9026 N WOODMAN AVE 91331

Certificate Information: 9026 N WOODMAN AVE 91331

Application / Permit
20010-10000-04464
Plan Check / Job No.
B20LA21601
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(16) Laundry
Work Description
NEW CONSTRUCTION FOR COIN LAUNDRY BUILDING; NEW SHELL AND NEW INTERIOR FINISH.
Permit Issued
Issued on 8/9/2021
Issuing Office
Current Status
CofO Issued on 12/26/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/20/2020 APPLICANT
Assigned to Plan Check Engineer 12/23/2020 ZAW HAN
Corrections Issued 1/5/2021 ZAW HAN
Quality Review Completed 1/20/2021 WING SUEN
Disabled Access Plans Picked Up 2/2/2021 APPLICANT
Green Plans Picked Up 4/14/2021 APPLICANT
Applicant returned to address corrections 7/19/2021 ZAW HAN
Plan Check Approved 7/21/2021 ZAW HAN
Issued 8/9/2021 APPLICANT
Building Plans Picked Up 8/17/2021 APPLICANT
CofO in Progress 12/20/2023 DANNY RODRIGUEZ
CofO Issued 12/26/2023 RICKEY JACKSON
Permit Finaled 12/26/2023 RICKEY JACKSON

Permit Application Clearance Information

Address approval Cleared 2/23/2021 GABRIEL ROBLES
"Q" conditions Cleared 2/24/2021 DANIEL CORONADO
ZA Case Cleared 2/24/2021 DANIEL CORONADO
Highway dedication Cleared 3/8/2021 GABRIEL ROBLES
Permit Cleared 3/8/2021 GABRIEL ROBLES
Prkng lot landscape/Water mgmt Cleared 4/9/2021 DANIEL CORONADO
Hydrant and Access approval Cleared 4/23/2021 MATTHEW CRAIG
Sewer availability Cleared 5/5/2021 GABRIEL ROBLES
DAS Clearance Cleared 6/2/2021 ZAW HAN
Green Code Cleared 6/14/2021 AARON COSTA
Low Impact Development Cleared 7/1/2021 JORGE MEJIA LEMUS
Eng Process Fee Ord 176,300 Cleared 7/7/2021 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 7/7/2021 CARLOS AGUILERA

Contact Information

Architect , ; Lic. No.: C37928       ,
Contractor Ubcon Inc; Lic. No.: 1058343-B 3055 WILSHIRE BLVD #810      LOS ANGELES, CA 90010
Engineer Kim,, Hosang; Lic. No.: C67288 18759 WILLOWTREE LANE      PORTER RANCH, CA 91326
Engineer Lee,, Sang Youck; Lic. No.: S3821 3531 BROOKHILL ST      GLENDALE, CA 91214

