7047 N LONGRIDGE AVE 91605
Certificate Information: 7047 N LONGRIDGE AVE 91605
- Application / Permit
- 20010-10000-04449
- Plan Check / Job No.
- B20LA21525
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan new ADU. New Detached ADU per ordinance 1-story
- Permit Issued
- Issued on 5/7/2021
- Issuing Office
- Current Status
- CofO Issued on 8/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/30/2020 | CARLOS MONTES |
| Corrections Issued | 1/5/2021 | CARLOS MONTES |
| Quality Review Completed | 1/14/2021 | TU HUA |
| Plan Check Approved | 5/3/2021 | CARLOS MONTES |
| Issued | 5/7/2021 | APPLICANT |
| CofO in Progress | 6/23/2022 | CHRISTOPHE COCHRAN |
| Permit Finaled | 8/5/2022 | DANIEL ORRANTE |
| CofO Issued | 8/5/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/5/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 1/22/2021 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 1/22/2021 | GUILLERMO PETRA |
| Sewer availability | Cleared | 1/22/2021 | GUILLERMO PETRA |
| Hydrant and Access approval | Cleared | 3/4/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 4/23/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 4/23/2021 | GUILLERMO PETRA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kim,, Hong Kook; Lic. No.: C64529 | 3600 WILSHIRE BLVD STE 1903 LOS ANGELES, CA 90010 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/7/2021 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 7/16/2021 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 8/19/2021 | Partial Approval | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 8/19/2021 | Approved | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2021 | Approved | CHRISTOPHE COCHRAN |
| Green Building Rough | 8/19/2021 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 8/19/2021 | Approved | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 8/19/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 9/1/2021 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Rough | 9/1/2021 | Approved | CHRISTOPHE COCHRAN |
| Shower Pan | 9/1/2021 | Approved | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 9/1/2021 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 9/8/2021 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 9/15/2021 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 9/27/2021 | Approved | LILIANA PORTILLO |
| Sewer | 10/25/2021 | Approved | CHRISTOPHE COCHRAN |
| Final | 11/18/2021 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 11/18/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 11/18/2021 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Service/Power Release | 11/18/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Smoke Detectors | 11/18/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Final | 11/29/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Green Building Final | 11/29/2021 | Approved | CHRISTOPHE COCHRAN |
| Service/Power Release | 11/29/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Smoke Detectors | 11/29/2021 | Approved | CHRISTOPHE COCHRAN |
| Final | 4/12/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| Service/Power Release | 4/12/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| ELECTRICAL-Final | 6/23/2022 | Approved | CHRISTOPHE COCHRAN |
| Final | 6/23/2022 | OK to Issue CofO | CHRISTOPHE COCHRAN |
| Service/Power Release | 6/23/2022 | Approved | CHRISTOPHE COCHRAN |