8116 N FAUST AVE 91304
Certificate Information: 8116 N FAUST AVE 91304
- Application / Permit
- 20010-10000-04153
- Plan Check / Job No.
- B20LA20707
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan. New construction of an accessory dwelling unit in the rear yard.
- Permit Issued
- Issued on 7/14/2021
- Issuing Office
- Current Status
- CofO Issued on 11/3/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/17/2020 | ARSALAN SHABESTARI |
| Corrections Issued | 12/21/2020 | ARSALAN SHABESTARI |
| Quality Review Completed | 1/13/2021 | PRANITA SHAH |
| Plan Check Approved | 6/27/2021 | ARSALAN SHABESTARI |
| Issued | 7/14/2021 | APPLICANT |
| CofO in Progress | 10/17/2023 | CHRIS CHRISTENSEN |
| Permit Finaled | 11/3/2023 | JOHN JANSON |
| CofO Issued | 11/3/2023 | JOHN JANSON |
| Permit Finaled | 11/3/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 1/20/2021 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 1/21/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 1/21/2021 | JOHN TRIANTAFYLLOS |
| Hydrant and Access approval | Cleared | 3/1/2021 | KURT CORRAL |
| Construction near power lines | Cleared | 4/5/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 4/5/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 5/8/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 6/1/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/27/2021 | Approved | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 10/22/2021 | Partial Approval | DAVID STEPANYAN |
| PLUMBING-Rough | 10/22/2021 | Approved | DAVID STEPANYAN |
| Sewer | 10/22/2021 | Approved | DAVID STEPANYAN |
| Footing/Foundation/Slab | 11/5/2021 | Approved | DAVID STEPANYAN |
| PLUMBING-Rough | 11/5/2021 | Partial Approval | DAVID STEPANYAN |
| PLUMBING-Rough | 11/18/2021 | Partial Approval | DAVID STEPANYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2021 | Partial Approval | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 12/17/2021 | Approved | DAVID STEPANYAN |
| PLUMBING-Rough | 12/17/2021 | Approved | DAVID STEPANYAN |
| Deputy Wood Construction | 12/21/2021 | Approved | DAVID STEPANYAN |
| ELECTRICAL-Rough | 1/11/2022 | Approved | TROY SANDERS |
| HVAC-Rough | 1/11/2022 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 2/1/2022 | Approved | DAVID SCANTLIN |
| Green Building Rough | 2/1/2022 | Approved | DAVID SCANTLIN |
| Insulation | 2/24/2022 | Corrections Issued | JAVIER RAMOS JR |
| Insulation | 3/9/2022 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 3/9/2022 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 3/11/2022 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 2/15/2023 | Partial Approval | CHRIS CHRISTENSEN |
| Shower Pan | 2/15/2023 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 7/10/2023 | Approved | HORACE FULTZ |
| ELECTRICAL-Final | 10/12/2023 | Approved | CHRIS CHRISTENSEN |
| Final | 10/12/2023 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 10/12/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| HVAC-Final | 10/12/2023 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 10/12/2023 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 10/12/2023 | SGSOV Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 10/12/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Smoke Detectors | 10/12/2023 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 10/14/2023 | Off-Hour Fees Due | |
| HVAC-Final | 10/14/2023 | Off-Hour Fees Due | |
| PLUMBING-Final | 10/14/2023 | Off-Hour Fees Due | |
| Service/Power Release | 10/14/2023 | Off-Hour Fees Due | |
| ELECTRICAL-Final | 10/16/2023 | Approved | CHRIS CHRISTENSEN |
| Final | 10/16/2023 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Green Building Final | 10/16/2023 | Approved | CHRIS CHRISTENSEN |
| HVAC-Final | 10/16/2023 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 10/16/2023 | Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 10/16/2023 | Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 10/27/2023 | Approved | JEFFREY BULL |