5538 W LEXINGTON AVE 90038

Certificate Information: 5538 W LEXINGTON AVE 90038

Application / Permit
20010-10000-04527
Plan Check / Job No.
B20LA21790
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 2 STORY ADU WITH 4-CAR ATTACHED GARAGE AT REAR OF LOT PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 9/27/2021
Issuing Office
Current Status
CofO Issued on 8/3/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/25/2020 APPLICANT
Assigned to Plan Check Engineer 12/30/2020 SERGIO GUTIERREZ
Corrections Issued 2/4/2021 SERGIO GUTIERREZ
Quality Review Completed 2/18/2021 TIEN JEN WANG
Plan Check Approved 9/17/2021 SERGIO GUTIERREZ
Issued 9/27/2021 APPLICANT
Building Plans Picked Up 9/28/2021 APPLICANT
CofO in Progress 7/30/2022 ALEJANDRO DE ARTOLA
CofO Issued 8/3/2022 DEROLD HAUFF
Permit Finaled 8/3/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/25/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 3/26/2021 JEANIE LAM
Historic Resource Verification Cleared 3/26/2021 MICAELA TORRES-GIL
Sewer availability Cleared 3/26/2021 JEANIE LAM
Watercourse Cleared 4/20/2021 SAM NAVID
Miscellaneous Cleared 4/22/2021 DAVID URITA
Miscellaneous Cleared 4/22/2021 DAVID URITA
Redevelopment Project Area Cleared 4/22/2021 DAVID URITA
Hydrant and Access approval Cleared 5/2/2021 JOHN CONNEALLY
Low Impact Development Cleared 9/1/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 9/10/2021 RENZ SORIANO

Contact Information

Contractor Owner-Builder       ,
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/20/2021 Partial Approval ALEJANDRO DE ARTOLA
Deputy Other (see comments) 12/14/2021 Partial Approval RUBEN SALAS
Footing/Foundation/Slab 12/18/2021 Partial Approval DANIEL GONZALEZ
Deputy Steel/Welding 12/20/2021 Conditional Approval BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 1/22/2022 Partial Approval DANIEL GONZALEZ
Footing/Foundation/Slab 1/22/2022 Approved DANIEL GONZALEZ
Sewer 1/22/2022 Approved DANIEL GONZALEZ
Floor/Roof Diaphrgm/Shear Wall 2/2/2022 Partial Approval BRIAN SULLIVAN
BUILDING-Rough-Frame 3/10/2022 Corrections Issued BRIAN SULLIVAN
Deputy Wood Construction 3/10/2022 Conditional Approval BRIAN SULLIVAN
ELECTRICAL-Rough 3/10/2022 Approved BRIAN SULLIVAN
HVAC-Rough 3/10/2022 Approved BRIAN SULLIVAN
PLUMBING-Rough 3/10/2022 Approved BRIAN SULLIVAN
Pre-Inspection 3/10/2022 Not Ready for Inspection BRIAN SULLIVAN
Deputy Wood Construction 3/11/2022 Conditional Approval RUBEN SALAS
Insulation 3/17/2022 Approved ARTHUR SARGSYAN
Shower Pan 3/17/2022 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 3/22/2022 Approved BRIAN SULLIVAN
Drywall Nailing 3/22/2022 Approved BRIAN SULLIVAN
Green Building Rough 3/22/2022 Approved BRIAN SULLIVAN
MERV13>=Rough 3/22/2022 Approved BRIAN SULLIVAN
Verify Sprinkler Sign Off 3/22/2022 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 3/23/2022 Not Ready for Inspection RAUL BARAJAS
Interior/Exterior Lathing 3/25/2022 Approved BRIAN SULLIVAN
ELECTRICAL-Final 4/26/2022 Corrections Issued ALIZAH MAYAGOITIA
ELECTRICAL-Final 5/6/2022 Approved JOSEPH MCGARRY
HVAC-Final 5/6/2022 Approved JOSEPH MCGARRY
PLUMBING-Final 5/6/2022 Approved JOSEPH MCGARRY
Service/Power Release 5/6/2022 Approved JOSEPH MCGARRY
Service/Power Release 5/18/2022 Approved JOSEPH MCGARRY
Final 6/8/2022 Corrections Issued ALEJANDRO DE ARTOLA
Final 7/11/2022 Partial Approval ALEJANDRO DE ARTOLA
Smoke Detectors 7/11/2022 Approved ALEJANDRO DE ARTOLA
Final 7/18/2022 Corrections Issued ALEJANDRO DE ARTOLA
MERV13>=Final 7/18/2022 Approved ALEJANDRO DE ARTOLA
Service/Power Release 7/18/2022 Approved ALEJANDRO DE ARTOLA
Final 7/29/2022 OK to Issue CofO ALEJANDRO DE ARTOLA
Green Building Final 7/29/2022 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 7/29/2022 SGSOV Approved ALEJANDRO DE ARTOLA