414-416 E 84TH ST 90003
Certificate Information: 414-416 E 84TH ST 90003
- Application / Permit
- 20010-10000-04598
- Plan Check / Job No.
- B20LA22031
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2 STORY DUPLEX WITH ATTACHED GARAGE
- Permit Issued
- Issued on 3/5/2021
- Issuing Office
- Current Status
- CofO Issued on 8/10/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/1/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/10/2020 | STARR CHEN |
| Corrections Issued | 12/28/2020 | STARR CHEN |
| Quality Review Completed | 1/7/2021 | HERNAN ARREOLA |
| Plan Check Approved | 2/22/2021 | STARR CHEN |
| Issued | 3/5/2021 | APPLICANT |
| Building Plans Picked Up | 3/8/2021 | APPLICANT |
| CofO in Progress | 7/30/2021 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 8/10/2021 | DEROLD HAUFF |
| CofO Issued | 8/10/2021 | DEROLD HAUFF |
| Permit Finaled | 8/10/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/20/2021 | RENZ SORIANO |
| Permit | Cleared | 1/20/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 1/21/2021 | RENZ SORIANO |
| Low Impact Development | Cleared | 1/21/2021 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 1/22/2021 | CELINA MORENO |
| Sewer availability | Cleared | 1/22/2021 | RENZ SORIANO |
| Trees in Parkway | Cleared | 1/25/2021 | JOHN KIM |
| Hydrant and Access approval | Cleared | 1/29/2021 | ROBERT DUFF |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/25/2021 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 4/9/2021 | Partial Approval | EUGENE CASSIDY |
| PLUMBING-Rough | 4/9/2021 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 4/12/2021 | Partial Approval | EUGENE CASSIDY |
| Insulation | 4/12/2021 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 4/19/2021 | Partial Approval | EUGENE CASSIDY |
| Insulation | 4/19/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 5/10/2021 | Approved | DAVID FEILER |
| BUILDING-Rough-Frame | 5/19/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 5/19/2021 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 5/19/2021 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 5/19/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 5/19/2021 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 5/19/2021 | Approved | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 5/19/2021 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 5/20/2021 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 5/20/2021 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 6/2/2021 | Approved | ALEJANDRO DE ARTOLA |
| Gas Test | 6/2/2021 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 6/2/2021 | Approved | ALEJANDRO DE ARTOLA |
| Pre-Inspection | 6/3/2021 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 7/22/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 7/29/2021 | Approved | ALEJANDRO DE ARTOLA |
| Final | 7/29/2021 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| Green Building Final | 7/29/2021 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 7/29/2021 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 7/29/2021 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 7/29/2021 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 7/29/2021 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 7/29/2021 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 8/5/2021 | Approved | ALEJANDRO DE ARTOLA |