2436-2436 1/2 E CINCINNATI ST 90033

Certificate Information: 2436-2436 1/2 E CINCINNATI ST 90033

Application / Permit
20010-10000-04149
Plan Check / Job No.
B20LA20698
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 3-STORY FRONT DUPLEX WITH ATTACHED GARAGE
Permit Issued
Issued on 4/14/2021
Issuing Office
Current Status
CofO Issued on 2/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/11/2020 APPLICANT
Assigned to Plan Check Engineer 12/17/2020 DANIEL YIP
Corrections Issued 12/22/2020 DANIEL YIP
Quality Review Completed 12/31/2020 ALLEN MANALANSAN
Plan Check Approved 4/14/2021 DANIEL YIP
Issued 4/14/2021 APPLICANT
Building Plans Picked Up 4/16/2021 APPLICANT
CofO in Progress 2/10/2022 OSVALDO PARAMO
CofO in Progress 2/10/2022 OSVALDO PARAMO
Permit Finaled 2/17/2022 DEROLD HAUFF
CofO Issued 2/17/2022 DEROLD HAUFF
Permit Finaled 2/17/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/29/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 3/10/2021 RENZ SORIANO
Sewer availability Cleared 3/10/2021 RENZ SORIANO
Low Impact Development Cleared 3/19/2021 MARTIN FRAGOSO
Clean Up Green Up Cleared 3/22/2021 RUBEN VASQUEZ
Hydrant and Access approval Cleared 3/22/2021 MATTHEW CRAIG
Roof/Waste drainage to street Cleared 3/22/2021 RENZ SORIANO
GPI Written Notices Cleared 4/6/2021 DANIEL YIP
Grading Pre-Inspection Cleared 4/6/2021 DANIEL YIP

Contact Information

Contractor New World Construction; Lic. No.: 864461-B 838 E 93RD STREET      LOS ANGELES, CA 90002
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/4/2021 Approved OSVALDO PARAMO
Underground Mechanical 5/4/2021 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 5/17/2021 Approved OSVALDO PARAMO
Deputy Wood Construction 8/19/2021 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 8/19/2021 Partial Approval OSVALDO PARAMO
PLUMBING-Rough 8/19/2021 Approved OSVALDO PARAMO
ELECTRICAL-Rough 8/26/2021 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 8/26/2021 Partial Approval OSVALDO PARAMO
HVAC-Rough 8/26/2021 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 8/27/2021 Approved OSVALDO PARAMO
Verify Sprinkler Sign Off 8/27/2021 Approved OSVALDO PARAMO
Insulation 9/2/2021 Not Ready for Inspection OSVALDO PARAMO
Interior/Exterior Lathing 9/2/2021 Partial Approval OSVALDO PARAMO
Drywall Nailing 9/13/2021 Not Ready for Inspection CALEB MEISTER
Insulation 9/14/2021 Approved CALEB MEISTER
Drywall Nailing 9/15/2021 Approved OSVALDO PARAMO
ELECTRICAL-Final 1/4/2022 Not Ready for Inspection SHAVONNE ESPINOZA
Final 1/4/2022 Not Ready for Inspection SHAVONNE ESPINOZA
Gas Test 1/4/2022 Corrections Issued SHAVONNE ESPINOZA
HVAC-Final 1/4/2022 Not Ready for Inspection SHAVONNE ESPINOZA
PLUMBING-Final 1/4/2022 Not Ready for Inspection SHAVONNE ESPINOZA
SGSOV-Seismic Gas S/O Valve 1/4/2022 SGSOV Approved SHAVONNE ESPINOZA
Service/Power Release 1/4/2022 Not Ready for Inspection SHAVONNE ESPINOZA
Smoke Detectors 1/4/2022 Approved SHAVONNE ESPINOZA
Verify Rec and Parks Fee Memo 1/4/2022 Approved SHAVONNE ESPINOZA
Final 1/11/2022 Corrections Issued OSVALDO PARAMO
Gas Test 1/11/2022 Approved OSVALDO PARAMO
Service/Power Release 1/11/2022 Approved OSVALDO PARAMO
Final 2/4/2022 OK to Issue CofO OSVALDO PARAMO