20662 W QUEDO DR 91364
Certificate Information: 20662 W QUEDO DR 91364
- Application / Permit
- 20010-10000-04248
- Plan Check / Job No.
- B20LA20850
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED 1 STORY DETACHED ACCESSORY DEWLLING UNIT PER ENGINEEER DESIGN (800 SF MAX NEW CONSTRUCTION PER STATE LAW, CA Govt. 65852.2(e)(1)(B))
- Permit Issued
- Issued on 4/20/2021
- Issuing Office
- Current Status
- CofO Issued on 11/2/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/25/2020 | AUNG SOE |
| Corrections Issued | 11/30/2020 | AUNG SOE |
| Applicant returned to address corrections | 2/9/2021 | GEORGE ALVAREZ |
| Applicant returned to address corrections | 4/6/2021 | AUNG SOE |
| Plan Check Approved | 4/7/2021 | AUNG SOE |
| Building Plans Picked Up | 4/12/2021 | APPLICANT |
| Issued | 4/20/2021 | APPLICANT |
| CofO in Progress | 10/28/2022 | PETER FOLLING |
| Permit Finaled | 11/2/2022 | JOHN JANSON |
| CofO Issued | 11/2/2022 | JOHN JANSON |
| Permit Finaled | 11/2/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 12/22/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 1/11/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 1/11/2021 | JOHN TRIANTAFYLLOS |
| Low Impact Development | Cleared | 1/22/2021 | SARAH YOUSSEF |
| Hydrant and Access approval | Cleared | 2/10/2021 | JOHN CONNEALLY |
| Roof/Waste drainage to street | Cleared | 2/23/2021 | JOHN TRIANTAFYLLOS |
| Grading Pre-Inspection | Cleared | 4/5/2021 | PATRICK MISCHLICH |
Contact Information
| Contractor | Affordable Building Solutions Inc; Lic. No.: 1068574-B | 8885 SANDALWOOD CT RANCHO CUCAMONGA, CA 91730 |
| Engineer | Ramirez, Cid, Jose Carlos; Lic. No.: C91046 | 5164 N RATON CIR LONG BEACH, CA 90807 |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/21/2021 | Partial Approval | HENRY KIM |
| Pre-Inspection | 4/21/2021 | Corrections Issued | HENRY KIM |
| Excavation/Setback/Form/Re-Bar | 4/29/2021 | Off-Hour Fees Due | |
| Footing/Foundation/Slab | 4/29/2021 | Off-Hour Fees Due | |
| Grading Pre-Inspection | 4/29/2021 | Off-Hour Fees Due | |
| PLUMBING-Rough | 4/29/2021 | Off-Hour Fees Due | |
| Pre-Inspection | 4/29/2021 | Off-Hour Fees Due | |
| Excavation/Setback/Form/Re-Bar | 4/30/2021 | Partial Approval | HENRY KIM |
| Footing/Foundation/Slab | 4/30/2021 | Not Ready for Inspection | HENRY KIM |
| Footing/Foundation/Slab | 4/30/2021 | Off-Hour Fees Due | |
| Grading Pre-Inspection | 4/30/2021 | Off-Hour Fees Due | |
| PLUMBING-Rough | 4/30/2021 | Off-Hour Fees Due | |
| PLUMBING-Rough | 4/30/2021 | Partial Approval | HENRY KIM |
| Pre-Inspection | 4/30/2021 | Corrections Issued | HENRY KIM |
| Pre-Inspection | 4/30/2021 | Off-Hour Fees Due | |
| Excavation/Setback/Form/Re-Bar | 5/4/2021 | Approved | HENRY KIM |
| Footing/Foundation/Slab | 5/4/2021 | Approved | HENRY KIM |
| PLUMBING-Rough | 5/4/2021 | Partial Approval | HENRY KIM |
| ELECTRICAL-Rough | 6/7/2021 | Corrections Issued | PETER FOLLING |
| Gas Test | 6/7/2021 | Not Ready for Inspection | PETER FOLLING |
| HVAC-Rough | 6/7/2021 | Corrections Issued | PETER FOLLING |
| PLUMBING-Rough | 6/7/2021 | Approved | PETER FOLLING |
| Wood Frame | 6/7/2021 | Not Ready for Inspection | PETER FOLLING |
| ELECTRICAL-Rough | 6/11/2021 | Not Ready for Inspection | PETER FOLLING |
