17555 W BALTAR ST 91325
Certificate Information: 17555 W BALTAR ST 91325
- Application / Permit
- 20010-10000-04518
- Plan Check / Job No.
- B20LA21774
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New 2-story detached ADU per ordinance.
- Permit Issued
- Issued on 2/10/2022
- Issuing Office
- Current Status
- CofO Issued on 12/8/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/30/2020 | HELEN NGUYEN |
| Corrections Issued | 1/4/2021 | HELEN NGUYEN |
| Quality Review Completed | 1/20/2021 | MINYE PAK |
| Applicant returned to address corrections | 12/13/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 1/12/2022 | HELEN NGUYEN |
| Plan Check Approved | 2/9/2022 | HELEN NGUYEN |
| Issued | 2/10/2022 | APPLICANT |
| CofO in Progress | 10/17/2023 | RAUL OLAGI |
| Permit Finaled | 12/8/2023 | RUBEN SALAS |
| CofO Issued | 12/8/2023 | RUBEN SALAS |
| Permit Finaled | 12/8/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/19/2021 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 3/19/2021 | GUILLERMO PETRA |
| Sewer availability | Cleared | 3/19/2021 | GUILLERMO PETRA |
| Hydrant and Access approval | Cleared | 4/25/2021 | KURT CORRAL |
| Construction near power lines | Cleared | 5/5/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 11/30/2021 | TA ANH |
| Roof/Waste drainage to street | Cleared | 11/30/2021 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/22/2022 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 3/15/2022 | Partial Approval | RAUL OLAGI |
| Underground Mechanical | 3/15/2022 | Corrections Issued | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 3/21/2022 | Corrections Issued | RAUL OLAGI |
| Underground Mechanical | 3/21/2022 | Approved | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 4/8/2022 | Approved | RAUL OLAGI |
| Pre-Inspection | 4/8/2022 | Partial Inspection | ALAN MORELOS |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2022 | Partial Approval | RAUL OLAGI |
| Deputy Wood Construction | 6/1/2022 | Approved | DEANDRE HOFFMAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/6/2022 | Corrections Issued | ALAN MORELOS |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2022 | Not Ready for Inspection | DEANDRE HOFFMAN |
| PLUMBING-Rough | 6/13/2022 | Corrections Issued | DEANDRE HOFFMAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/16/2022 | Partial Approval | ALAN MORELOS |
| PLUMBING-Rough | 6/16/2022 | Approved | ALAN MORELOS |
| ELECTRICAL-Rough | 7/14/2022 | Corrections Issued | CALEB MEISTER |
| ELECTRICAL-Rough | 7/20/2022 | Approved | ALAN MORELOS |
| Interior/Exterior Lathing | 7/20/2022 | Partial Approval | ALAN MORELOS |
| BUILDING-Rough-Frame | 8/1/2022 | Approved | RAUL OLAGI |
| Green Building Rough | 8/1/2022 | Approved | RAUL OLAGI |
| HVAC-Rough | 8/1/2022 | Approved | RAUL OLAGI |
| Verify Sprinkler Sign Off | 8/1/2022 | Approved | RAUL OLAGI |
| Insulation | 8/8/2022 | Approved | RAUL OLAGI |
| Drywall Nailing | 8/16/2022 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 11/7/2022 | Approved | RAUL OLAGI |
| Shower Pan | 11/7/2022 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 5/17/2023 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Final | 5/17/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 8/25/2023 | Corrections Issued | RAUL OLAGI |
| Footing/Foundation/Slab | 8/25/2023 | Approved | RAUL OLAGI |
| Green Building Final | 8/25/2023 | Approved | RAUL OLAGI |
| HVAC-Final | 8/25/2023 | Approved | RAUL OLAGI |
| PLUMBING-Final | 8/25/2023 | Corrections Issued | RAUL OLAGI |
| Smoke Detectors | 8/25/2023 | Approved | RAUL OLAGI |
| Final | 9/12/2023 | Corrections Issued | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 9/12/2023 | SGSOV Approved | RAUL OLAGI |
| Service/Power Release | 9/12/2023 | Not Ready for Inspection | RAUL OLAGI |
| ELECTRICAL-Final | 10/17/2023 | Approved | RAUL OLAGI |
| Final | 10/17/2023 | OK to Issue CofO | RAUL OLAGI |
| PLUMBING-Final | 10/17/2023 | Approved | RAUL OLAGI |
| Service/Power Release | 10/17/2023 | Approved | RAUL OLAGI |