Deputy Grading
|
1/24/2023
|
Partial Approval
|
JAMES POWERS
|
|
Pre-Inspection
|
1/24/2023
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Grading
|
1/25/2023
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Grading
|
1/26/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Concrete
|
1/26/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Grading
|
1/30/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Grading
|
2/1/2023
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
2/8/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Concrete
|
2/9/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Grading
|
2/13/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Concrete
|
2/13/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Concrete
|
2/15/2023
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
2/17/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Steel/Welding
|
2/17/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Concrete
|
2/21/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Steel/Welding
|
2/22/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Steel/Welding
|
2/23/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Footing/Foundation/Slab
|
5/31/2023
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Footing/Foundation/Slab
|
6/1/2023
|
Approved
|
LARRY ARNICK
|
|
Deputy Shotcrete
|
6/5/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Shotcrete
|
6/6/2023
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Shotcrete
|
6/9/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Excavation/Setback/Form/Re-Bar
|
6/12/2023
|
Partial Approval
|
LARRY ARNICK
|
|
Deputy Shotcrete
|
6/13/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Excavation/Setback/Form/Re-Bar
|
6/23/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Excavation/Setback/Form/Re-Bar
|
6/27/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Deputy Shotcrete
|
6/28/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Reinforced Concrete Frame
|
6/29/2023
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
7/14/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Pre-Inspection
|
7/14/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Pre-Inspection
|
7/17/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
8/1/2023
|
Partial Approval
|
JAMES POWERS
|
|
Excavation/Setback/Form/Re-Bar
|
8/1/2023
|
Partial Approval
|
JAMES POWERS
|
|
Excavation/Setback/Form/Re-Bar
|
8/11/2023
|
Partial Approval
|
LARRY ARNICK
|
|
Masonry Wall/Backfill
|
8/14/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
9/11/2023
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
9/12/2023
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
9/13/2023
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
9/14/2023
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
9/15/2023
|
Partial Approval
|
JAMES POWERS
|
|
Excavation/Setback/Form/Re-Bar
|
9/15/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Reinforced Concrete Frame
|
9/18/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
9/19/2023
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
9/19/2023
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
9/20/2023
|
Partial Approval
|
JAMES POWERS
|
|
Light Gage Steel Frame
|
9/25/2023
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
10/4/2023
|
Partial Approval
|
JAMES POWERS
|
|
Masonry Wall/Backfill
|
10/5/2023
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/6/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Deputy Wood Construction
|
10/11/2023
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/13/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Deputy Wood Construction
|
10/18/2023
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
10/24/2023
|
Conditional Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/24/2023
|
Partial Approval
|
LARRY ARNICK
|
|
Deputy Wood Construction
|
11/1/2023
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
11/8/2023
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/8/2023
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
11/17/2023
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/21/2023
|
Partial Approval
|
GREGORY POMISH
|
|
Deputy Steel/Welding
|
11/27/2023
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/28/2023
|
Partial Approval
|
JAMES POWERS
|
|
Excavation/Setback/Form/Re-Bar
|
12/5/2023
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/7/2023
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
12/11/2023
|
Partial Approval
|
JAMES POWERS
|
|
Wall Anchors
|
12/12/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Deputy Wood Construction
|
12/14/2023
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/14/2023
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
12/18/2023
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/18/2023
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/3/2024
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
1/24/2024
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
1/31/2024
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/6/2024
|
No Access for Inspection
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/7/2024
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
2/14/2024
|
Partial Approval
|
JAMES POWERS
|
|
Excavation/Setback/Form/Re-Bar
|
2/14/2024
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
2/15/2024
|
Partial Approval
|
JAMES POWERS
|
|
Excavation/Setback/Form/Re-Bar
|
2/23/2024
|
Partial Approval
|
LUIS CCAMACHO
|
|
Excavation/Setback/Form/Re-Bar
|
2/28/2024
|
Partial Approval
|
JAMES POWERS
|
|
Final
|
2/29/2024
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Green Building Final
|
2/29/2024
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Green Building Rough
|
2/29/2024
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Reinforced Concrete Frame
|
2/29/2024
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Reinforced Masonry Frame
|
2/29/2024
|
Not Ready for Inspection
|
JAMES POWERS
|
|
SGSOV-Seismic Gas S/O Valve
|
2/29/2024
|
SGSOV Not Ready
|
JAMES POWERS
|
|
Smoke Detectors
|
2/29/2024
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
2/29/2024
