/2024 SGSOV Not Ready MATTHEW NELSON
Service/Power Release 2/21/2024 Corrections Issued MATTHEW NELSON
Smoke Detectors 2/21/2024 Approved MATTHEW NELSON
Final 4/29/2024 Corrections Issued MATTHEW NELSON
Green Building Final 4/29/2024 Corrections Issued MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 4/29/2024 SGSOV Approved MATTHEW NELSON
Service/Power Release 4/29/2024 Not Ready for Inspection MATTHEW NELSON
Service/Power Release 5/10/2024 Approved MATTHEW NELSON
Final 7/18/2024 Corrections Issued MATTHEW NELSON
Green Building Final 7/18/2024 Corrections Issued MATTHEW NELSON
Final 7/26/2024 OK to Issue CofO MATTHEW NELSON
Green Building Final 7/26/2024 Approved MATTHEW NELSON
Final 7/29/2024 OK to Issue CofO MATTHEW NELSON