(N) 3 STORY SFD W/ ATT GARAGE
Permit Issued
Issued on 7/22/2021
Issuing Office
Current Status
CofO Issued on 4/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/20/2020 APPLICANT
Assigned to Plan Check Engineer 11/25/2020 HERNAN ARREOLA
Corrections Issued 11/30/2020 HERNAN ARREOLA
Quality Review Completed 12/4/2020 ALLEN MANALANSAN
Building Plans Picked Up 12/9/2020 APPLICANT
Plan Check Approved 7/12/2021 HERNAN ARREOLA
Plan Check Approved 7/12/2021 HERNAN ARREOLA
Issued 7/22/2021 APPLICANT
CofO in Progress 3/30/2022 STUART CHAPMAN
Permit Finaled 4/1/2022 DEROLD HAUFF
CofO Issued 4/1/2022 DEROLD HAUFF
Permit Finaled 4/1/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/23/2021 WALLIE JONG
Highway dedication Cleared 2/23/2021 WALLIE JONG
Permit Cleared 2/23/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 2/25/2021 WALLIE JONG
Sewer availability Cleared 2/25/2021 WALLIE JONG
Trees in Parkway Cleared 3/31/2021 JOHN KIM
Hydrant and Access approval Cleared 5/5/2021 KURT CORRAL
Low Impact Development Cleared 5/12/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 5/13/2021 WALLIE JONG

Contact Information

Contractor Arrow Construction Co; Lic. No.: 573067-B 18729 CLARK DALE AVE #C      ARTESIA, CA 90701
Contractor Owner-Builder       ,
Engineer Dorta,, Michael Rohrs; Lic. No.: C72538 2445 VIA SONOMA      PALOS VERDES ESTATES, CA 90274
Engineer Salehipour,, Sassan A; Lic. No.: GE2579 1290 N LAKE AVENUE #204      PASADENA, CA 91104

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/23/2021 Partial Approval STUART CHAPMAN
Sewer 7/23/2021 Corrections Issued STUART CHAPMAN
Footing/Foundation/Slab 8/2/2021 Corrections Issued ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 8/4/2021 Conditional Approval SCOTT FINNILA
Sewer 8/4/2021 Partial Inspection SCOTT FINNILA
Sewer 8/23/2021 Approved STUART CHAPMAN
Underground Mechanical 8/23/2021 Partial Approval STUART CHAPMAN
Deputy Drilled-In Anchors 10/20/2021 Conditional Approval JUSTIN HAWLEY
ELECTRICAL-Rough 10/20/2021 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 10/20/2021 Corrections Issued STUART CHAPMAN
HVAC-Rough 10/20/2021 Corrections Issued STUART CHAPMAN
PLUMBING-Rough 10/20/2021 Approved STUART CHAPMAN
BUILDING-Rough-Frame 10/26/2021 Corrections Issued STUART CHAPMAN
Green Building Rough 10/26/2021 Approved STUART CHAPMAN
Insulation 10/26/2021 Not Ready for Inspection STUART CHAPMAN
Interior/Exterior Lathing 10/26/2021 Partial Approval STUART CHAPMAN
MERV13>=Rough 10/26/2021 Approved STUART CHAPMAN
Verify Sprinkler Sign Off 10/26/2021 Approved STUART CHAPMAN
BUILDING-Rough-Frame 10/29/2021 Approved STUART CHAPMAN
HVAC-Rough 10/29/2021 Approved STUART CHAPMAN
Insulation 10/29/2021 Approved STUART CHAPMAN
Interior/Exterior Lathing 10/29/2021 Approved STUART CHAPMAN
Drywall Nailing 11/4/2021 Approved AMY COLIN
ELECTRICAL-Final 3/23/2022 Approved STUART CHAPMAN
Final 3/23/2022 Corrections Issued STUART CHAPMAN
Footing/Foundation/Slab 3/23/2022 Approved STUART CHAPMAN
Green Building Final 3/23/2022 Approved STUART CHAPMAN
HVAC-Final 3/23/2022 Approved STUART CHAPMAN
MERV13>=Final 3/23/2022 Approved STUART CHAPMAN
PLUMBING-Final 3/23/2022 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 3/23/2022 SGSOV Approved STUART CHAPMAN
Service/Power Release 3/23/2022 Not Ready for Inspection STUART CHAPMAN
Smoke Detectors 3/23/2022 Approved STUART CHAPMAN
BUILDING-Rough-Frame 3/29/2022 Approved STUART CHAPMAN
Final 3/29/2022 OK to Issue CofO STUART CHAPMAN
Service/Power Release 3/29/2022 Approved STUART CHAPMAN