3017 3/4 S ALSACE AVE 90016

Certificate Information: 3017 3/4 S ALSACE AVE 90016

Application / Permit
20010-10000-04355
Plan Check / Job No.
B20LA21183
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2 STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d).
Permit Issued
Issued on 2/12/2022
Issuing Office
Current Status
CofO Issued on 2/19/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/13/2020 APPLICANT
Assigned to Plan Check Engineer 12/10/2020 DANIEL YIP
Corrections Issued 12/14/2020 DANIEL YIP
Quality Review Completed 12/18/2020 JASON HEALEY
Building Plans Picked Up 12/21/2020 APPLICANT
Plan Check Approved 2/2/2021 DANIEL YIP
Issued 2/12/2022 APPLICANT
CofO in Progress 1/23/2024 STUART CHAPMAN
Permit Finaled 2/19/2024 DEROLD HAUFF
CofO Issued 2/19/2024 DEROLD HAUFF
Permit Finaled 2/19/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/5/2021 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 1/6/2021 THOMAS LANG
Sewer availability Cleared 1/6/2021 THOMAS LANG
Roof/Waste drainage to street Cleared 1/15/2021 THOMAS LANG
Tenant Habitability Plan Cleared 1/29/2021 MICHAEL SOTO

Contact Information

Contractor Apel Construction Inc; Lic. No.: 1051980-B 15030 VENTURA BLVD #399      SHERMAN OAKS, CA 91403
Engineer Kim,, Hosang; Lic. No.: C67288 18759 WILLOWTREE LANE      PORTER RANCH, CA 91326

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/1/2022 Approved JOSE AVILA
ELECTRICAL-Rough 8/8/2022 Corrections Issued JOSE AVILA
Drywall Nailing 9/28/2022 Corrections Issued JOSE AVILA
Green Building Rough 9/28/2022 Corrections Issued JOSE AVILA
PLUMBING-Rough 2/27/2023 Partial Approval JOSE AVILA
Excavation/Setback/Form/Re-Bar 3/31/2023 Corrections Issued JOSE AVILA
Special/Order Compliance 5/11/2023 Approved JOSE AVILA
Excavation/Setback/Form/Re-Bar 5/18/2023 Corrections Issued JOSE AVILA
Excavation/Setback/Form/Re-Bar 5/26/2023 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 7/18/2023 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 8/8/2023 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 8/18/2023 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 8/22/2023 Partial Approval JOSE AVILA
Drywall Nailing 9/7/2023 Partial Approval ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 9/27/2023 Corrections Issued JOSE AVILA
HVAC-Rough 10/12/2023 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 10/17/2023 Partial Approval JOSE AVILA
PLUMBING-Rough 10/17/2023 Approved JOSE AVILA
BUILDING-Rough-Frame 10/26/2023 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 10/26/2023 Approved JOSE AVILA
Green Building Rough 10/26/2023 Approved JOSE AVILA
HVAC-Rough 10/26/2023 Approved JOSE AVILA
Verify Sprinkler Sign Off 10/26/2023 Approved JOSE AVILA
BUILDING-Rough-Frame 11/15/2023 Approved JUSTIN HAWLEY
Green Building Rough 11/15/2023 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 11/15/2023 Partial Approval JUSTIN HAWLEY
Insulation 11/20/2023 Approved JOSE AVILA
Drywall Nailing 11/22/2023 Not Ready for Inspection LILIANA PORTILLO
Drywall Nailing 11/29/2023 Approved RONNIE MINDANAO
Final 12/28/2023 Corrections Issued SCOTT FINNILA
Footing/Foundation/Slab 12/28/2023 Approved SCOTT FINNILA
Green Building Final 12/28/2023 Approved SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 12/28/2023 SGSOV Approved SCOTT FINNILA
Service/Power Release 12/28/2023 Approved SCOTT FINNILA
Smoke Detectors 12/28/2023 Approved SCOTT FINNILA
Final 1/5/2024 Corrections Issued RONNIE MINDANAO
Final 1/12/2024 Corrections Issued RONNIE MINDANAO
ELECTRICAL-Final 1/22/2024 Approved STUART CHAPMAN
Final 1/22/2024 OK to Issue CofO STUART CHAPMAN
HVAC-Final 1/22/2024 Approved STUART CHAPMAN
PLUMBING-Final 1/22/2024 Approved STUART CHAPMAN
Service/Power Release 1/22/2024 Approved STUART CHAPMAN