9313 N EL DORADO AVE 91352
Certificate Information: 9313 N EL DORADO AVE 91352
- Application / Permit
- 20010-10000-04623
- Plan Check / Job No.
- B20LA22169
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW TWO STORY SINGLE FAMILY RESIDENCE WITH AN ATTACHED 2 CAR GARAGE.
- Permit Issued
- Issued on 1/26/2022
- Issuing Office
- Current Status
- CofO Issued on 8/6/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2021 | JOHNNY WU |
| Corrections Issued | 2/23/2021 | JOHNNY WU |
| Quality Review Completed | 3/1/2021 | FARUK SEZER |
| Applicant returned to address corrections | 11/19/2021 | JOHNNY WU |
| Applicant returned to address corrections | 12/14/2021 | JOHNNY WU |
| Plan Check Approved | 12/14/2021 | JOHNNY WU |
| Issued | 1/26/2022 | APPLICANT |
| Building Plans Picked Up | 2/15/2022 | APPLICANT |
| CofO in Progress | 7/29/2024 | MATTHEW NELSON |
| CofO in Progress | 7/29/2024 | MATTHEW NELSON |
| CofO in Progress | 7/30/2024 | MATTHEW NELSON |
| CofO in Progress | 7/30/2024 | MATTHEW NELSON |
| Permit Finaled | 8/6/2024 | RUBEN SALAS |
| CofO Issued | 8/6/2024 | RUBEN SALAS |
| Permit Finaled | 8/6/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/18/2021 | ADRIAN CASTRO |
| Permit | Cleared | 3/18/2021 | ADRIAN CASTRO |
| Construction near power lines | Cleared | 7/8/2021 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 8/26/2021 | JOHN CONNEALLY |
| Eng Process Fee Ord 176,300 | Cleared | 9/9/2021 | ROSE MARIE SMITH |
| Roof/Waste drainage to street | Cleared | 9/9/2021 | ROSE MARIE SMITH |
| Sewer availability | Cleared | 9/9/2021 | ROSE MARIE SMITH |
| ZA Case | Cleared | 9/14/2021 | JOE LUCKEY |
| ZA Case | Cleared | 9/14/2021 | JOE LUCKEY |
| ZI | Cleared | 9/14/2021 | JOE LUCKEY |
| Low Impact Development | Cleared | 9/21/2021 | MARCO SANCHEZ |
| Green Code | Cleared | 12/28/2021 | JOHNNY WU |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Martirossyan,, Armen; Lic. No.: C64223 | 802 PORTOLA AVE GLENDALE, CA 91206 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| WILLIAM WREN, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/16/2022 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 3/23/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Insulation | 3/23/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2022 | Partial Approval | JENNIFER RABUCHIN |
| Insulation | 3/31/2022 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 4/20/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 5/18/2022 | No Access for Inspection | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Pre-Inspection | 5/20/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 6/6/2022 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 6/6/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 6/6/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 6/9/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 6/9/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Gas Test | 6/9/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 6/9/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 6/9/2022 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 6/9/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Verify Sprinkler Sign Off | 6/9/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 6/24/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 6/24/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Verify Sprinkler Sign Off | 6/24/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 7/5/2022 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 7/14/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 7/26/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Shower Pan | 7/26/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Sewer | 9/15/2022 | Approved | WILLIAM WREN |
| Underground Mechanical | 9/15/2022 | Approved | WILLIAM WREN |
| SGSOV-Seismic Gas S/O Valve | 1/6/2023 | SGSOV Not Ready | MATTHEW NELSON |
| Gas Test | 6/13/2023 | Corrections Issued | MATTHEW NELSON |
| ELECTRICAL-Final | 6/23/2023 | Not Ready for Inspection | MATTHEW NELSON |
| Final | 6/23/2023 | Not Ready for Inspection | MATTHEW NELSON |
| Footing/Foundation/Slab | 6/23/2023 | Not Ready for Inspection | MATTHEW NELSON |
| Green Building Final | 6/23/2023 | Not Ready for Inspection | MATTHEW NELSON |
| HVAC-Final | 6/23/2023 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Final | 6/23/2023 | Not Ready for Inspection | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 6/23/2023 | SGSOV Not Ready | MATTHEW NELSON |
| Service/Power Release | 6/23/2023 | Not Ready for Inspection | MATTHEW NELSON |
| Smoke Detectors | 6/23/2023 | Not Ready for Inspection | MATTHEW NELSON |
| ELECTRICAL-Final | 12/28/2023 | Corrections Issued | DAVID ANDERSON |
| Final | 1/12/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 1/12/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Green Building Final | 1/12/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 1/12/2024 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Service/Power Release | 1/12/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Smoke Detectors | 1/12/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Final | 2/13/2024 | No Access for Inspection | MATTHEW NELSON |
| Footing/Foundation/Slab | 2/13/2024 | No Access for Inspection | MATTHEW NELSON |
| Green Building Final | 2/13/2024 | No Access for Inspection | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 2/13/2024 | SGSOV Not Ready | MATTHEW NELSON |
| Service/Power Release | 2/13/2024 | No Access for Inspection | MATTHEW NELSON |
| Smoke Detectors | 2/13/2024 | No Access for Inspection | MATTHEW NELSON |
| Final | 2/21/2024 | Corrections Issued | MATTHEW NELSON |
| Footing/Foundation/Slab | 2/21/2024 | Approved | MATTHEW NELSON |
| Green Building Final | 2/21/2024 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 2/21/2024 | SGSOV Not Ready | MATTHEW NELSON |
| Service/Power Release | 2/21/2024 | Corrections Issued | MATTHEW NELSON |
| Smoke Detectors | 2/21/2024 | Approved | MATTHEW NELSON |
| Final | 4/29/2024 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 4/29/2024 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 4/29/2024 | SGSOV Approved | MATTHEW NELSON |
| Service/Power Release | 4/29/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Service/Power Release | 5/10/2024 | Approved | MATTHEW NELSON |
| Final | 7/18/2024 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 7/18/2024 | Corrections Issued | MATTHEW NELSON |
| Final | 7/26/2024 | OK to Issue CofO | MATTHEW NELSON |
| Green Building Final | 7/26/2024 | Approved | MATTHEW NELSON |
| Final | 7/29/2024 | OK to Issue CofO | MATTHEW NELSON |