2719 S LA BREA AVE 90016

Certificate Information: 2719 S LA BREA AVE 90016

Application / Permit
20010-10000-04415
Plan Check / Job No.
B20LA21416
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 29'-7"X22'-9" 3-STORY SINGLE FAMILY DWELLING 1,865.40 SF (FRONT BUILDING). 1 OF 2
Permit Issued
Issued on 11/19/2021
Issuing Office
Current Status
CofO Issued on 5/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/25/2021 APPLICANT
Assigned to Plan Check Engineer 3/18/2021 CHUNG-WEN CHUANG
Corrections Issued 3/26/2021 CHUNG-WEN CHUANG
Quality Review Completed 4/4/2021 HERNAN ARREOLA
Applicant returned to address corrections 5/13/2021 CHUNG-WEN CHUANG
Applicant returned to address corrections 5/17/2021 CHUNG-WEN CHUANG
Applicant returned to address corrections 7/6/2021 CHUNG-WEN CHUANG
Applicant returned to address corrections 7/20/2021 CHUNG-WEN CHUANG
Applicant returned to address corrections 10/4/2021 CHUNG-WEN CHUANG
Plan Check Approved 10/28/2021 CHUNG-WEN CHUANG
Issued 11/19/2021 APPLICANT
Building Plans Picked Up 11/24/2021 APPLICANT
CofO in Progress 5/5/2023 JOSE AVILA
Permit Finaled 5/7/2023 DEROLD HAUFF
CofO Issued 5/7/2023 DEROLD HAUFF
Permit Finaled 5/7/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/1/2021 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 4/1/2021 ELAINE LEI
Permit Cleared 4/1/2021 ELAINE LEI
Sewer availability Cleared 4/1/2021 ELAINE LEI
ZA Case Cleared 4/13/2021 MIGUEL GAMBOA
ZA Case Cleared 4/13/2021 MIGUEL GAMBOA
ZA Case Cleared 4/13/2021 MIGUEL GAMBOA
Frnt yard landscape/Water mgmt Cleared 4/23/2021 LAUREN PADICK
Hydrant and Access approval Cleared 5/13/2021 MATTHEW CRAIG
Low Impact Development Cleared 7/27/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 8/13/2021 THAN WIN

Contact Information

Architect Feagins,, Larry; Lic. No.: C27009 669 N THIRD AVENUE      UPLAND, CA 91786
Engineer Lee,, Allen C; Lic. No.: GE2781 11823 SLAUSON AVE STE 46      SANTA FE SPRINGS, CA 90670
Engineer Xiao,, Qiang; Lic. No.: S5289 1520 BROOKHOLLOW #45      SANTA ANA, CA 92705

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/1/2021 Approved STUART CHAPMAN
Grading Pre-Inspection 12/7/2021 Partial Inspection JOSE AVILA
Underground Mechanical 1/10/2022 Partial Approval JOSE AVILA
Excavation/Setback/Form/Re-Bar 1/12/2022 Corrections Issued JOSE AVILA
Excavation/Setback/Form/Re-Bar 1/19/2022 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 2/4/2022 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 2/18/2022 Partial Approval JOSE AVILA
HVAC-Rough 4/29/2022 Corrections Issued JOSE AVILA
PLUMBING-Rough 4/29/2022 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 5/12/2022 Corrections Issued JOSE AVILA
PLUMBING-Rough 5/12/2022 Partial Approval JOSE AVILA
BUILDING-Rough-Frame 5/17/2022 Corrections Issued JOSE AVILA
Green Building Rough 5/17/2022 Approved JOSE AVILA
Verify Sprinkler Sign Off 5/17/2022 Approved JOSE AVILA
BUILDING-Rough-Frame 6/6/2022 Corrections Issued JOSE AVILA
BUILDING-Rough-Frame 6/14/2022 Conditional Approval JOSE AVILA
Drywall Nailing 6/28/2022 Partial Inspection JOSE AVILA
Insulation 6/28/2022 Approved JOSE AVILA
BUILDING-Rough-Frame 8/10/2022 Approved JOSE AVILA
ELECTRICAL-Rough 12/12/2022 Approved JOSE AVILA
HVAC-Rough 12/12/2022 Approved JOSE AVILA
PLUMBING-Rough 12/12/2022 Approved JOSE AVILA
Drywall Nailing 12/16/2022 Approved JOSE AVILA
ELECTRICAL-Final 12/16/2022 Corrections Issued JOSE AVILA
Final 12/16/2022 Corrections Issued JOSE AVILA
Green Building Final 12/16/2022 Corrections Issued JOSE AVILA
HVAC-Final 12/16/2022 Corrections Issued JOSE AVILA
PLUMBING-Final 12/16/2022 Corrections Issued JOSE AVILA
SGSOV-Seismic Gas S/O Valve 12/16/2022 SGSOV Not Ready JOSE AVILA
Service/Power Release 12/16/2022 Corrections Issued JOSE AVILA
Smoke Detectors 12/16/2022 Corrections Issued JOSE AVILA
Final 2/21/2023 Corrections Issued JOSE AVILA
Green Building Final 2/21/2023 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 2/21/2023 SGSOV Approved JOSE AVILA
Smoke Detectors 2/21/2023 Approved JOSE AVILA
Final 2/28/2023 Not Ready for Inspection JOSE AVILA
Final 3/31/2023 Corrections Issued JOSE AVILA
Service/Power Release 3/31/2023 Approved JOSE AVILA
Final 5/5/2023 OK to Issue CofO JOSE AVILA