16308 S DENVER AVE 90248
Certificate Information: 16308 S DENVER AVE 90248
- Application / Permit
- 20010-10000-04246
- Plan Check / Job No.
- B20LA20833
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU W/ 2-CAR GARAGE (2-STROY) PER ORDINANCE
- Permit Issued
- Issued on 10/17/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/28/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/17/2020 | CARLOS MONTES |
| Corrections Issued | 1/13/2021 | CARLOS MONTES |
| Quality Review Completed | 1/13/2021 | TU HUA |
| Building Plans Picked Up | 1/19/2021 | APPLICANT |
| Applicant returned to address corrections | 3/12/2021 | CARLOS MONTES |
| Plan Check Approved | 10/17/2022 | CARLOS MONTES |
| Issued | 10/17/2022 | APPLICANT |
| CofO in Progress | 11/28/2023 | JAMES CHAVEZ |
| CofO Issued | 11/28/2023 | ANSON MAGLASANG |
| Permit Finaled | 11/28/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 5/5/2021 | YEGANEH SADEGHI |
| Sewer availability | Cleared | 5/12/2021 | CHINH DINH |
| Hydrant and Access approval | Cleared | 6/27/2021 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 9/1/2022 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 9/7/2022 | JOSE HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/15/2022 | HUGO LOPEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Vo,, Tung Thanh; Lic. No.: C69546 | 9756 EMMONS CIR FOUNTAIN VALLEY, CA 92708 |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 12/13/2022 | Approved | JAMES CHAVEZ |
| Footing/Foundation/Slab | 12/19/2022 | Corrections Issued | JAMES CHAVEZ |
| Footing/Foundation/Slab | 12/30/2022 | Not Ready for Inspection | JAMES CHAVEZ |
| Footing/Foundation/Slab | 1/6/2023 | Approved | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/19/2023 | Approved | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2023 | Partial Inspection | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 2/27/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| ELECTRICAL-Rough | 2/27/2023 | Approved | JAMES CHAVEZ |
| Green Building Rough | 2/27/2023 | Approved | JAMES CHAVEZ |
| HVAC-Rough | 2/27/2023 | Approved | JAMES CHAVEZ |
| MERV13>=Rough | 2/27/2023 | Approved | JAMES CHAVEZ |
| PLUMBING-Rough | 2/27/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Sewer | 2/27/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Verify Sprinkler Sign Off | 2/27/2023 | Approved | JAMES CHAVEZ |
| PLUMBING-Rough | 3/1/2023 | Approved | JAMES CHAVEZ |
| Green Building Rough | 3/16/2023 | Approved | JAMES CHAVEZ |
| Shower Pan | 3/16/2023 | Approved | JAMES CHAVEZ |
| Insulation | 3/20/2023 | Approved | JAMES CHAVEZ |
| Drywall Nailing | 3/28/2023 | Approved | JAMES CHAVEZ |
| Interior/Exterior Lathing | 3/28/2023 | Partial Approval | JAMES CHAVEZ |
| Interior/Exterior Lathing | 4/27/2023 | Approved | JAMES CHAVEZ |
| Sewer | 4/27/2023 | Approved | JAMES CHAVEZ |
| Underground Mechanical | 4/27/2023 | Approved | JAMES CHAVEZ |
| Service/Power Release | 6/20/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 9/28/2023 | Approved | JAMES CHAVEZ |
| Final | 9/28/2023 | Corrections Issued | JAMES CHAVEZ |
| Gas Test | 9/28/2023 | Approved | JAMES CHAVEZ |
| Green Building Final | 9/28/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| MERV13>=Final | 9/28/2023 | Approved | JAMES CHAVEZ |
| SGSOV-Seismic Gas S/O Valve | 9/28/2023 | SGSOV Not Ready | JAMES CHAVEZ |
| Service/Power Release | 9/28/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Smoke Detectors | 9/28/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| ELECTRICAL-Final | 10/19/2023 | Approved | JAMES CHAVEZ |
| Gas Test | 10/19/2023 | Approved | JAMES CHAVEZ |
| Green Building Final | 10/19/2023 | Approved | JAMES CHAVEZ |
| HVAC-Final | 10/19/2023 | Approved | JAMES CHAVEZ |
| PLUMBING-Final | 10/19/2023 | Approved | JAMES CHAVEZ |
| Service/Power Release | 10/19/2023 | Approved | JAMES CHAVEZ |
| Smoke Detectors | 10/19/2023 | Approved | JAMES CHAVEZ |
| Final | 11/28/2023 | OK to Issue CofO | JAMES CHAVEZ |
| SGSOV-Seismic Gas S/O Valve | 11/28/2023 | SGSOV Approved | JAMES CHAVEZ |