20949 S NORMANDIE AVE 90501
Certificate Information: 20949 S NORMANDIE AVE 90501
- Application / Permit
- 20010-10000-04344
- Plan Check / Job No.
- B20LA21119
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU AT REAR OF LOT PER LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 11/3/2021
- Issuing Office
- Current Status
- CofO Issued on 9/30/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/25/2020 | RACHEL BEYENE |
| Corrections Issued | 12/2/2020 | RACHEL BEYENE |
| Applicant returned to address corrections | 8/10/2021 | RICARDO RAMIREZ |
| Applicant returned to address corrections | 8/25/2021 | LUKE GONZALES |
| Plan Check Approved | 10/26/2021 | RICARDO RAMIREZ |
| Issued | 11/3/2021 | APPLICANT |
| Building Plans Picked Up | 11/8/2021 | APPLICANT |
| CofO in Progress | 9/9/2022 | EUGENE CASSIDY |
| Permit Finaled | 9/30/2022 | DEROLD HAUFF |
| CofO Issued | 9/30/2022 | DEROLD HAUFF |
| Permit Finaled | 9/30/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/23/2021 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 3/24/2021 | ERIK BEASLEY |
| ZA Case | Cleared | 4/29/2021 | LAUREN PADICK |
| Construction near power lines | Cleared | 6/2/2021 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 6/11/2021 | KURT CORRAL |
| Low Impact Development | Cleared | 8/16/2021 | YVAINNE GALSIM |
| Roof/Waste drainage to street | Cleared | 8/16/2021 | CHINH DINH |
| Sewer availability | Cleared | 8/16/2021 | CHINH DINH |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Garcia,, Eddy Alexander; Lic. No.: S6159 | 17958 LULL ST RESEDA, CA 91335 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/15/2021 | Not Ready for Inspection | JOHN KLARIN |
| Pre-Inspection | 11/15/2021 | Approved | JOHN KLARIN |
| Sewer | 11/15/2021 | Approved | JOHN KLARIN |
| Excavation/Setback/Form/Re-Bar | 11/19/2021 | Approved | CRAIG DAVIS |
| BUILDING-Rough-Frame | 2/9/2022 | Partial Approval | EUGENE CASSIDY |
| Green Building Rough | 2/9/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 2/9/2022 | Corrections Issued | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 2/25/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Rough | 2/25/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 2/25/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Rough-Elec/Plmb/HVAC | 2/25/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 2/25/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Rough-Elec/Plmb/HVAC | 3/1/2022 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 3/2/2022 | Approved | EUGENE CASSIDY |
| Green Building Rough | 3/2/2022 | Approved | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 3/2/2022 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 3/7/2022 | Approved | EUGENE CASSIDY |
| Insulation | 3/15/2022 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 3/23/2022 | Approved | EUGENE CASSIDY |
| Shower Pan | 4/15/2022 | Approved | EUGENE CASSIDY |
| Final | 6/9/2022 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 6/9/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Rough-Elec/Plmb/HVAC | 6/9/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 6/9/2022 | SGSOV Not Ready | EUGENE CASSIDY |
| Smoke Detectors | 6/9/2022 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 7/6/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| HVAC-Final | 7/6/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Final | 7/6/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Final | 8/31/2022 | Corrections Issued | EUGENE CASSIDY |
| Final | 8/31/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Footing/Foundation/Slab | 8/31/2022 | Approved | EUGENE CASSIDY |
| Green Building Final | 8/31/2022 | Approved | EUGENE CASSIDY |
| HVAC-Final | 8/31/2022 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 8/31/2022 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 8/31/2022 | SGSOV Approved | EUGENE CASSIDY |
| Service/Power Release | 8/31/2022 | Not Required | EUGENE CASSIDY |
| ELECTRICAL-Final | 9/8/2022 | Approved | EUGENE CASSIDY |
| Final | 9/8/2022 | OK to Issue CofO | EUGENE CASSIDY |