1642 S RIMPAU BLVD 90019
Certificate Information: 1642 S RIMPAU BLVD 90019
- Application / Permit
- 20010-10000-04540
- Plan Check / Job No.
- B20LA21848
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 3-story SFD with roof deck and attached 2-car garage. Fire sprinkler is provided.
- Permit Issued
- Issued on 12/30/2021
- Issuing Office
- Current Status
- CofO Issued on 4/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/14/2021 | HELEN NGUYEN |
| Corrections Issued | 1/25/2021 | HELEN NGUYEN |
| Quality Review Completed | 2/8/2021 | KEN GILL |
| Applicant returned to address corrections | 7/23/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 9/24/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 9/28/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 9/29/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 9/30/2021 | HELEN NGUYEN |
| Plan Check Approved | 12/2/2021 | HELEN NGUYEN |
| Issued | 12/30/2021 | APPLICANT |
| Building Plans Picked Up | 1/3/2022 | APPLICANT |
| CofO in Progress | 4/9/2024 | JUSTIN HAWLEY |
| Permit Finaled | 4/12/2024 | DEROLD HAUFF |
| CofO Issued | 4/12/2024 | DEROLD HAUFF |
| Permit Finaled | 4/12/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/24/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 3/4/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 3/5/2021 | JEANIE LAM |
| ZA Case | Cleared | 4/1/2021 | ANACANY HURTADO |
| Frnt yard landscape/Water mgmt | Cleared | 4/16/2021 | ANACANY HURTADO |
| Hydrant and Access approval | Cleared | 4/21/2021 | MATTHEW CRAIG |
| Highway dedication | Cleared | 5/20/2021 | JEANIE LAM |
| Low Impact Development | Cleared | 5/24/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 5/26/2021 | JEANIE LAM |
| Flood clearance | Cleared | 6/22/2021 | BRYAN GATHUKA |
Contact Information
| Contractor | Blue Phoenix Builders Inc; Lic. No.: 1066549-B | 4474 W ADAMS BLVD #205 LOS ANGELES, CA 90016 |
| Engineer | Nuno,, Arnulfo; Lic. No.: C88425 | 7057 DWIGHT WAY SAN BERNARDINO, CA 92404 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| FLOOD-Elevation Certificate | 2/2/2022 | Conditional Approval | STUART CHAPMAN |
| Footing/Foundation/Slab | 2/2/2022 | Partial Approval | STUART CHAPMAN |
| METHANE-Barrier | 2/2/2022 | Approved | STUART CHAPMAN |
| METHANE-Subgrade | 2/2/2022 | Approved | STUART CHAPMAN |
| FLOOD-Elevation Certificate | 2/14/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Footing/Foundation/Slab | 2/14/2022 | Partial Approval | STUART CHAPMAN |
| PLUMBING-Rough | 2/14/2022 | Partial Approval | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2022 | Partial Approval | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2022 | Partial Approval | STUART CHAPMAN |
| Sewer | 3/18/2022 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2022 | Partial Approval | STUART CHAPMAN |
| Pre-Inspection | 6/30/2022 | Approved | STUART CHAPMAN |
| ELECTRICAL-Rough | 7/18/2022 | Approved | STUART CHAPMAN |
| HVAC-Rough | 7/18/2022 | Approved | STUART CHAPMAN |
| METHANE-Rough | 7/18/2022 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 7/18/2022 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2022 | Corrections Issued | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2022 | Partial Approval | STUART CHAPMAN |
| FLOOD-Elevation Certificate | 10/27/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Footing/Foundation/Slab | 10/27/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Special/Order Compliance | 10/27/2022 | Approved | RUBEN SALAS |
| Deputy Wood Construction | 12/29/2022 | Approved | DONALD CRICHLOW |
| BUILDING-Rough-Frame | 1/23/2023 | Not Ready for Inspection | CALEB MEISTER |
| FLOOD-Elevation Certificate | 1/23/2023 | Not Ready for Inspection | CALEB MEISTER |
| FLOOD-Proofing Certificate | 1/23/2023 | Not Ready for Inspection | CALEB MEISTER |
| Footing/Foundation/Slab | 1/23/2023 | Partial Approval | CALEB MEISTER |
| Green Building Rough | 1/23/2023 | Not Ready for Inspection | CALEB MEISTER |
| Verify Sprinkler Sign Off | 1/23/2023 | Not Ready for Inspection | CALEB MEISTER |
| BUILDING-Rough-Frame | 1/26/2023 | Partial Approval | CALEB MEISTER |
| FLOOD-Proofing Certificate | 1/26/2023 | Not Ready for Inspection | CALEB MEISTER |
| Green Building Rough | 1/26/2023 | Not Ready for Inspection | CALEB MEISTER |
| Verify Sprinkler Sign Off | 1/26/2023 | Approved | CALEB MEISTER |
| BUILDING-Rough-Frame | 2/21/2023 | Conditional Approval | CALEB MEISTER |
| FLOOD-Proofing Certificate | 2/21/2023 | Not Ready for Inspection | CALEB MEISTER |
| Green Building Rough | 2/21/2023 | Approved | CALEB MEISTER |
| Insulation | 4/3/2023 | Corrections Issued | CALEB MEISTER |
| Interior/Exterior Lathing | 4/3/2023 | Approved | CALEB MEISTER |
| Drywall Nailing | 5/2/2023 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 6/15/2023 | Partial Approval | STUART CHAPMAN |
| Shower Pan | 6/15/2023 | Approved | STUART CHAPMAN |
| HVAC-Final | 10/19/2023 | Not Ready for Inspection | CALEB MEISTER |
| ELECTRICAL-Final | 11/22/2023 | Approved | JUSTIN HAWLEY |
| Final | 11/22/2023 | Corrections Issued | JUSTIN HAWLEY |
| HVAC-Final | 11/22/2023 | Approved | JUSTIN HAWLEY |
| PLUMBING-Final | 11/22/2023 | Approved | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 11/22/2023 | SGSOV Approved | JUSTIN HAWLEY |
| Service/Power Release | 11/22/2023 | Approved | JUSTIN HAWLEY |
| Smoke Detectors | 11/22/2023 | Approved | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 4/2/2024 | Approved | ENRIQUE MIRELES |
| FLOOD-Elevation Certificate | 4/2/2024 | Approved | ENRIQUE MIRELES |
| FLOOD-Proofing Certificate | 4/2/2024 | Approved | ENRIQUE MIRELES |
| Final | 4/2/2024 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 4/2/2024 | Approved | ENRIQUE MIRELES |
| Green Building Final | 4/2/2024 | Approved | ENRIQUE MIRELES |
| Final | 4/4/2024 | Not Ready for Inspection | CRAIG DAVIS |
| Final | 4/9/2024 | OK to Issue CofO | JUSTIN HAWLEY |