3017 3/4 S ALSACE AVE 90016
Certificate Information: 3017 3/4 S ALSACE AVE 90016
- Application / Permit
- 20010-10000-04355
- Plan Check / Job No.
- B20LA21183
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2 STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d).
- Permit Issued
- Issued on 2/12/2022
- Issuing Office
- Current Status
- CofO Issued on 2/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/10/2020 | DANIEL YIP |
| Corrections Issued | 12/14/2020 | DANIEL YIP |
| Quality Review Completed | 12/18/2020 | JASON HEALEY |
| Building Plans Picked Up | 12/21/2020 | APPLICANT |
| Plan Check Approved | 2/2/2021 | DANIEL YIP |
| Issued | 2/12/2022 | APPLICANT |
| CofO in Progress | 1/23/2024 | STUART CHAPMAN |
| Permit Finaled | 2/19/2024 | DEROLD HAUFF |
| CofO Issued | 2/19/2024 | DEROLD HAUFF |
| Permit Finaled | 2/19/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/5/2021 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 1/6/2021 | THOMAS LANG |
| Sewer availability | Cleared | 1/6/2021 | THOMAS LANG |
| Roof/Waste drainage to street | Cleared | 1/15/2021 | THOMAS LANG |
| Tenant Habitability Plan | Cleared | 1/29/2021 | MICHAEL SOTO |
Contact Information
| Contractor | Apel Construction Inc; Lic. No.: 1051980-B | 15030 VENTURA BLVD #399 SHERMAN OAKS, CA 91403 |
| Engineer | Kim,, Hosang; Lic. No.: C67288 | 18759 WILLOWTREE LANE PORTER RANCH, CA 91326 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/1/2022 | Approved | JOSE AVILA |
| ELECTRICAL-Rough | 8/8/2022 | Corrections Issued | JOSE AVILA |
| Drywall Nailing | 9/28/2022 | Corrections Issued | JOSE AVILA |
| Green Building Rough | 9/28/2022 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 2/27/2023 | Partial Approval | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 3/31/2023 | Corrections Issued | JOSE AVILA |
| Special/Order Compliance | 5/11/2023 | Approved | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 5/18/2023 | Corrections Issued | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 5/26/2023 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 7/18/2023 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 8/8/2023 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 8/18/2023 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2023 | Partial Approval | JOSE AVILA |
| Drywall Nailing | 9/7/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 9/27/2023 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 10/12/2023 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 10/17/2023 | Partial Approval | JOSE AVILA |
| PLUMBING-Rough | 10/17/2023 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 10/26/2023 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 10/26/2023 | Approved | JOSE AVILA |
| Green Building Rough | 10/26/2023 | Approved | JOSE AVILA |
| HVAC-Rough | 10/26/2023 | Approved | JOSE AVILA |
| Verify Sprinkler Sign Off | 10/26/2023 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 11/15/2023 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 11/15/2023 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 11/15/2023 | Partial Approval | JUSTIN HAWLEY |
| Insulation | 11/20/2023 | Approved | JOSE AVILA |
| Drywall Nailing | 11/22/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| Drywall Nailing | 11/29/2023 | Approved | RONNIE MINDANAO |
| Final | 12/28/2023 | Corrections Issued | SCOTT FINNILA |
| Footing/Foundation/Slab | 12/28/2023 | Approved | SCOTT FINNILA |
| Green Building Final | 12/28/2023 | Approved | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 12/28/2023 | SGSOV Approved | SCOTT FINNILA |
| Service/Power Release | 12/28/2023 | Approved | SCOTT FINNILA |
| Smoke Detectors | 12/28/2023 | Approved | SCOTT FINNILA |
| Final | 1/5/2024 | Corrections Issued | RONNIE MINDANAO |
| Final | 1/12/2024 | Corrections Issued | RONNIE MINDANAO |
| ELECTRICAL-Final | 1/22/2024 | Approved | STUART CHAPMAN |
| Final | 1/22/2024 | OK to Issue CofO | STUART CHAPMAN |
| HVAC-Final | 1/22/2024 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 1/22/2024 | Approved | STUART CHAPMAN |
| Service/Power Release | 1/22/2024 | Approved | STUART CHAPMAN |