4200 E ROLLE ST 90032
Certificate Information: 4200 E ROLLE ST 90032
- Application / Permit
- 20010-10000-04443
- Plan Check / Job No.
- B20LA21493
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE. ***SHALL BE SPRINKLERED PER NFPA 13D*** . 1 OF 3
- Permit Issued
- Issued on 5/5/2022
- Issuing Office
- Current Status
- CofO Corrected on 5/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/25/2020 | MICHAEL LOPEZ |
| Corrections Issued | 12/7/2020 | MICHAEL LOPEZ |
| Quality Review Completed | 12/22/2020 | PRANITA SHAH |
| Applicant returned to address corrections | 5/19/2021 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 8/9/2021 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 12/13/2021 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 2/15/2022 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 4/4/2022 | MICHAEL LOPEZ |
| Plan Check Approved | 4/14/2022 | MICHAEL LOPEZ |
| Issued | 5/5/2022 | APPLICANT |
| Building Plans Picked Up | 5/9/2022 | APPLICANT |
| CofO in Progress | 6/14/2024 | ALIZAH MAYAGOITIA |
| CofO Issued-Status Void | 7/3/2024 | DEROLD HAUFF |
| Permit Finaled-Status Void | 7/3/2024 | DEROLD HAUFF |
| Re-Activate Permit | 5/30/2025 | DEROLD HAUFF |
| Permit Finaled | 5/30/2025 | DEROLD HAUFF |
| CofO Corrected | 5/30/2025 | DEROLD HAUFF |
| Permit Finaled | 5/30/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/29/2020 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 12/29/2020 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 12/29/2020 | CELINA MORENO |
| Highway dedication | Cleared | 12/29/2020 | CELINA MORENO |
| Sewer availability | Cleared | 12/29/2020 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 1/28/2021 | MATTHEW CRAIG |
| Trees in Parkway | Cleared | 1/28/2021 | JOHN KIM |
| GPI Written Notices | Cleared | 5/19/2021 | ROBERT HUGHES |
| Grading Pre-Inspection | Cleared | 5/19/2021 | ROBERT HUGHES |
| Low Impact Development | Cleared | 7/8/2021 | ORVAL HERNANDEZ-MARCI |
| Stormwater Pollution Mitigatn | Cleared | 7/8/2021 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 7/12/2021 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 8/27/2021 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 8/27/2021 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 8/27/2021 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 8/27/2021 | CELINA MORENO |
| Permit | Cleared | 8/27/2021 | CELINA MORENO |
| "D" conditions | Cleared | 10/8/2021 | ANACANY HURTADO |
| "Q" conditions | Cleared | 10/8/2021 | ANACANY HURTADO |
| ZI | Cleared | 10/8/2021 | ANACANY HURTADO |
| Excavation more than 5-ft deep | Cleared | 3/24/2022 | CALOSHA APPROVED |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Salehipour,, Sassan A; Lic. No.: GE2579 | 1290 N LAKE AVENUE #204 PASADENA, CA 91104 |
| Engineer | Samadzadeh,, Hooman Ali; Lic. No.: C87661 | 22430 CRISWELL ST WEST HILLS, CA 91307 |
| Geologist | Hill,, Thomas George; Lic. No.: EG1100 | 3210 VAL VERDE LONG BEACH, CA 90808 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/1/2022 | Corrections Issued | OSVALDO PARAMO |
| Piling/Pier/Caisson | 7/5/2022 | Partial Approval | OSVALDO PARAMO |
| Deputy Reinf. Concrete | 7/6/2022 | Approved | OSVALDO PARAMO |
| Piling/Pier/Caisson | 7/6/2022 | Approved | OSVALDO PARAMO |
| Footing/Foundation/Slab | 8/2/2022 | Partial Approval | OSVALDO PARAMO |
| PLUMBING-Rough | 8/11/2022 | Partial Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 8/15/2022 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 9/6/2022 | Partial Approval | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 10/3/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 10/3/2022 | Corrections Issued | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 10/3/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 10/14/2022 | Partial Inspection | OSVALDO PARAMO |
| Footing/Foundation/Slab | 10/14/2022 | Corrections Issued | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2022 | Corrections Issued | OSVALDO PARAMO |
| ELECTRICAL-Rough | 11/3/2022 | Corrections Issued | OSVALDO PARAMO |
| HVAC-Rough | 11/3/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| PLUMBING-Rough | 11/3/2022 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Rough | 11/8/2022 | Approved | OSVALDO PARAMO |
| HVAC-Rough | 11/8/2022 | Corrections Issued | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2022 | Partial Inspection | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 12/7/2022 | Corrections Issued | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 12/7/2022 | Approved | OSVALDO PARAMO |
| Green Building Rough | 12/7/2022 | Approved | OSVALDO PARAMO |
| HVAC-Rough | 12/7/2022 | Approved | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 12/7/2022 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 12/12/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 12/15/2022 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 12/15/2022 | Partial Approval | OSVALDO PARAMO |
| Insulation | 12/20/2022 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 12/28/2022 | Approved | ALIZAH MAYAGOITIA |
| Shower Pan | 12/28/2022 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 1/6/2023 | Approved | ALIZAH MAYAGOITIA |
| Special/Order Compliance | 1/6/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 6/5/2023 | Corrections Issued | OSVALDO PARAMO |
| ELECTRICAL-Rough | 6/12/2023 | Approved | OSVALDO PARAMO |
| PLUMBING-Final | 6/12/2023 | Corrections Issued | OSVALDO PARAMO |
| HVAC-Final | 6/14/2023 | Corrections Issued | OSVALDO PARAMO |
| PLUMBING-Final | 6/14/2023 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Final | 6/15/2023 | Partial Inspection | OSVALDO PARAMO |
| ELECTRICAL-Final | 6/23/2023 | Approved | OSVALDO PARAMO |
| HVAC-Final | 6/23/2023 | Approved | OSVALDO PARAMO |
| Final | 10/26/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Footing/Foundation/Slab | 10/26/2023 | Approved | OSVALDO PARAMO |
| Green Building Final | 10/26/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 10/26/2023 | SGSOV Not Ready | OSVALDO PARAMO |
| Service/Power Release | 10/26/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Smoke Detectors | 10/26/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Final | 6/5/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Final | 6/5/2024 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 6/5/2024 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 6/5/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Smoke Detectors | 6/5/2024 | Approved | ALIZAH MAYAGOITIA |
| Final | 6/11/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Service/Power Release | 6/11/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Final | 6/13/2024 | OK to Issue CofO | ALIZAH MAYAGOITIA |
| Service/Power Release | 6/13/2024 | Approved | ALIZAH MAYAGOITIA |