812-814 E 76TH PL 90001

Certificate Information: 812-814 E 76TH PL 90001

Application / Permit
20010-10000-04252
Plan Check / Job No.
B20LA20875
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 2 STORY DUPLEX WITH ATTACHED 3-CAR GARAGE
Permit Issued
Issued on 4/27/2021
Issuing Office
Current Status
CofO Issued on 10/23/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/9/2020 APPLICANT
Assigned to Plan Check Engineer 12/10/2020 CARLOS MONTES
Corrections Issued 12/14/2020 CARLOS MONTES
Quality Review Completed 12/21/2020 WING SUEN
Plan Check Approved 3/24/2021 CARLOS MONTES
Issued 4/27/2021 APPLICANT
Building Plans Picked Up 5/4/2021 APPLICANT
CofO in Progress 9/18/2021 EUGENE CASSIDY
Permit Finaled 10/23/2021 DEROLD HAUFF
CofO Issued 10/23/2021 DEROLD HAUFF
Permit Finaled 10/23/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/8/2021 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 1/13/2021 THOMAS LANG
Sewer availability Cleared 1/13/2021 THOMAS LANG
Low Impact Development Cleared 1/26/2021 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 2/9/2021 CELINA MORENO
Hydrant and Access approval Cleared 2/16/2021 MATTHEW CRAIG

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/14/2021 Conditional Approval ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 5/25/2021 Partial Approval ALEJANDRO DE ARTOLA
Underground Mechanical 5/25/2021 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 5/26/2021 Partial Approval ALEJANDRO DE ARTOLA
Insulation 5/26/2021 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 5/27/2021 Partial Approval ALEJANDRO DE ARTOLA
Insulation 5/27/2021 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 6/7/2021 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 6/25/2021 Partial Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 7/7/2021 Partial Approval ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 7/9/2021 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 7/9/2021 Approved ALEJANDRO DE ARTOLA
Green Building Rough 7/9/2021 Not Ready for Inspection ALEJANDRO DE ARTOLA
HVAC-Rough 7/9/2021 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 7/9/2021 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 7/9/2021 Corrections Issued ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 7/9/2021 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 7/13/2021 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 7/13/2021 Approved ALEJANDRO DE ARTOLA
HVAC-Final 7/13/2021 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 7/13/2021 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 7/13/2021 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 7/14/2021 Approved ALEJANDRO DE ARTOLA
Insulation 7/14/2021 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 7/21/2021 Approved HORACE FULTZ
Interior/Exterior Lathing 7/21/2021 Partial Approval HORACE FULTZ
ELECTRICAL-Final 9/16/2021 Approved EUGENE CASSIDY
Final 9/16/2021 OK to Issue CofO EUGENE CASSIDY
Footing/Foundation/Slab 9/16/2021 Approved EUGENE CASSIDY
Green Building Final 9/16/2021 Approved EUGENE CASSIDY
HVAC-Final 9/16/2021 Approved EUGENE CASSIDY
PLUMBING-Final 9/16/2021 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 9/16/2021 SGSOV Approved EUGENE CASSIDY
Service/Power Release 9/16/2021 Approved EUGENE CASSIDY
Smoke Detectors 9/16/2021 Approved EUGENE CASSIDY
Service/Power Release 9/17/2021 Approved EUGENE CASSIDY
Service/Power Release 9/21/2021 Approved EUGENE CASSIDY