Inspector Information

JOHN KITCKO, (818) 374-1109 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Grading Pre-Inspection 9/28/2021 Partial Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 11/19/2021 Partial Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 12/7/2021 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 12/15/2021 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 12/16/2021 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 12/20/2021 Conditional Approval JEFFREY DURAN
Green Building Rough 12/21/2021 Not Ready for Inspection DANIEL VARNUM
Reinforced Masonry Frame 12/21/2021 Partial Approval DANIEL VARNUM
Verify Sprinkler Sign Off 12/21/2021 Not Ready for Inspection DANIEL VARNUM
Deputy Reinf. Masonry 12/22/2021 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 12/28/2021 Conditional Approval DANIEL VARNUM
Deputy Reinf. Masonry 1/3/2022 Approved DANNY RODRIGUEZ
Deputy Reinf. Masonry 1/4/2022 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 1/5/2022 Approved DANNY RODRIGUEZ
Green Building Rough 1/5/2022 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 1/5/2022 Partial Approval DANNY RODRIGUEZ
Verify Sprinkler Sign Off 1/5/2022 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Masonry 1/6/2022 Approved DANNY RODRIGUEZ
Deputy Reinf. Masonry 1/7/2022 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 1/7/2022 Approved DANNY RODRIGUEZ
Green Building Rough 1/10/2022 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 1/10/2022 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 1/10/2022 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 1/12/2022 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 1/12/2022 Partial Approval DANNY RODRIGUEZ
Verify Sprinkler Sign Off 1/12/2022 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Masonry 1/13/2022 Approved DANNY RODRIGUEZ
Deputy Reinf. Masonry 1/14/2022 Approved DANNY RODRIGUEZ
Deputy Reinf. Masonry 1/26/2022 Approved DANNY RODRIGUEZ
Masonry Wall/Backfill 1/26/2022 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 1/27/2022 Approved DANNY RODRIGUEZ
Footing/Foundation/Slab 2/8/2022 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 2/24/2022 Partial Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 4/27/2022 Corrections Issued DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 5/16/2022 Partial Inspection DANIEL VARNUM
Green Building Rough 5/16/2022 Not Ready for Inspection DANIEL VARNUM
Verify Sprinkler Sign Off 5/16/2022 Not Ready for Inspection DANIEL VARNUM
Wood Frame 5/16/2022 Partial Approval DANIEL VARNUM
Deputy Drilled-In Anchors 6/1/2022 Conditional Approval DANNY RODRIGUEZ
Insulation 6/1/2022 Not Ready for Inspection DANNY RODRIGUEZ
Interior/Exterior Lathing 6/1/2022 Partial Approval DANNY RODRIGUEZ
Green Building Rough 6/3/2022 Corrections Issued DANIEL VARNUM
Verify Sprinkler Sign Off 6/3/2022 No Access for Inspection DANIEL VARNUM
Wood Frame 6/3/2022 Corrections Issued DANIEL VARNUM
Green Building Rough 6/17/2022 Approved DANIEL VARNUM
Verify Sprinkler Sign Off 6/17/2022 Approved DANIEL VARNUM
Wood Frame 6/17/2022 Partial Approval DANIEL VARNUM
Drywall Nailing 7/5/2022 Approved DANIEL VARNUM
Excavation/Setback/Form/Re-Bar 8/12/2022 Partial Approval DANIEL VARNUM
Excavation/Setback/Form/Re-Bar 6/7/2023 Partial Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 6/15/2023 Not Ready for Inspection DANNY RODRIGUEZ
Final 8/7/2023 Partial Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 8/7/2023 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Final 8/7/2023 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 8/7/2023 Not Ready for Inspection DANNY RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 8/7/2023 SGSOV Not Ready DANNY RODRIGUEZ
Smoke Detectors 8/7/2023 Not Ready for Inspection DANNY RODRIGUEZ
Structural Steel Frame 8/7/2023 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 8/7/2023 Not Ready for Inspection DANNY RODRIGUEZ
Final 11/29/2023 Not Ready for Inspection JEFFREY DURAN
Footing/Foundation/Slab 11/29/2023 Not Ready for Inspection JEFFREY DURAN
Green Building Final 11/29/2023 Not Ready for Inspection JEFFREY DURAN
Reinforced Masonry Frame 11/29/2023 Not Ready for Inspection JEFFREY DURAN
SGSOV-Seismic Gas S/O Valve 11/29/2023 SGSOV Not Ready JEFFREY DURAN
Smoke Detectors 11/29/2023 Not Ready for Inspection JEFFREY DURAN
Structural Steel Frame 11/29/2023 Not Ready for Inspection JEFFREY DURAN
Wood Frame 11/29/2023 Not Ready for Inspection JEFFREY DURAN
Final 11/30/2023 Not Ready for Inspection CAMERON CHABAN
Footing/Foundation/Slab 11/30/2023 Partial Inspection CAMERON CHABAN
Green Building Final 11/30/2023 Partial Inspection CAMERON CHABAN
Reinforced Masonry Frame 11/30/2023 Partial Inspection CAMERON CHABAN
SGSOV-Seismic Gas S/O Valve 11/30/2023 SGSOV Not Ready CAMERON CHABAN
Smoke Detectors 11/30/2023 Approved CAMERON CHABAN
Structural Steel Frame 11/30/2023 Partial Inspection CAMERON CHABAN
Wood Frame 11/30/2023 Partial Inspection CAMERON CHABAN
Final 12/6/2023 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 12/6/2023 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Final 12/6/2023 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 12/6/2023 Not Ready for Inspection DANNY RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 12/6/2023 SGSOV Approved DANNY RODRIGUEZ
Structural Steel Frame 12/6/2023 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 12/6/2023 Not Ready for Inspection DANNY RODRIGUEZ
Final 12/12/2023 OK to Issue CofO DANNY RODRIGUEZ
Footing/Foundation/Slab 12/12/2023 Approved DANNY RODRIGUEZ
Green Building Final 12/12/2023 Approved DANNY RODRIGUEZ
Reinforced Masonry Frame 12/12/2023 Approved DANNY RODRIGUEZ
Structural Steel Frame 12/12/2023 Approved DANNY RODRIGUEZ
Wood Frame 12/12/2023 Approved DANNY RODRIGUEZ