823-823 1/2 E 83RD ST 90001
Certificate Information: 823-823 1/2 E 83RD ST 90001
- Application / Permit
- 20010-10000-04402
- Plan Check / Job No.
- B20LA21336
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2-STORY DUPLEX WITH ATTACHED 3 CAR GARAGE
- Permit Issued
- Issued on 4/13/2021
- Issuing Office
- Current Status
- CofO Issued on 11/29/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/18/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/23/2020 | GARO TELMI |
| Corrections Issued | 12/28/2020 | GARO TELMI |
| Quality Review Completed | 1/5/2021 | WING SUEN |
| Plan Check Approved | 3/24/2021 | GARO TELMI |
| Issued | 4/13/2021 | APPLICANT |
| Building Plans Picked Up | 4/15/2021 | APPLICANT |
| CofO in Progress | 9/14/2021 | JOHN KLARIN |
| Permit Finaled | 11/29/2021 | DEROLD HAUFF |
| CofO Issued | 11/29/2021 | DEROLD HAUFF |
| Permit Finaled | 11/29/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/20/2021 | ELAINE LEI |
| Highway dedication | Cleared | 1/20/2021 | ELAINE LEI |
| Eng Process Fee Ord 176,300 | Cleared | 1/21/2021 | ELAINE LEI |
| Low Impact Development | Cleared | 1/21/2021 | JORGE MEJIA LEMUS |
| Permit | Cleared | 1/21/2021 | ELAINE LEI |
| Sewer availability | Cleared | 1/21/2021 | ELAINE LEI |
| Roof/Waste drainage to street | Cleared | 1/22/2021 | CELINA MORENO |
| Trees in Parkway | Cleared | 1/25/2021 | JOHN KIM |
| Hydrant and Access approval | Cleared | 1/29/2021 | ROBERT DUFF |
| Green Code | Cleared | 3/24/2021 | GARO TELMI |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/7/2021 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 5/25/2021 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 5/25/2021 | Partial Approval | EUGENE CASSIDY |
| Insulation | 5/25/2021 | Partial Approval | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 5/25/2021 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2021 | Partial Approval | ALEJANDRO DE ARTOLA |
| Insulation | 5/28/2021 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 6/15/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2021 | Partial Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2021 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 7/2/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 7/2/2021 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 7/2/2021 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 7/2/2021 | Approved | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 7/2/2021 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 7/6/2021 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 7/6/2021 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 7/6/2021 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 7/6/2021 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 7/14/2021 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 7/14/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 7/14/2021 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 8/26/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 8/26/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 8/30/2021 | Partial Approval | ALEJANDRO DE ARTOLA |
| Final | 8/30/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 9/13/2021 | Approved | JOHN KLARIN |
| Final | 9/13/2021 | OK to Issue CofO | JOHN KLARIN |
| HVAC-Final | 9/13/2021 | Approved | JOHN KLARIN |
| PLUMBING-Final | 9/13/2021 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 9/13/2021 | SGSOV Approved | JOHN KLARIN |
| Service/Power Release | 9/13/2021 | Approved | JOHN KLARIN |
| Smoke Detectors | 9/13/2021 | Approved | JOHN KLARIN |
| Service/Power Release | 9/28/2021 | Approved | ALEJANDRO DE ARTOLA |