3448 W PERLITA AVE 90039
Certificate Information: 3448 W PERLITA AVE 90039
- Application / Permit
- 20010-10000-04591
- Plan Check / Job No.
- B20LA22027
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- e-plan: New 2 story Detached Accessory Dwelling Unit per Ordinance 186481 and LAMC 12.22.A.33 (c)&(d). All work per Engineer Design.
- Permit Issued
- Issued on 6/9/2022
- Issuing Office
- Current Status
- CofO Issued on 7/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/1/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/30/2020 | ZAW HAN |
| Corrections Issued | 1/11/2021 | ZAW HAN |
| Quality Review Completed | 1/26/2021 | WING SUEN |
| Applicant returned to address corrections | 6/17/2021 | ZAW HAN |
| Applicant returned to address corrections | 6/22/2021 | ZAW HAN |
| Applicant returned to address corrections | 7/12/2021 | ZAW HAN |
| Applicant returned to address corrections | 7/29/2021 | ZAW HAN |
| Applicant returned to address corrections | 10/21/2021 | ZAW HAN |
| Plan Check Approved | 6/2/2022 | ZAW HAN |
| Issued | 6/9/2022 | APPLICANT |
| CofO in Progress | 7/15/2025 | NICHOLAS LOPEZ |
| Permit Finaled | 7/20/2025 | DEROLD HAUFF |
| CofO Issued | 7/20/2025 | DEROLD HAUFF |
| Permit Finaled | 7/20/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/8/2021 | CECILIO NAVARRO |
| Tenant Habitability Plan | Cleared | 4/8/2021 | PHILLIP MUNGUIA |
| Hydrant and Access approval | Cleared | 5/14/2021 | JOHN CONNEALLY |
| Address approval | Cleared | 6/15/2021 | JEREMY CHOK |
| Sewer availability | Cleared | 6/16/2021 | JEREMY CHOK |
| ZI | Cleared | 6/22/2021 | RICHARD REASER |
| Low Impact Development | Cleared | 10/5/2021 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 10/7/2021 | CECILIO NAVARRO |
| Green Code | Cleared | 6/2/2022 | ZAW HAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Dominguez,, Refugio; Lic. No.: C50820 | 254 COTTONWOOD ST ONTARIO, CA 91761 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/3/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 10/13/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Pre-Inspection | 10/13/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Pre-Inspection | 10/24/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 11/21/2022 | Partial Approval | STUART CHAPMAN |
| Footing/Foundation/Slab | 12/8/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 12/8/2022 | Partial Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 12/15/2022 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 3/6/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 3/6/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/16/2023 | Partial Approval | HAMIK HARTOUNIAN |
| Wood Frame | 4/25/2023 | Partial Approval | SCOTT FINNILA |
| ELECTRICAL-Rough | 5/10/2023 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 5/10/2023 | Approved | STUART CHAPMAN |
| Underground Mechanical | 5/18/2023 | Partial Approval | JOSEPH MCGARRY |
| Wood Frame | 5/18/2023 | Corrections Issued | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| HVAC-Rough | 6/23/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/3/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| HVAC-Rough | 7/3/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| HVAC-Rough | 7/24/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/11/2023 | Partial Approval | HAMIK HARTOUNIAN |
| HVAC-Final | 8/11/2023 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Deputy Wood Construction | 9/1/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/7/2023 | Approved | HAMIK HARTOUNIAN |
| Deputy Wood Construction | 9/19/2023 | Conditional Approval | JOSH MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 9/21/2023 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 10/3/2023 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 10/3/2023 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 10/3/2023 | Partial Approval | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 10/3/2023 | Approved | HAMIK HARTOUNIAN |
| Insulation | 10/17/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| Insulation | 11/2/2023 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 11/22/2023 | Corrections Issued | BRENDAN MORELLI |
| Drywall Nailing | 11/30/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Drywall Nailing | 12/6/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| Smoke Detectors | 12/6/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Gas Test | 1/24/2024 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 8/21/2024 | Approved | THOMAS LOGRASSO |
| Final | 8/21/2024 | Corrections Issued | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 8/21/2024 | SGSOV Approved | THOMAS LOGRASSO |
| Service/Power Release | 8/21/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Smoke Detectors | 8/21/2024 | Approved | THOMAS LOGRASSO |
| Final | 6/6/2025 | Corrections Issued | BRENDAN MORELLI |
| Green Building Final | 6/6/2025 | Corrections Issued | BRENDAN MORELLI |
| Service/Power Release | 6/6/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| Final | 7/10/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Green Building Final | 7/10/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Service/Power Release | 7/10/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Final | 7/14/2025 | OK to Issue CofO | NICHOLAS LOPEZ |
| Green Building Final | 7/14/2025 | Approved | NICHOLAS LOPEZ |
| Service/Power Release | 7/14/2025 | Approved | NICHOLAS LOPEZ |