20949 S NORMANDIE AVE 90501

Certificate Information: 20949 S NORMANDIE AVE 90501

Application / Permit
20010-10000-04344
Plan Check / Job No.
B20LA21119
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ADU AT REAR OF LOT PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 11/3/2021
Issuing Office
Current Status
CofO Issued on 9/30/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/12/2020 APPLICANT
Assigned to Plan Check Engineer 11/25/2020 RACHEL BEYENE
Corrections Issued 12/2/2020 RACHEL BEYENE
Applicant returned to address corrections 8/10/2021 RICARDO RAMIREZ
Applicant returned to address corrections 8/25/2021 LUKE GONZALES
Plan Check Approved 10/26/2021 RICARDO RAMIREZ
Issued 11/3/2021 APPLICANT
Building Plans Picked Up 11/8/2021 APPLICANT
CofO in Progress 9/9/2022 EUGENE CASSIDY
Permit Finaled 9/30/2022 DEROLD HAUFF
CofO Issued 9/30/2022 DEROLD HAUFF
Permit Finaled 9/30/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/23/2021 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 3/24/2021 ERIK BEASLEY
ZA Case Cleared 4/29/2021 LAUREN PADICK
Construction near power lines Cleared 6/2/2021 RIDWAN HARDY
Hydrant and Access approval Cleared 6/11/2021 KURT CORRAL
Low Impact Development Cleared 8/16/2021 YVAINNE GALSIM
Roof/Waste drainage to street Cleared 8/16/2021 CHINH DINH
Sewer availability Cleared 8/16/2021 CHINH DINH

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia,, Eddy Alexander; Lic. No.: S6159 17958 LULL ST      RESEDA, CA 91335

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/15/2021 Not Ready for Inspection JOHN KLARIN
Pre-Inspection 11/15/2021 Approved JOHN KLARIN
Sewer 11/15/2021 Approved JOHN KLARIN
Excavation/Setback/Form/Re-Bar 11/19/2021 Approved CRAIG DAVIS
BUILDING-Rough-Frame 2/9/2022 Partial Approval EUGENE CASSIDY
Green Building Rough 2/9/2022 Not Ready for Inspection EUGENE CASSIDY
Verify Sprinkler Sign Off 2/9/2022 Corrections Issued EUGENE CASSIDY
BUILDING-Rough-Frame 2/25/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Green Building Rough 2/25/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Interior/Exterior Lathing 2/25/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Rough-Elec/Plmb/HVAC 2/25/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Verify Sprinkler Sign Off 2/25/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Rough-Elec/Plmb/HVAC 3/1/2022 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 3/2/2022 Approved EUGENE CASSIDY
Green Building Rough 3/2/2022 Approved EUGENE CASSIDY
Verify Sprinkler Sign Off 3/2/2022 Approved EUGENE CASSIDY
Interior/Exterior Lathing 3/7/2022 Approved EUGENE CASSIDY
Insulation 3/15/2022 Approved EUGENE CASSIDY
Drywall Nailing 3/23/2022 Approved EUGENE CASSIDY
Shower Pan 4/15/2022 Approved EUGENE CASSIDY
Final 6/9/2022 Corrections Issued EUGENE CASSIDY
Green Building Final 6/9/2022 Not Ready for Inspection EUGENE CASSIDY
Rough-Elec/Plmb/HVAC 6/9/2022 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 6/9/2022 SGSOV Not Ready EUGENE CASSIDY
Smoke Detectors 6/9/2022 Approved EUGENE CASSIDY
ELECTRICAL-Final 7/6/2022 Not Ready for Inspection EUGENE CASSIDY
HVAC-Final 7/6/2022 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Final 7/6/2022 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Final 8/31/2022 Corrections Issued EUGENE CASSIDY
Final 8/31/2022 Not Ready for Inspection EUGENE CASSIDY
Footing/Foundation/Slab 8/31/2022 Approved EUGENE CASSIDY
Green Building Final 8/31/2022 Approved EUGENE CASSIDY
HVAC-Final 8/31/2022 Approved EUGENE CASSIDY
PLUMBING-Final 8/31/2022 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 8/31/2022 SGSOV Approved EUGENE CASSIDY
Service/Power Release 8/31/2022 Not Required EUGENE CASSIDY
ELECTRICAL-Final 9/8/2022 Approved EUGENE CASSIDY
Final 9/8/2022 OK to Issue CofO EUGENE CASSIDY