833-835 W 50TH PL 90037

Certificate Information: 833-835 W 50TH PL 90037

Application / Permit
20010-10000-04600
Plan Check / Job No.
B20LA22040
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 2-STORY DUPLEX WITH ATTACHED 1-CAR GARAGE AT FRONT AND 2-CAR GARAGE AT REAR
Permit Issued
Issued on 2/25/2021
Issuing Office
Current Status
CofO Issued on 7/30/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/1/2020 APPLICANT
Assigned to Plan Check Engineer 12/10/2020 DANIEL YIP
Corrections Issued 12/14/2020 DANIEL YIP
Quality Review Completed 12/16/2020 JASON HEALEY
Plan Check Approved 2/22/2021 DANIEL YIP
Issued 2/25/2021 APPLICANT
Building Plans Picked Up 2/26/2021 APPLICANT
CofO in Progress 7/29/2021 SABAS ALONSO
Permit Finaled 7/30/2021 DEROLD HAUFF
CofO Issued 7/30/2021 DEROLD HAUFF
Permit Finaled 7/30/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/6/2021 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 1/7/2021 THOMAS LANG
Sewer availability Cleared 1/7/2021 THOMAS LANG
Trees in Parkway Cleared 1/25/2021 JOHN KIM
Low Impact Development Cleared 1/27/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 1/28/2021 CELINA MORENO
Hydrant and Access approval Cleared 2/5/2021 MATTHEW CRAIG

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/11/2021 Approved ROBERT MCDOWELL
Deputy Other (see comments) 3/12/2021 No Access for Inspection ELMER BLAND
Deputy Reinf. Concrete 3/12/2021 No Access for Inspection ELMER BLAND
Floor/Roof Diaphrgm/Shear Wall 3/22/2021 Partial Approval ROBERT MCDOWELL
Underground Mechanical 3/22/2021 Approved ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 3/23/2021 Partial Approval ROBERT MCDOWELL
Insulation 3/23/2021 Partial Approval ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 3/31/2021 Partial Approval ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 4/14/2021 Partial Approval ROBERT MCDOWELL
BUILDING-Rough-Frame 4/23/2021 Approved ROBERT MCDOWELL
ELECTRICAL-Rough 4/23/2021 Approved ROBERT MCDOWELL
Green Building Rough 4/23/2021 Approved ROBERT MCDOWELL
HVAC-Rough 4/23/2021 Approved ROBERT MCDOWELL
PLUMBING-Rough 4/23/2021 Approved ROBERT MCDOWELL
Verify Sprinkler Sign Off 4/23/2021 Approved ROBERT MCDOWELL
Insulation 4/26/2021 Approved ROBERT MCDOWELL
Drywall Nailing 5/6/2021 Approved ROBERT MCDOWELL
Interior/Exterior Lathing 5/6/2021 Approved ROBERT MCDOWELL
ELECTRICAL-Final 6/29/2021 Approved JOAQUIN GREENOUGH
Final 6/29/2021 Corrections Issued JOAQUIN GREENOUGH
Green Building Final 6/29/2021 Approved JOAQUIN GREENOUGH
HVAC-Final 6/29/2021 Approved JOAQUIN GREENOUGH
PLUMBING-Final 6/29/2021 Approved JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 6/29/2021 SGSOV Approved JOAQUIN GREENOUGH
Service/Power Release 6/29/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Smoke Detectors 6/29/2021 Approved JOAQUIN GREENOUGH
Final 7/28/2021 OK to Issue CofO SABAS ALONSO
Service/Power Release 7/28/2021 Approved SABAS ALONSO
Special/Order Compliance 7/28/2021 Approved HORACE FULTZ