| Floor/Roof Diaphrgm/Shear Wall | 6/11/2021 | Approved | PETER FOLLING |
| Gas Test | 6/11/2021 | Not Ready for Inspection | PETER FOLLING |
| Interior/Exterior Lathing | 8/2/2021 | Corrections Issued | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 8/4/2021 | Corrections Issued | PETER FOLLING |
| HVAC-Rough | 8/4/2021 | Corrections Issued | PETER FOLLING |
| Interior/Exterior Lathing | 8/4/2021 | Not Ready for Inspection | PETER FOLLING |
| PLUMBING-Rough | 8/4/2021 | Approved | PETER FOLLING |
| ELECTRICAL-Rough | 8/10/2021 | Not Ready for Inspection | PETER FOLLING |
| HVAC-Rough | 8/10/2021 | Not Ready for Inspection | PETER FOLLING |
| Interior/Exterior Lathing | 8/10/2021 | Not Ready for Inspection | PETER FOLLING |
| ELECTRICAL-Rough | 8/16/2021 | No Access for Inspection | PETER FOLLING |
| HVAC-Rough | 8/16/2021 | No Access for Inspection | PETER FOLLING |
| ELECTRICAL-Rough | 9/7/2021 | Approved | PETER FOLLING |
| HVAC-Rough | 9/7/2021 | Approved | PETER FOLLING |
| BUILDING-Rough-Frame | 9/8/2021 | Partial Approval | PETER FOLLING |
| Green Building Rough | 9/8/2021 | Approved | PETER FOLLING |
| HVAC-Rough | 9/8/2021 | Approved | PETER FOLLING |
| Insulation | 9/20/2021 | Corrections Issued | PETER FOLLING |
| Insulation | 9/28/2021 | Not Ready for Inspection | PETER FOLLING |
| Shower Pan | 9/28/2021 | Approved | PETER FOLLING |
| Insulation | 9/30/2021 | Approved | PETER FOLLING |
| Drywall Nailing | 10/12/2021 | Approved | MORRIS JACKSON |
| ELECTRICAL-Final | 3/8/2022 | Not Ready for Inspection | PETER FOLLING |
| Gas Test | 3/8/2022 | Not Ready for Inspection | PETER FOLLING |
| HVAC-Final | 3/8/2022 | Not Ready for Inspection | PETER FOLLING |
| PLUMBING-Final | 3/8/2022 | Not Ready for Inspection | PETER FOLLING |
| Sewer | 3/8/2022 | Corrections Issued | PETER FOLLING |
| Sewer | 4/4/2022 | Not Ready for Inspection | PETER FOLLING |
| Sewer | 5/3/2022 | Not Ready for Inspection | PETER FOLLING |
| Sewer | 5/10/2022 | Not Ready for Inspection | PETER FOLLING |
| Sewer | 5/17/2022 | Approved | HENRY KIM |
| BUILDING-Rough-Frame | 7/8/2022 | Approved | PETER FOLLING |
| Final | 7/8/2022 | Not Ready for Inspection | PETER FOLLING |
| Green Building Final | 7/8/2022 | Approved | PETER FOLLING |
| SGSOV-Seismic Gas S/O Valve | 7/8/2022 | SGSOV Not Ready | PETER FOLLING |
| Service/Power Release | 7/8/2022 | Not Ready for Inspection | PETER FOLLING |
| Smoke Detectors | 7/8/2022 | Not Ready for Inspection | PETER FOLLING |
| Verify Sprinkler Sign Off | 7/8/2022 | Approved | PETER FOLLING |
| SGSOV-Seismic Gas S/O Valve | 8/4/2022 | SGSOV Not Ready | DAVID SANDOVAL |
| Final | 8/12/2022 | Corrections Issued | PETER FOLLING |
| SGSOV-Seismic Gas S/O Valve | 8/12/2022 | SGSOV Not Ready | PETER FOLLING |
| Service/Power Release | 8/12/2022 | Not Ready for Inspection | PETER FOLLING |
| Smoke Detectors | 8/12/2022 | Approved | PETER FOLLING |
| Pre-Inspection | 8/30/2022 | Approved | TROY SANDERS |
| Final | 9/16/2022 | Corrections Issued | SEAN WIRCH |
| SGSOV-Seismic Gas S/O Valve | 9/16/2022 | SGSOV Approved | SEAN WIRCH |
| Service/Power Release | 9/16/2022 | Corrections Issued | SEAN WIRCH |
| Final | 10/26/2022 | Partial Approval | PETER FOLLING |
| Service/Power Release | 10/26/2022 | Approved | PETER FOLLING |
| Final | 10/27/2022 | OK to Issue CofO | PETER FOLLING |