7047 N LONGRIDGE AVE 91605

Certificate Information: 7047 N LONGRIDGE AVE 91605

Application / Permit
20010-10000-04449
Plan Check / Job No.
B20LA21525
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan new ADU. New Detached ADU per ordinance 1-story
Permit Issued
Issued on 5/7/2021
Issuing Office
Current Status
CofO Issued on 8/5/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/27/2020 APPLICANT
Assigned to Plan Check Engineer 12/30/2020 CARLOS MONTES
Corrections Issued 1/5/2021 CARLOS MONTES
Quality Review Completed 1/14/2021 TU HUA
Plan Check Approved 5/3/2021 CARLOS MONTES
Issued 5/7/2021 APPLICANT
CofO in Progress 6/23/2022 CHRISTOPHE COCHRAN
Permit Finaled 8/5/2022 DANIEL ORRANTE
CofO Issued 8/5/2022 DANIEL ORRANTE
Permit Finaled 8/5/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 1/22/2021 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 1/22/2021 GUILLERMO PETRA
Sewer availability Cleared 1/22/2021 GUILLERMO PETRA
Hydrant and Access approval Cleared 3/4/2021 MATTHEW CRAIG
Low Impact Development Cleared 4/23/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 4/23/2021 GUILLERMO PETRA

Contact Information

Contractor Owner-Builder       ,
Engineer Kim,, Hong Kook; Lic. No.: C64529 3600 WILSHIRE BLVD STE 1903      LOS ANGELES, CA 90010

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/7/2021 Partial Approval MICHEL ABAJAN
Footing/Foundation/Slab 7/16/2021 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 8/19/2021 Partial Approval CHRISTOPHE COCHRAN
ELECTRICAL-Rough 8/19/2021 Approved CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 8/19/2021 Approved CHRISTOPHE COCHRAN
Green Building Rough 8/19/2021 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 8/19/2021 Approved CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 8/19/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 9/1/2021 Approved CHRISTOPHE COCHRAN
HVAC-Rough 9/1/2021 Approved CHRISTOPHE COCHRAN
Shower Pan 9/1/2021 Approved CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 9/1/2021 Approved CHRISTOPHE COCHRAN
Insulation 9/8/2021 Approved CHRISTOPHE COCHRAN
Drywall Nailing 9/15/2021 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 9/27/2021 Approved LILIANA PORTILLO
Sewer 10/25/2021 Approved CHRISTOPHE COCHRAN
Final 11/18/2021 Corrections Issued CHRISTOPHE COCHRAN
Green Building Final 11/18/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 11/18/2021 SGSOV Approved CHRISTOPHE COCHRAN
Service/Power Release 11/18/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
Smoke Detectors 11/18/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
Final 11/29/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
Green Building Final 11/29/2021 Approved CHRISTOPHE COCHRAN
Service/Power Release 11/29/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
Smoke Detectors 11/29/2021 Approved CHRISTOPHE COCHRAN
Final 4/12/2022 Corrections Issued CHRISTOPHE COCHRAN
Service/Power Release 4/12/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
ELECTRICAL-Final 6/23/2022 Approved CHRISTOPHE COCHRAN
Final 6/23/2022 OK to Issue CofO CHRISTOPHE COCHRAN
Service/Power Release 6/23/2022 Approved CHRISTOPHE COCHRAN