2717 S LA BREA AVE 90016
Certificate Information: 2717 S LA BREA AVE 90016
- Application / Permit
- 20010-10000-04418
- Plan Check / Job No.
- B20LA21419
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 3-STORY SINGLE FAMILY DWELLING IN REAR
- Permit Issued
- Issued on 10/1/2021
- Issuing Office
- Current Status
- CofO Issued on 5/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/11/2021 | DANIEL YIP |
| Corrections Issued | 3/18/2021 | DANIEL YIP |
| Quality Review Completed | 3/19/2021 | JASON HEALEY |
| Applicant returned to address corrections | 4/28/2021 | DANIEL YIP |
| Plan Check Approved | 7/30/2021 | JASON HEALEY |
| Issued | 10/1/2021 | APPLICANT |
| Building Plans Picked Up | 10/5/2021 | APPLICANT |
| CofO in Progress | 5/5/2023 | JOSE AVILA |
| Permit Finaled | 5/7/2023 | DEROLD HAUFF |
| CofO Issued | 5/7/2023 | DEROLD HAUFF |
| Permit Finaled | 5/7/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/18/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 3/22/2021 | WALLIE JONG |
| Sewer availability | Cleared | 4/6/2021 | WALLIE JONG |
| Frnt yard landscape/Water mgmt | Cleared | 5/7/2021 | LAUREN PADICK |
| Hydrant and Access approval | Cleared | 5/10/2021 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 7/19/2021 | MARCO SANCHEZ |
Contact Information
| Architect | Feagins,, Larry; Lic. No.: C27009 | 669 N THIRD AVENUE UPLAND, CA 91786 |
| Engineer | Xiao,, Qiang; Lic. No.: S5289 | 1520 BROOKHOLLOW #45 SANTA ANA, CA 92705 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 12/27/2021 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 1/27/2022 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2022 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 4/29/2022 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 4/29/2022 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 5/12/2022 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 5/12/2022 | Corrections Issued | JOSE AVILA |
| BUILDING-Rough-Frame | 5/17/2022 | Corrections Issued | JOSE AVILA |
| Green Building Rough | 5/17/2022 | Approved | JOSE AVILA |
| Verify Sprinkler Sign Off | 5/17/2022 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 6/6/2022 | Corrections Issued | JOSE AVILA |
| BUILDING-Rough-Frame | 6/14/2022 | Conditional Approval | JOSE AVILA |
| Drywall Nailing | 6/28/2022 | Partial Inspection | JOSE AVILA |
| Insulation | 6/28/2022 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 8/10/2022 | Approved | JOSE AVILA |
| Drywall Nailing | 12/16/2022 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 12/16/2022 | Corrections Issued | JOSE AVILA |
| Final | 12/16/2022 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 12/16/2022 | Approved | JOSE AVILA |
| Green Building Final | 12/16/2022 | Corrections Issued | JOSE AVILA |
| HVAC-Final | 12/16/2022 | Corrections Issued | JOSE AVILA |
| PLUMBING-Final | 12/16/2022 | Corrections Issued | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 12/16/2022 | SGSOV Not Ready | JOSE AVILA |
| Service/Power Release | 12/16/2022 | Corrections Issued | JOSE AVILA |
| Smoke Detectors | 12/16/2022 | Corrections Issued | JOSE AVILA |
| Final | 2/28/2023 | Not Ready for Inspection | JOSE AVILA |
| Green Building Final | 2/28/2023 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 2/28/2023 | SGSOV Approved | JOSE AVILA |
| Smoke Detectors | 2/28/2023 | Approved | JOSE AVILA |
| Final | 3/31/2023 | Corrections Issued | JOSE AVILA |
| Service/Power Release | 3/31/2023 | Approved | JOSE AVILA |
| Final | 5/5/2023 | OK to Issue CofO | JOSE AVILA |