3428 S NORTON AVE 90018
Certificate Information: 3428 S NORTON AVE 90018
- Application / Permit
- 20010-10000-04505
- Plan Check / Job No.
- B20LA21692
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED 4-CAR GARAGE (REAR BLDG).
- Permit Issued
- Issued on 6/16/2021
- Issuing Office
- Current Status
- CofO Issued on 2/26/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/23/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/30/2020 | GARO TELMI |
| Corrections Issued | 1/6/2021 | GARO TELMI |
| Quality Review Completed | 1/14/2021 | WING SUEN |
| Building Plans Picked Up | 1/21/2021 | APPLICANT |
| Applicant returned to address corrections | 5/19/2021 | GARO TELMI |
| Plan Check Approved | 6/16/2021 | GARO TELMI |
| Issued | 6/16/2021 | APPLICANT |
| CofO in Progress | 2/23/2022 | STUART CHAPMAN |
| Permit Finaled | 2/26/2022 | DEROLD HAUFF |
| CofO Issued | 2/26/2022 | DEROLD HAUFF |
| Permit Finaled | 2/26/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Frnt yard landscape/Water mgmt | Cleared | 1/21/2021 | TERRI OSBORNE |
| Address approval | Cleared | 1/26/2021 | RENZ SORIANO |
| Highway dedication | Cleared | 1/26/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 1/27/2021 | RENZ SORIANO |
| Permit | Cleared | 1/27/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 1/28/2021 | RENZ SORIANO |
| Hydrant and Access approval | Cleared | 3/4/2021 | ROBERT DUFF |
| Low Impact Development | Cleared | 4/7/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 4/13/2021 | CELINA MORENO |
| Trees in Parkway | Cleared | 6/8/2021 | JOHN KIM |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/12/2021 | Corrections Issued | STUART CHAPMAN |
| Footing/Foundation/Slab | 8/16/2021 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/10/2021 | Partial Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/26/2021 | Corrections Issued | STUART CHAPMAN |
| BUILDING-Rough-Frame | 10/29/2021 | Corrections Issued | STUART CHAPMAN |
| ELECTRICAL-Rough | 10/29/2021 | Approved | STUART CHAPMAN |
| Green Building Rough | 10/29/2021 | Not Ready for Inspection | STUART CHAPMAN |
| HVAC-Rough | 10/29/2021 | Conditional Approval | STUART CHAPMAN |
| PLUMBING-Rough | 10/29/2021 | Approved | STUART CHAPMAN |
| Rough-Elec/Plmb/HVAC | 10/29/2021 | Approved | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 10/29/2021 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 11/1/2021 | Conditional Approval | STUART CHAPMAN |
| Green Building Rough | 11/1/2021 | Approved | STUART CHAPMAN |
| Insulation | 11/1/2021 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 11/1/2021 | Partial Approval | STUART CHAPMAN |
| Drywall Nailing | 11/9/2021 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 11/9/2021 | Approved | STUART CHAPMAN |
| ELECTRICAL-Rough | 1/5/2022 | Approved | STUART CHAPMAN |
| Pre-Inspection | 1/5/2022 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 2/7/2022 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 2/7/2022 | Corrections Issued | STUART CHAPMAN |
| Final | 2/7/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Green Building Final | 2/7/2022 | Approved | STUART CHAPMAN |
| HVAC-Final | 2/7/2022 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 2/7/2022 | Corrections Issued | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 2/7/2022 | SGSOV Approved | STUART CHAPMAN |
| Service/Power Release | 2/7/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Smoke Detectors | 2/7/2022 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 2/18/2022 | Approved | STUART CHAPMAN |
| Final | 2/18/2022 | Partial Approval | STUART CHAPMAN |
| HVAC-Final | 2/18/2022 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 2/18/2022 | Approved | STUART CHAPMAN |
| Service/Power Release | 2/18/2022 | Approved | STUART CHAPMAN |
| Special/Order Compliance | 2/18/2022 | Approved | STUART CHAPMAN |
| Final | 2/22/2022 | OK to Issue CofO | STUART CHAPMAN |