9026 N WOODMAN AVE 91331
Certificate Information: 9026 N WOODMAN AVE 91331
- Application / Permit
- 20010-10000-04464
- Plan Check / Job No.
- B20LA21601
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (16) Laundry
- Work Description
- NEW CONSTRUCTION FOR COIN LAUNDRY BUILDING; NEW SHELL AND NEW INTERIOR FINISH.
- Permit Issued
- Issued on 8/9/2021
- Issuing Office
- Current Status
- CofO Issued on 12/26/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/23/2020 | ZAW HAN |
| Corrections Issued | 1/5/2021 | ZAW HAN |
| Quality Review Completed | 1/20/2021 | WING SUEN |
| Disabled Access Plans Picked Up | 2/2/2021 | APPLICANT |
| Green Plans Picked Up | 4/14/2021 | APPLICANT |
| Applicant returned to address corrections | 7/19/2021 | ZAW HAN |
| Plan Check Approved | 7/21/2021 | ZAW HAN |
| Issued | 8/9/2021 | APPLICANT |
| Building Plans Picked Up | 8/17/2021 | APPLICANT |
| CofO in Progress | 12/20/2023 | DANNY RODRIGUEZ |
| CofO Issued | 12/26/2023 | RICKEY JACKSON |
| Permit Finaled | 12/26/2023 | RICKEY JACKSON |
Permit Application Clearance Information
| Address approval | Cleared | 2/23/2021 | GABRIEL ROBLES |
| "Q" conditions | Cleared | 2/24/2021 | DANIEL CORONADO |
| ZA Case | Cleared | 2/24/2021 | DANIEL CORONADO |
| Highway dedication | Cleared | 3/8/2021 | GABRIEL ROBLES |
| Permit | Cleared | 3/8/2021 | GABRIEL ROBLES |
| Prkng lot landscape/Water mgmt | Cleared | 4/9/2021 | DANIEL CORONADO |
| Hydrant and Access approval | Cleared | 4/23/2021 | MATTHEW CRAIG |
| Sewer availability | Cleared | 5/5/2021 | GABRIEL ROBLES |
| DAS Clearance | Cleared | 6/2/2021 | ZAW HAN |
| Green Code | Cleared | 6/14/2021 | AARON COSTA |
| Low Impact Development | Cleared | 7/1/2021 | JORGE MEJIA LEMUS |
| Eng Process Fee Ord 176,300 | Cleared | 7/7/2021 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 7/7/2021 | CARLOS AGUILERA |
Contact Information
| Architect | , ; Lic. No.: C37928 | , |
| Contractor | Ubcon Inc; Lic. No.: 1058343-B | 3055 WILSHIRE BLVD #810 LOS ANGELES, CA 90010 |
| Engineer | Kim,, Hosang; Lic. No.: C67288 | 18759 WILLOWTREE LANE PORTER RANCH, CA 91326 |
| Engineer | Lee,, Sang Youck; Lic. No.: S3821 | 3531 BROOKHILL ST GLENDALE, CA 91214 |
Inspector Information
| JOHN KITCKO, (818) 374-1109 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grading Pre-Inspection | 9/28/2021 | Partial Inspection | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 11/19/2021 | Partial Inspection | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 12/7/2021 | Partial Approval | DANNY RODRIGUEZ |
| Deputy Reinf. Masonry | 12/15/2021 | Conditional Approval | DANNY RODRIGUEZ |
| Deputy Reinf. Masonry | 12/16/2021 | Conditional Approval | DANNY RODRIGUEZ |
| Deputy Reinf. Masonry | 12/20/2021 | Conditional Approval | JEFFREY DURAN |
| Green Building Rough | 12/21/2021 | Not Ready for Inspection | DANIEL VARNUM |
| Reinforced Masonry Frame | 12/21/2021 | Partial Approval | DANIEL VARNUM |
| Verify Sprinkler Sign Off | 12/21/2021 | Not Ready for Inspection | DANIEL VARNUM |
| Deputy Reinf. Masonry | 12/22/2021 | Conditional Approval | JEFFREY DURAN |
| Deputy Reinf. Masonry | 12/28/2021 | Conditional Approval | DANIEL VARNUM |
| Deputy Reinf. Masonry | 1/3/2022 | Approved | DANNY RODRIGUEZ |
| Deputy Reinf. Masonry | 1/4/2022 | Conditional Approval | DANNY RODRIGUEZ |
| Deputy Reinf. Masonry | 1/5/2022 | Approved | DANNY RODRIGUEZ |
| Green Building Rough | 1/5/2022 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Reinforced Masonry Frame | 1/5/2022 | Partial Approval | DANNY RODRIGUEZ |
| Verify Sprinkler Sign Off | 1/5/2022 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Deputy Reinf. Masonry | 1/6/2022 | Approved | DANNY RODRIGUEZ |
| Deputy Reinf. Masonry | 1/7/2022 | Approved | DANNY RODRIGUEZ |
| Deputy Steel/Welding | 1/7/2022 | Approved | DANNY RODRIGUEZ |
| Green Building Rough | 1/10/2022 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Reinforced Masonry Frame | 1/10/2022 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Verify Sprinkler Sign Off | 1/10/2022 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Green Building Rough | 1/12/2022 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Reinforced Masonry Frame | 1/12/2022 | Partial Approval | DANNY RODRIGUEZ |
| Verify Sprinkler Sign Off | 1/12/2022 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Deputy Reinf. Masonry | 1/13/2022 | Approved | DANNY RODRIGUEZ |