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Wood Frame
|
2/29/2024
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
3/5/2024
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/8/2024
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
3/14/2024
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
3/14/2024
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
3/18/2024
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/19/2024
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
3/26/2024
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/26/2024
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Insulation
|
3/26/2024
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
4/1/2024
|
Conditional Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/1/2024
|
Approved
|
LARRY ARNICK
|
|
Drywall Nailing
|
4/10/2024
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/17/2024
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
4/17/2024
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
5/1/2024
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
5/1/2024
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
5/7/2024
|
Partial Approval
|
JAMES POWERS
|
|
Masonry Wall/Backfill
|
5/7/2024
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
5/28/2024
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/4/2024
|
Partial Approval
|
JAMES POWERS
|
|
Wood Frame
|
6/4/2024
|
Partial Approval
|
JAMES POWERS
|
|
Wood Frame
|
6/7/2024
|
Partial Approval
|
JAMES POWERS
|
|
Wood Frame
|
6/10/2024
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Deputy Wood Construction
|
6/12/2024
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
6/18/2024
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
6/24/2024
|
Partial Approval
|
JAMES POWERS
|
|
Light Gage Steel Frame
|
6/26/2024
|
Partial Approval
|
JAMES POWERS
|
|
Reinforced Masonry Frame
|
6/26/2024
|
Partial Approval
|
JAMES POWERS
|
|
Excavation/Setback/Form/Re-Bar
|
7/1/2024
|
Partial Approval
|
JAMES POWERS
|
|
Excavation/Setback/Form/Re-Bar
|
7/5/2024
|
Partial Approval
|
JAMES POWERS
|
|
Wood Frame
|
7/12/2024
|
Partial Approval
|
JAMES POWERS
|
|
Wood Frame
|
7/15/2024
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
7/16/2024
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
7/18/2024
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
7/22/2024
|
Partial Approval
|
JAMES POWERS
|
|
Wood Frame
|
7/22/2024
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
7/24/2024
|
Partial Approval
|
JAMES POWERS
|
|
Interior/Exterior Lathing
|
7/29/2024
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
7/30/2024
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
7/30/2024
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
7/31/2024
|
Partial Approval
|
LARRY ARNICK
|
|
Drywall Nailing
|
8/2/2024
|
Partial Approval
|
JAMES POWERS
|
|
Structural Steel Frame
|
8/2/2024
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
8/12/2024
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
8/14/2024
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Interior/Exterior Lathing
|
8/14/2024
|
Partial Approval
|
LARRY ARNICK
|
|
Light Gage Steel Frame
|
8/14/2024
|
Partial Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/16/2024
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Insulation
|
8/16/2024
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/22/2024
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
8/29/2024
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
9/10/2024
|
Partial Approval
|
JAMES POWERS
|
|
Light Gage Steel Frame
|
9/10/2024
|
Partial Approval
|
JAMES POWERS
|
|
Masonry Wall/Backfill
|
9/20/2024
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
9/30/2024
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
9/30/2024
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
10/3/2024
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Insulation
|
10/3/2024
|
Partial Approval
|
JAMES POWERS
|
|
Masonry Wall/Backfill
|
10/11/2024
|
Partial Approval
|
LARRY ARNICK
|
|
Light Gage Steel Frame
|
10/21/2024
|
Partial Approval
|
LARRY ARNICK
|
|
Drywall Nailing
|
10/25/2024
|
Partial Approval
|
LARRY ARNICK
|
|
Light Gage Steel Frame
|
10/25/2024
|
Partial Approval
|
LARRY ARNICK
|
|
Interior/Exterior Lathing
|
10/31/2024
|
Partial Approval
|
JAMES POWERS
|
|
Light Gage Steel Frame
|
10/31/2024
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
11/6/2024
|
Partial Approval
|
JAMES POWERS
|
|
Light Gage Steel Frame
|
11/8/2024
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
11/22/2024
|
Partial Approval
|
JAMES POWERS
|
|
Footing/Foundation/Slab
|
12/18/2024
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
1/13/2025
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Shotcrete
|
1/13/2025
|
Partial Approval
|
JAMES POWERS
|
|
Final
|
1/13/2025
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Footing/Foundation/Slab
|
1/13/2025
|
Approved
|
JAMES POWERS
|
|
Green Building Final
|
1/13/2025
|
Approved
|
JAMES POWERS
|
|
Green Building Rough
|
1/13/2025
|
Approved
|
JAMES POWERS
|
|
Reinforced Concrete Frame
|
1/13/2025
|
Partial Approval
|
JAMES POWERS
|
|
Reinforced Masonry Frame
|
1/13/2025
|
Partial Approval
|
JAMES POWERS
|
|
SGSOV-Seismic Gas S/O Valve
|
1/13/2025
|
SGSOV Not Ready
|
JAMES POWERS
|
|
Smoke Detectors
|
1/13/2025
|
Approved
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
1/13/2025
|
Approved
|
JAMES POWERS
|
|
Deputy Shotcrete
|
1/14/2025
|
Partial Approval
|
JAMES POWERS
|
|
Final
|
2/6/2025
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Reinforced Concrete Frame
|
2/6/2025
|
Approved
|
JAMES POWERS
|
|
Reinforced Masonry Frame
|
2/6/2025
|
Approved
|
JAMES POWERS
|
|
SGSOV-Seismic Gas S/O Valve
|
2/6/2025
|
SGSOV Approved
|
JAMES POWERS
|
|
Light Gage Steel Frame
|
2/7/2025
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Final
|
2/13/2025
|
OK for TCO
|
JAMES POWERS
|
|
Final
|
4/9/2025
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Special/Order Compliance
|
7/30/2025
|
Partial Approval
|
JAMES POWERS
|
|
Special/Order Compliance
|
1/6/2026
|
Approved
|
JAMES POWERS
|