12874 N NORRIS AVE 91342

Certificate Information: 12874 N NORRIS AVE 91342

Application / Permit
20010-10000-04348
Plan Check / Job No.
B20LA21160
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 25'0" X 32'0", 800 sf. DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d).
Permit Issued
Issued on 12/7/2021
Issuing Office
Current Status
CofO Issued on 1/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/18/2020 APPLICANT
Assigned to Plan Check Engineer 12/1/2020 STANLEY RAAP
Corrections Issued 12/9/2020 STANLEY RAAP
Applicant returned to address corrections 3/15/2021 FERNANDO FLORES
Applicant returned to address corrections 4/6/2021 RICARDO RAMIREZ
Applicant returned to address corrections 4/15/2021 FERNANDO FLORES
Applicant returned to address corrections 11/13/2021 SAMUEL GONZALEZ
Plan Check Approved 11/19/2021 SAMUEL GONZALEZ
Issued 12/7/2021 APPLICANT
Building Plans Picked Up 12/13/2021 APPLICANT
CofO in Progress 10/18/2023 KEVIN BERBERYAN
Permit Finaled 1/10/2024 RUBEN SALAS
CofO Issued 1/10/2024 RUBEN SALAS
Permit Finaled 1/10/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/22/2021 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 3/23/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 3/23/2021 JOHN TRIANTAFYLLOS
Hydrant and Access approval Cleared 5/20/2021 JOHN CONNEALLY
Low Impact Development Cleared 9/10/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 11/2/2021 DAGOVERTO GUERRERO

Contact Information

Contractor Financial Consulting Help Center; Lic. No.: 1030177-B 9651 BUSINESS CENTER DR STE B      RANCHO CUCAMONGA, CA 91730

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/13/2021 Corrections Issued JOHN HAYES
PLUMBING-Rough 12/13/2021 Not Ready for Inspection JOHN HAYES
Pre-Inspection 12/13/2021 Not Ready for Inspection JOHN HAYES
Excavation/Setback/Form/Re-Bar 1/7/2022 Partial Approval JOHN HAYES
Underground Mechanical 1/7/2022 Approved JOHN HAYES
Excavation/Setback/Form/Re-Bar 2/4/2022 Corrections Issued JOHN HAYES
Excavation/Setback/Form/Re-Bar 2/9/2022 Not Ready for Inspection JOHN HAYES
Excavation/Setback/Form/Re-Bar 2/17/2022 Not Ready for Inspection JOHN HAYES
Footing/Foundation/Slab 2/17/2022 Not Ready for Inspection JOHN HAYES
Excavation/Setback/Form/Re-Bar 2/18/2022 Not Ready for Inspection MICHAEL TEMPLE
Excavation/Setback/Form/Re-Bar 2/24/2022 Corrections Issued JOHN HAYES
Excavation/Setback/Form/Re-Bar 3/2/2022 Approved JOHN HAYES
BUILDING-Rough-Frame 4/13/2022 Partial Approval JOHN HAYES
Verify Sprinkler Sign Off 4/13/2022 Not Ready for Inspection JOHN HAYES
Wood Frame 4/13/2022 Partial Approval JOHN HAYES
Pre-Inspection 5/13/2022 Partial Approval JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 5/25/2022 Partial Approval JOHN HAYES
Underground Mechanical 5/25/2022 Partial Approval JOHN HAYES
Rough-Elec/Plmb/HVAC 7/7/2022 Corrections Issued ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 7/18/2022 Approved ARAM AVEDISIAN
Rough-Elec/Plmb/HVAC 7/18/2022 Corrections Issued ARAM AVEDISIAN
HVAC-Rough 7/27/2022 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Rough 7/27/2022 Partial Approval CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 8/2/2022 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 8/2/2022 Corrections Issued ARAM AVEDISIAN
PLUMBING-Rough 8/2/2022 Approved ARAM AVEDISIAN
Verify Sprinkler Sign Off 8/2/2022 Approved ARAM AVEDISIAN
Insulation 8/5/2022 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 8/5/2022 Partial Approval ARAM AVEDISIAN
Drywall Nailing 8/11/2022 Approved JENNIFER RABUCHIN
Shower Pan 8/18/2022 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 8/23/2022 Partial Approval ARAM AVEDISIAN
Final 5/9/2023 Corrections Issued ARAM AVEDISIAN
Footing/Foundation/Slab 5/9/2023 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 5/9/2023 SGSOV Not Ready ARAM AVEDISIAN
Service/Power Release 5/9/2023 Not Ready for Inspection ARAM AVEDISIAN
Smoke Detectors 5/9/2023 Approved ARAM AVEDISIAN
Final 10/17/2023 OK to Issue CofO KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 10/17/2023 SGSOV Approved KEVIN BERBERYAN
Service/Power Release 10/17/2023 Approved KEVIN BERBERYAN