634 E 106TH ST 90002
Certificate Information: 634 E 106TH ST 90002
- Application / Permit
- 20010-10000-04128
- Plan Check / Job No.
- B20LA20552
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SFD WITH ATTACHED GARAGE
- Permit Issued
- Issued on 7/29/2021
- Issuing Office
- Current Status
- CofO Issued on 8/22/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/14/2021 | TSE MING HUANG |
| Corrections Issued | 1/16/2021 | TSE MING HUANG |
| Quality Review Completed | 1/29/2021 | STANLEY RAAP |
| Plan Check Approved | 7/23/2021 | TSE MING HUANG |
| Issued | 7/29/2021 | APPLICANT |
| Building Plans Picked Up | 8/2/2021 | APPLICANT |
| CofO in Progress | 8/18/2023 | JOHN KLARIN |
| CofO Issued | 8/22/2023 | ANSON MAGLASANG |
| Permit Finaled | 8/22/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/26/2021 | JEANIE LAM |
| Sewer availability | Cleared | 4/26/2021 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 5/19/2021 | KURT CORRAL |
| Low Impact Development | Cleared | 6/29/2021 | TA ANH |
| Roof/Waste drainage to street | Cleared | 6/29/2021 | JEANIE LAM |
Contact Information
| Contractor | Pacific Coast Builders; Lic. No.: 834794-B | 9277OTTO ST DOWNEY, CA 90240 |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 2543 E NORMAN AVE WEST COVINA, CA 91791 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/3/2021 | Partial Approval | EUGENE CASSIDY |
| Underground Mechanical | 8/3/2021 | Partial Approval | EUGENE CASSIDY |
| Footing/Foundation/Slab | 8/9/2021 | Approved | EUGENE CASSIDY |
| Deputy Reinf. Concrete | 8/10/2021 | Conditional Approval | WILLIAM ROSE |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2021 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 9/1/2021 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 9/8/2021 | Conditional Approval | EUGENE CASSIDY |
| ELECTRICAL-Rough | 9/8/2021 | Conditional Approval | EUGENE CASSIDY |
| HVAC-Rough | 9/8/2021 | Partial Approval | EUGENE CASSIDY |
| PLUMBING-Rough | 9/8/2021 | Partial Approval | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 9/8/2021 | Partial Approval | EUGENE CASSIDY |
| Insulation | 9/10/2021 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 9/16/2021 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 9/16/2021 | Approved | EUGENE CASSIDY |
| Sewer | 10/26/2021 | Approved | EUGENE CASSIDY |
| Verify Rec and Parks Fee Memo | 10/26/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Gas Test | 1/6/2022 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 2/2/2022 | Approved | JOHN KLARIN |
| HVAC-Final | 2/2/2022 | Corrections Issued | JOHN KLARIN |
| PLUMBING-Final | 2/2/2022 | Approved | JOHN KLARIN |
| Service/Power Release | 2/2/2022 | Not Ready for Inspection | JOHN KLARIN |
| Verify Rec and Parks Fee Memo | 2/2/2022 | Corrections Issued | JOHN KLARIN |
| BUILDING-Rough-Frame | 2/23/2022 | Approved | JOHN KLARIN |
| Final | 2/23/2022 | Corrections Issued | JOHN KLARIN |
| HVAC-Final | 2/23/2022 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 2/23/2022 | SGSOV Approved | JOHN KLARIN |
| Service/Power Release | 2/23/2022 | Not Ready for Inspection | JOHN KLARIN |
| Smoke Detectors | 2/23/2022 | Approved | JOHN KLARIN |
| Verify Sprinkler Sign Off | 2/23/2022 | Approved | JOHN KLARIN |
| Service/Power Release | 3/4/2022 | Approved | JOHN KLARIN |
| Final | 8/17/2023 | OK to Issue CofO | JOHN KLARIN |
| Service/Power Release | 8/17/2023 | Approved | JOHN KLARIN |