4200 E ROLLE ST 90032

Certificate Information: 4200 E ROLLE ST 90032

Application / Permit
20010-10000-04443
Plan Check / Job No.
B20LA21493
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE. ***SHALL BE SPRINKLERED PER NFPA 13D*** . 1 OF 3
Permit Issued
Issued on 5/5/2022
Issuing Office
Current Status
CofO Corrected on 5/30/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/19/2020 APPLICANT
Assigned to Plan Check Engineer 11/25/2020 MICHAEL LOPEZ
Corrections Issued 12/7/2020 MICHAEL LOPEZ
Quality Review Completed 12/22/2020 PRANITA SHAH
Applicant returned to address corrections 5/19/2021 MICHAEL LOPEZ
Applicant returned to address corrections 8/9/2021 MICHAEL LOPEZ
Applicant returned to address corrections 12/13/2021 MICHAEL LOPEZ
Applicant returned to address corrections 2/15/2022 MICHAEL LOPEZ
Applicant returned to address corrections 4/4/2022 MICHAEL LOPEZ
Plan Check Approved 4/14/2022 MICHAEL LOPEZ
Issued 5/5/2022 APPLICANT
Building Plans Picked Up 5/9/2022 APPLICANT
CofO in Progress 6/14/2024 ALIZAH MAYAGOITIA
CofO Issued-Status Void 7/3/2024 DEROLD HAUFF
Permit Finaled-Status Void 7/3/2024 DEROLD HAUFF
Re-Activate Permit 5/30/2025 DEROLD HAUFF
Permit Finaled 5/30/2025 DEROLD HAUFF
CofO Corrected 5/30/2025 DEROLD HAUFF
Permit Finaled 5/30/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/29/2020 CELINA MORENO
BHO/Hillside ordinance Cleared 12/29/2020 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 12/29/2020 CELINA MORENO
Highway dedication Cleared 12/29/2020 CELINA MORENO
Sewer availability Cleared 12/29/2020 CELINA MORENO
Hydrant and Access approval Cleared 1/28/2021 MATTHEW CRAIG
Trees in Parkway Cleared 1/28/2021 JOHN KIM
GPI Written Notices Cleared 5/19/2021 ROBERT HUGHES
Grading Pre-Inspection Cleared 5/19/2021 ROBERT HUGHES
Low Impact Development Cleared 7/8/2021 ORVAL HERNANDEZ-MARCI
Stormwater Pollution Mitigatn Cleared 7/8/2021 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 7/12/2021 CELINA MORENO
BHO/Hillside ordinance Cleared 8/27/2021 CELINA MORENO
BHO/Hillside ordinance Cleared 8/27/2021 CELINA MORENO
BHO/Hillside ordinance Cleared 8/27/2021 CELINA MORENO
BHO/Hillside ordinance Cleared 8/27/2021 CELINA MORENO
Permit Cleared 8/27/2021 CELINA MORENO
"D" conditions Cleared 10/8/2021 ANACANY HURTADO
"Q" conditions Cleared 10/8/2021 ANACANY HURTADO
ZI Cleared 10/8/2021 ANACANY HURTADO
Excavation more than 5-ft deep Cleared 3/24/2022 CALOSHA APPROVED

Contact Information

Contractor Owner-Builder       ,
Engineer Salehipour,, Sassan A; Lic. No.: GE2579 1290 N LAKE AVENUE #204      PASADENA, CA 91104
Engineer Samadzadeh,, Hooman Ali; Lic. No.: C87661 22430 CRISWELL ST      WEST HILLS, CA 91307
Geologist Hill,, Thomas George; Lic. No.: EG1100 3210 VAL VERDE      LONG BEACH, CA 90808

