6536 E MERIDIAN ST 90042
Certificate Information: 6536 E MERIDIAN ST 90042
- Application / Permit
- 20010-10000-04511
- Plan Check / Job No.
- B20LA21748
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 1-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(B)
- Permit Issued
- Issued on 6/10/2021
- Issuing Office
- Current Status
- CofO Issued on 11/2/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/30/2020 | DANIEL YIP |
| Corrections Issued | 1/7/2021 | DANIEL YIP |
| Quality Review Completed | 1/8/2021 | ALLEN MANALANSAN |
| Building Plans Picked Up | 1/14/2021 | APPLICANT |
| Applicant returned to address corrections | 5/5/2021 | DANIEL YIP |
| Plan Check Approved | 5/25/2021 | DANIEL YIP |
| Issued | 6/10/2021 | APPLICANT |
| CofO in Progress | 11/1/2022 | CRAIG VAUGHAN |
| CofO in Progress | 11/1/2022 | CRAIG VAUGHAN |
| Permit Finaled | 11/2/2022 | RONALD MYRICK |
| Permit Finaled | 11/2/2022 | RONALD MYRICK |
| CofO Issued | 11/2/2022 | RONALD MYRICK |
Permit Application Clearance Information
| HPOZ | Cleared | 1/11/2021 | KATIE DEBIASE |
| Miscellaneous | Cleared | 1/11/2021 | KATIE DEBIASE |
| Address approval | Cleared | 2/17/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 2/17/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 2/17/2021 | RENZ SORIANO |
| Grading Pre-Inspection | Cleared | 2/22/2021 | PATRICK MISCHLICH |
| Low Impact Development | Cleared | 3/3/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 3/23/2021 | THAN WIN |
| Hydrant and Access approval | Cleared | 4/26/2021 | MATTHEW CRAIG |
| GPI Written Notices | Cleared | 5/19/2021 | DANIEL YIP |
Contact Information
| Contractor | Jerahian Araz; Lic. No.: 1045340-B | 250 N COLLEGE PARK DR F36 UPLAND, CA 91786 |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/4/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| Underground Mechanical | 10/4/2021 | Partial Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 10/15/2021 | Corrections Issued | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 12/6/2021 | Corrections Issued | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 12/13/2021 | Approved | COREY HUPP |
| BUILDING-Rough-Frame | 2/28/2022 | Partial Approval | SCOTT FINNILA |
| ELECTRICAL-Rough | 2/28/2022 | Corrections Issued | SCOTT FINNILA |
| HVAC-Rough | 2/28/2022 | Corrections Issued | SCOTT FINNILA |
| PLUMBING-Rough | 2/28/2022 | Corrections Issued | SCOTT FINNILA |
| BUILDING-Rough-Frame | 3/11/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Green Building Rough | 3/11/2022 | Approved | CRAIG VAUGHAN |
| Rough-Elec/Plmb/HVAC | 3/11/2022 | Approved | CRAIG VAUGHAN |
| Sewer | 3/11/2022 | Approved | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 3/11/2022 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/14/2022 | Partial Approval | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 5/18/2022 | Corrections Issued | CRAIG VAUGHAN |
| HVAC-Rough | 5/18/2022 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 5/18/2022 | Approved | CRAIG VAUGHAN |
| Wood Frame | 5/18/2022 | Approved | CRAIG VAUGHAN |
| Insulation | 5/27/2022 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 6/6/2022 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 6/6/2022 | Partial Approval | CRAIG VAUGHAN |
| Shower Pan | 6/6/2022 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 6/21/2022 | Approved | AMY COLIN |
| ELECTRICAL-Final | 9/13/2022 | Corrections Issued | SCOTT FINNILA |
| HVAC-Final | 9/13/2022 | Corrections Issued | SCOTT FINNILA |
| PLUMBING-Final | 9/13/2022 | Corrections Issued | SCOTT FINNILA |
| BUILDING-Rough-Frame | 9/21/2022 | Approved | SCOTT FINNILA |
| ELECTRICAL-Final | 9/21/2022 | Approved | SCOTT FINNILA |
| Final | 9/21/2022 | Corrections Issued | SCOTT FINNILA |
| Green Building Final | 9/21/2022 | Corrections Issued | SCOTT FINNILA |
| HVAC-Final | 9/21/2022 | Approved | SCOTT FINNILA |
| PLUMBING-Final | 9/21/2022 | Approved | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 9/21/2022 | SGSOV Approved | SCOTT FINNILA |
| Service/Power Release | 9/21/2022 | Corrections Issued | SCOTT FINNILA |
| Smoke Detectors | 9/21/2022 | Approved | SCOTT FINNILA |
| Final | 10/31/2022 | OK to Issue CofO | CRAIG VAUGHAN |
| Gas Test | 10/31/2022 | Approved | CRAIG VAUGHAN |
| Green Building Final | 10/31/2022 | Approved | CRAIG VAUGHAN |
| Service/Power Release | 10/31/2022 | Approved | CRAIG VAUGHAN |