5176 N CASPAR AVE 90041

Certificate Information: 5176 N CASPAR AVE 90041

Application / Permit
20010-10000-04513
Plan Check / Job No.
B20LA21759
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
A NEW 28'-6"X31' 2-STORY ADU (1,198 SF) WITH ATTACHED 1-CAR GARAGE (274 SF) PER ORDINANCE.
Permit Issued
Issued on 1/4/2022
Issuing Office
Current Status
CofO Issued on 11/18/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/24/2020 APPLICANT
Assigned to Plan Check Engineer 12/30/2020 CHUNG-WEN CHUANG
Corrections Issued 1/15/2021 CHUNG-WEN CHUANG
Quality Review Completed 1/27/2021 TIEN JEN WANG
Applicant returned to address corrections 11/22/2021 CHUNG-WEN CHUANG
Plan Check Approved 11/23/2021 CHUNG-WEN CHUANG
Issued 1/4/2022 APPLICANT
Building Plans Picked Up 1/7/2022 APPLICANT
CofO in Progress 11/10/2022 BRIAN SULLIVAN
CofO Issued 11/18/2022 DEROLD HAUFF
Permit Finaled 11/18/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/4/2021 JEANIE LAM
Permit Cleared 3/4/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 3/5/2021 JEANIE LAM
Sewer availability Cleared 3/5/2021 JEANIE LAM
Grading Pre-Inspection Cleared 3/15/2021 BRIAN MILLER
Construction near power lines Cleared 4/28/2021 RIDWAN HARDY
Hydrant and Access approval Cleared 4/30/2021 JOHN CONNEALLY
Low Impact Development Cleared 10/22/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 10/22/2021 ABDULLAH SADOZAI

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 2/28/2022 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 3/8/2022 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 3/21/2022 Partial Approval CRAIG VAUGHAN
Green Building Rough 3/21/2022 Not Ready for Inspection CRAIG VAUGHAN
Verify Sprinkler Sign Off 3/21/2022 Approved CRAIG VAUGHAN
Deputy Wood Construction 4/8/2022 Conditional Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 4/8/2022 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 4/8/2022 Partial Approval SCOTT FINNILA
PLUMBING-Rough 4/12/2022 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 4/21/2022 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 4/21/2022 Approved CRAIG VAUGHAN
HVAC-Rough 4/21/2022 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 5/2/2022 Approved CRAIG VAUGHAN
Green Building Rough 5/2/2022 Approved CRAIG VAUGHAN
Insulation 5/11/2022 Approved CHARLES BOGHOSKHAN
Interior/Exterior Lathing 5/11/2022 Approved CHARLES BOGHOSKHAN
Underground Mechanical 5/11/2022 Approved CHARLES BOGHOSKHAN
Drywall Nailing 5/16/2022 Approved SCOTT FINNILA
Interior/Exterior Lathing 6/1/2022 Partial Approval KATHRYN BUTTERWORTH
Shower Pan 6/1/2022 Approved KATHRYN BUTTERWORTH
ELECTRICAL-Final 7/8/2022 Corrections Issued ALIZAH MAYAGOITIA
HVAC-Final 7/12/2022 Conditional Approval CRAIG VAUGHAN
Gas Test 8/2/2022 Approved CRAIG VAUGHAN
PLUMBING-Final 8/2/2022 Approved CRAIG VAUGHAN
Gas Test 8/29/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
Final 11/9/2022 OK to Issue CofO BRIAN SULLIVAN
Footing/Foundation/Slab 11/9/2022 Approved BRIAN SULLIVAN
Green Building Final 11/9/2022 Approved BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 11/9/2022 SGSOV Approved BRIAN SULLIVAN
Service/Power Release 11/9/2022 Approved BRIAN SULLIVAN
Smoke Detectors 11/9/2022 Approved BRIAN SULLIVAN