5115 N BASCULE AVE 91364
Certificate Information: 5115 N BASCULE AVE 91364
- Application / Permit
- 20010-10000-04240
- Plan Check / Job No.
- B20LA20820
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 1-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33(c)-(d)
- Permit Issued
- Issued on 3/18/2022
- Issuing Office
- Current Status
- CofO in Progress on 3/9/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/25/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/30/2020 | DANIEL YIP |
| Corrections Issued | 1/5/2021 | DANIEL YIP |
| Quality Review Completed | 1/12/2021 | ALLEN MANALANSAN |
| Applicant returned to address corrections | 4/15/2021 | DANIEL YIP |
| Plan Check Approved | 8/9/2021 | DANIEL YIP |
| Issued | 3/18/2022 | APPLICANT |
| Building Plans Picked Up | 3/22/2022 | APPLICANT |
| CofO in Progress | 3/9/2026 | JOHN HAYES |
Permit Application Clearance Information
| Address approval | Cleared | 4/21/2021 | JOHN TRIANTAFYLLOS |
| Hydrant and Access approval | Cleared | 4/21/2021 | MATTHEW CRAIG |
| ZA Case | Cleared | 4/21/2021 | JASON CHAN |
| Eng Process Fee Ord 176,300 | Cleared | 4/26/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 4/26/2021 | JOHN TRIANTAFYLLOS |
| GPI Written Notices | Cleared | 5/5/2021 | DANIEL YIP |
| Grading Pre-Inspection | Cleared | 5/5/2021 | DANIEL YIP |
| Low Impact Development | Cleared | 7/20/2021 | TA ANH |
| Roof/Waste drainage to street | Cleared | 7/31/2021 | CARLOS AGUILERA |
Contact Information
| Architect | Tam,, Anthony G; Lic. No.: C32145 | 107 S FAIR OAKS 213 PASADENA, CA 91105 |
| Contractor | Premier; Lic. No.: 654493-B | 3155 SAPPHIRE ST SIMI VALLEY, CA 93063 |
| Engineer | Jung,, Jason Stanley; Lic. No.: C80569 | 106 N ROSEMEAD BLVD STE 204 PASADENA, CA 91107 |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/11/2022 | Approved | PETER FOLLING |
| BUILDING-Rough-Frame | 5/17/2022 | Not Ready for Inspection | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 5/17/2022 | Corrections Issued | HENRY KIM |
| PLUMBING-Rough | 5/17/2022 | Partial Approval | HENRY KIM |
| Verify Sprinkler Sign Off | 5/17/2022 | Corrections Issued | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2022 | Partial Approval | PETER FOLLING |
| Drywall Nailing | 8/24/2022 | Not Ready for Inspection | PETER FOLLING |
| Floor/Roof Diaphrgm/Shear Wall | 8/24/2022 | Partial Approval | PETER FOLLING |
| Green Building Rough | 8/24/2022 | Not Ready for Inspection | PETER FOLLING |
| Underground Mechanical | 8/24/2022 | Approved | PETER FOLLING |
| Deputy Wood Construction | 8/31/2022 | No Access for Inspection | PETER FOLLING |
| BUILDING-Rough-Frame | 9/28/2022 | Not Ready for Inspection | PETER FOLLING |
| ELECTRICAL-Rough | 9/28/2022 | Approved | PETER FOLLING |
| Green Building Rough | 9/28/2022 | Not Ready for Inspection | PETER FOLLING |
| PLUMBING-Rough | 9/28/2022 | Approved | PETER FOLLING |
| Underground Mechanical | 9/28/2022 | Corrections Issued | PETER FOLLING |
| Verify Sprinkler Sign Off | 9/28/2022 | Not Ready for Inspection | PETER FOLLING |
| Pre-Inspection | 10/14/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 11/2/2022 | Partial Approval | PETER FOLLING |
| Green Building Rough | 11/2/2022 | Not Ready for Inspection | PETER FOLLING |
| PLUMBING-Rough | 11/2/2022 | Approved | PETER FOLLING |
| Verify Sprinkler Sign Off | 11/2/2022 | Not Ready for Inspection | PETER FOLLING |
| Wood Frame | 11/2/2022 | Not Ready for Inspection | PETER FOLLING |
| BUILDING-Rough-Frame | 12/14/2022 | Approved | PETER FOLLING |
| Green Building Rough | 12/14/2022 | Approved | PETER FOLLING |
| HVAC-Rough | 12/14/2022 | Approved | PETER FOLLING |
| Verify Sprinkler Sign Off | 12/14/2022 | Approved | PETER FOLLING |
| Insulation | 12/21/2022 | Approved | MORRIS JACKSON |
| Drywall Nailing | 12/28/2022 | Approved | PETER FOLLING |
| Interior/Exterior Lathing | 2/14/2023 | Partial Approval | PETER FOLLING |
| Shower Pan | 2/14/2023 | Approved | PETER FOLLING |
| Sewer | 2/24/2023 | Not Ready for Inspection | PETER FOLLING |
| PLUMBING-Rough | 3/3/2023 | Corrections Issued | PETER FOLLING |
| Underground Mechanical | 3/3/2023 | Approved | PETER FOLLING |
| Final | 7/7/2023 | Corrections Issued | PETER FOLLING |
| Green Building Final | 7/7/2023 | Approved | PETER FOLLING |
| SGSOV-Seismic Gas S/O Valve | 7/7/2023 | SGSOV Approved | PETER FOLLING |
| Service/Power Release | 7/7/2023 | Not Ready for Inspection | PETER FOLLING |
| Smoke Detectors | 7/7/2023 | Approved | PETER FOLLING |
| Final | 12/19/2023 | Corrections Issued | JOHN KIDWELL |
| Service/Power Release | 12/19/2023 | Not Ready for Inspection | JOHN KIDWELL |
| Final | 11/21/2025 | OK to Issue CofO | JOHN HAYES |
| Service/Power Release | 11/21/2025 | Approved | JOHN HAYES |