| Deputy Reinf. Masonry | 1/14/2022 | Approved | DANNY RODRIGUEZ |
| Deputy Reinf. Masonry | 1/26/2022 | Approved | DANNY RODRIGUEZ |
| Masonry Wall/Backfill | 1/26/2022 | Partial Approval | DANNY RODRIGUEZ |
| Deputy Reinf. Masonry | 1/27/2022 | Approved | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 2/8/2022 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 2/24/2022 | Partial Approval | DANNY RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/27/2022 | Corrections Issued | DANNY RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2022 | Partial Inspection | DANIEL VARNUM |
| Green Building Rough | 5/16/2022 | Not Ready for Inspection | DANIEL VARNUM |
| Verify Sprinkler Sign Off | 5/16/2022 | Not Ready for Inspection | DANIEL VARNUM |
| Wood Frame | 5/16/2022 | Partial Approval | DANIEL VARNUM |
| Deputy Drilled-In Anchors | 6/1/2022 | Conditional Approval | DANNY RODRIGUEZ |
| Insulation | 6/1/2022 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Interior/Exterior Lathing | 6/1/2022 | Partial Approval | DANNY RODRIGUEZ |
| Green Building Rough | 6/3/2022 | Corrections Issued | DANIEL VARNUM |
| Verify Sprinkler Sign Off | 6/3/2022 | No Access for Inspection | DANIEL VARNUM |
| Wood Frame | 6/3/2022 | Corrections Issued | DANIEL VARNUM |
| Green Building Rough | 6/17/2022 | Approved | DANIEL VARNUM |
| Verify Sprinkler Sign Off | 6/17/2022 | Approved | DANIEL VARNUM |
| Wood Frame | 6/17/2022 | Partial Approval | DANIEL VARNUM |
| Drywall Nailing | 7/5/2022 | Approved | DANIEL VARNUM |
| Excavation/Setback/Form/Re-Bar | 8/12/2022 | Partial Approval | DANIEL VARNUM |
| Excavation/Setback/Form/Re-Bar | 6/7/2023 | Partial Inspection | DANNY RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 6/15/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Final | 8/7/2023 | Partial Inspection | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 8/7/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Green Building Final | 8/7/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Reinforced Masonry Frame | 8/7/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 8/7/2023 | SGSOV Not Ready | DANNY RODRIGUEZ |
| Smoke Detectors | 8/7/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Structural Steel Frame | 8/7/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Wood Frame | 8/7/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Final | 11/29/2023 | Not Ready for Inspection | JEFFREY DURAN |
| Footing/Foundation/Slab | 11/29/2023 | Not Ready for Inspection | JEFFREY DURAN |
| Green Building Final | 11/29/2023 | Not Ready for Inspection | JEFFREY DURAN |
| Reinforced Masonry Frame | 11/29/2023 | Not Ready for Inspection | JEFFREY DURAN |
| SGSOV-Seismic Gas S/O Valve | 11/29/2023 | SGSOV Not Ready | JEFFREY DURAN |
| Smoke Detectors | 11/29/2023 | Not Ready for Inspection | JEFFREY DURAN |
| Structural Steel Frame | 11/29/2023 | Not Ready for Inspection | JEFFREY DURAN |
| Wood Frame | 11/29/2023 | Not Ready for Inspection | JEFFREY DURAN |
| Final | 11/30/2023 | Not Ready for Inspection | CAMERON CHABAN |
| Footing/Foundation/Slab | 11/30/2023 | Partial Inspection | CAMERON CHABAN |
| Green Building Final | 11/30/2023 | Partial Inspection | CAMERON CHABAN |
| Reinforced Masonry Frame | 11/30/2023 | Partial Inspection | CAMERON CHABAN |
| SGSOV-Seismic Gas S/O Valve | 11/30/2023 | SGSOV Not Ready | CAMERON CHABAN |
| Smoke Detectors | 11/30/2023 | Approved | CAMERON CHABAN |
| Structural Steel Frame | 11/30/2023 | Partial Inspection | CAMERON CHABAN |
| Wood Frame | 11/30/2023 | Partial Inspection | CAMERON CHABAN |
| Final | 12/6/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 12/6/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Green Building Final | 12/6/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Reinforced Masonry Frame | 12/6/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 12/6/2023 | SGSOV Approved | DANNY RODRIGUEZ |
| Structural Steel Frame | 12/6/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Wood Frame | 12/6/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Final | 12/12/2023 | OK to Issue CofO | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 12/12/2023 | Approved | DANNY RODRIGUEZ |
| Green Building Final | 12/12/2023 | Approved | DANNY RODRIGUEZ |
| Reinforced Masonry Frame | 12/12/2023 | Approved | DANNY RODRIGUEZ |
| Structural Steel Frame | 12/12/2023 | Approved | DANNY RODRIGUEZ |
| Wood Frame | 12/12/2023 | Approved | DANNY RODRIGUEZ |