22998 W OXNARD ST 91367
Certificate Information: 22998 W OXNARD ST 91367
- Application / Permit
- 20010-10000-04553
- Plan Check / Job No.
- B20LA21892
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) ACCESSORY DWELLING UNIT per GCS 65852.2 The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy
- Permit Issued
- Issued on 3/11/2022
- Issuing Office
- Current Status
- CofO Issued on 3/11/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/25/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/30/2020 | HERNAN ARREOLA |
| Corrections Issued | 2/4/2021 | HERNAN ARREOLA |
| Quality Review Completed | 2/4/2021 | ALLEN MANALANSAN |
| Applicant returned to address corrections | 4/12/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 4/26/2021 | HERNAN ARREOLA |
| Plan Check Approved | 2/18/2022 | HERNAN ARREOLA |
| Issued | 3/11/2022 | APPLICANT |
| CofO in Progress | 2/8/2023 | TROY SANDERS |
| Permit Finaled | 3/11/2023 | DANIEL ORRANTE |
| CofO Issued | 3/11/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/11/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 3/18/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 3/18/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 3/18/2021 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 1/25/2022 | JOHN LIN |
| Grading Pre-Inspection | Cleared | 1/26/2022 | VASIL MIHALEV |
| GPI Written Notices | Cleared | 2/18/2022 | HERNAN ARREOLA |
Contact Information
| Contractor | Flip It Homes Inc; Lic. No.: 1043456-B | 20501 VENTURA BLVD #135 WOODLAND HILLS, CA 91364 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/6/2022 | Partial Approval | TROY SANDERS |
| Footing/Foundation/Slab | 6/22/2022 | Not Ready for Inspection | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 8/2/2022 | Corrections Issued | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 8/10/2022 | Partial Approval | TROY SANDERS |
| Footing/Foundation/Slab | 8/10/2022 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 9/9/2022 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 9/9/2022 | Approved | TROY SANDERS |
| Green Building Rough | 9/9/2022 | Not Ready for Inspection | TROY SANDERS |
| HVAC-Rough | 9/9/2022 | Approved | TROY SANDERS |
| PLUMBING-Rough | 9/9/2022 | Approved | TROY SANDERS |
| Rough-Elec/Plmb/HVAC | 9/9/2022 | Approved | TROY SANDERS |
| Verify Sprinkler Sign Off | 9/9/2022 | Approved | TROY SANDERS |
| Green Building Rough | 9/20/2022 | Approved | JESUS PINEDA |
| Insulation | 9/20/2022 | Conditional Approval | JESUS PINEDA |
| Interior/Exterior Lathing | 9/20/2022 | Partial Approval | JESUS PINEDA |
| Interior/Exterior Lathing | 9/26/2022 | Approved | JUSTIN HAWLEY |
| Shower Pan | 9/26/2022 | Approved | JUSTIN HAWLEY |
| Drywall Nailing | 10/3/2022 | Approved | MORRIS JACKSON |
| ELECTRICAL-Final | 1/4/2023 | Approved | TROY SANDERS |
| Final | 1/4/2023 | Corrections Issued | TROY SANDERS |
| Green Building Final | 1/4/2023 | Not Ready for Inspection | TROY SANDERS |
| HVAC-Final | 1/4/2023 | Approved | TROY SANDERS |
| PLUMBING-Final | 1/4/2023 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 1/4/2023 | SGSOV Approved | TROY SANDERS |
| Service/Power Release | 1/4/2023 | Approved | TROY SANDERS |
| Smoke Detectors | 1/4/2023 | Approved | TROY SANDERS |
| Final | 2/7/2023 | OK to Issue CofO | TROY SANDERS |
| Green Building Final | 2/7/2023 | Approved | TROY SANDERS |