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/1/2022 Corrections Issued OSVALDO PARAMO
Piling/Pier/Caisson 7/5/2022 Partial Approval OSVALDO PARAMO
Deputy Reinf. Concrete 7/6/2022 Approved OSVALDO PARAMO
Piling/Pier/Caisson 7/6/2022 Approved OSVALDO PARAMO
Footing/Foundation/Slab 8/2/2022 Partial Approval OSVALDO PARAMO
PLUMBING-Rough 8/11/2022 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 8/15/2022 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 9/6/2022 Partial Approval OSVALDO PARAMO
BUILDING-Rough-Frame 10/3/2022 Not Ready for Inspection OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 10/3/2022 Corrections Issued OSVALDO PARAMO
Verify Sprinkler Sign Off 10/3/2022 Not Ready for Inspection OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 10/14/2022 Partial Inspection OSVALDO PARAMO
Footing/Foundation/Slab 10/14/2022 Corrections Issued OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 10/17/2022 Corrections Issued OSVALDO PARAMO
ELECTRICAL-Rough 11/3/2022 Corrections Issued OSVALDO PARAMO
HVAC-Rough 11/3/2022 Not Ready for Inspection OSVALDO PARAMO
PLUMBING-Rough 11/3/2022 Approved OSVALDO PARAMO
ELECTRICAL-Rough 11/8/2022 Approved OSVALDO PARAMO
HVAC-Rough 11/8/2022 Corrections Issued OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 11/18/2022 Partial Inspection OSVALDO PARAMO
BUILDING-Rough-Frame 12/7/2022 Corrections Issued OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 12/7/2022 Approved OSVALDO PARAMO
Green Building Rough 12/7/2022 Approved OSVALDO PARAMO
HVAC-Rough 12/7/2022 Approved OSVALDO PARAMO
Verify Sprinkler Sign Off 12/7/2022 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 12/12/2022 Not Ready for Inspection OSVALDO PARAMO
BUILDING-Rough-Frame 12/15/2022 Approved OSVALDO PARAMO
Interior/Exterior Lathing 12/15/2022 Partial Approval OSVALDO PARAMO
Insulation 12/20/2022 Approved OSVALDO PARAMO
Drywall Nailing 12/28/2022 Approved ALIZAH MAYAGOITIA
Shower Pan 12/28/2022 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 1/6/2023 Approved ALIZAH MAYAGOITIA
Special/Order Compliance 1/6/2023 Corrections Issued ALIZAH MAYAGOITIA
ELECTRICAL-Final 6/5/2023 Corrections Issued OSVALDO PARAMO
ELECTRICAL-Rough 6/12/2023 Approved OSVALDO PARAMO
PLUMBING-Final 6/12/2023 Corrections Issued OSVALDO PARAMO
HVAC-Final 6/14/2023 Corrections Issued OSVALDO PARAMO
PLUMBING-Final 6/14/2023 Approved OSVALDO PARAMO
ELECTRICAL-Final 6/15/2023 Partial Inspection OSVALDO PARAMO
ELECTRICAL-Final 6/23/2023 Approved OSVALDO PARAMO
HVAC-Final 6/23/2023 Approved OSVALDO PARAMO
Final 10/26/2023 Not Ready for Inspection OSVALDO PARAMO
Footing/Foundation/Slab 10/26/2023 Approved OSVALDO PARAMO
Green Building Final 10/26/2023 Not Ready for Inspection OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 10/26/2023 SGSOV Not Ready OSVALDO PARAMO
Service/Power Release 10/26/2023 Not Ready for Inspection OSVALDO PARAMO
Smoke Detectors 10/26/2023 Not Ready for Inspection OSVALDO PARAMO
Final 6/5/2024 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 6/5/2024 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 6/5/2024 SGSOV Approved ALIZAH MAYAGOITIA
Service/Power Release 6/5/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Smoke Detectors 6/5/2024 Approved ALIZAH MAYAGOITIA
Final 6/11/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Service/Power Release 6/11/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Final 6/13/2024 OK to Issue CofO ALIZAH MAYAGOITIA
Service/Power Release 6/13/2024 Approved ALIZAH MAYAGOITIA