5916 N JUMILLA AVE 91367
Certificate Information: 5916 N JUMILLA AVE 91367
- Application / Permit
- 20010-10000-04122
- Plan Check / Job No.
- B20LA20516
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 1-story ADU per LAMC 12.22 A.33 (c)-(d).
- Permit Issued
- Issued on 6/2/2021
- Issuing Office
- Current Status
- CofO Issued on 8/27/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/16/2020 | TSE MING HUANG |
| Corrections Issued | 12/16/2020 | TSE MING HUANG |
| Applicant returned to address corrections | 4/28/2021 | TSE MING HUANG |
| Plan Check Approved | 5/17/2021 | CRISTINA SALAZAR |
| Issued | 6/2/2021 | APPLICANT |
| Building Plans Picked Up | 9/15/2021 | APPLICANT |
| CofO in Progress | 8/19/2022 | SEAN HAUPT |
| CofO Issued | 8/27/2022 | MICHAEL SMITH |
| Permit Finaled | 8/27/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 1/6/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 1/6/2021 | GABRIEL ROBLES |
| ZI | Cleared | 1/7/2021 | STEVEN WECHSLER |
| Sewer availability | Cleared | 1/25/2021 | GABRIEL ROBLES |
| Hydrant and Access approval | Cleared | 2/26/2021 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 5/5/2021 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 5/6/2021 | ABDULLAH SADOZAI |
Contact Information
| Contractor | Flip It Homes Inc; Lic. No.: 1043456-B | 20501 VENTURA BLVD #135 WOODLAND HILLS, CA 91364 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/26/2021 | Corrections Issued | STEVEN BACK |
| Pre-Inspection | 7/26/2021 | Partial Inspection | STEVEN BACK |
| Sewer | 7/26/2021 | Not Ready for Inspection | STEVEN BACK |
| Underground Mechanical | 7/26/2021 | Not Ready for Inspection | STEVEN BACK |
| Footing/Foundation/Slab | 8/2/2021 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 8/2/2021 | Partial Approval | STEVEN BACK |
| Footing/Foundation/Slab | 8/5/2021 | Corrections Issued | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 8/16/2021 | Approved | STEVEN BACK |
| Footing/Foundation/Slab | 8/16/2021 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2021 | Partial Approval | SHAVONNE ESPINOZA |
| Floor/Roof Diaphrgm/Shear Wall | 10/22/2021 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 11/24/2021 | Not Ready for Inspection | SEAN HAUPT |
| ELECTRICAL-Rough | 11/24/2021 | Approved | SEAN HAUPT |
| Green Building Rough | 11/24/2021 | Not Ready for Inspection | SEAN HAUPT |
| HVAC-Rough | 11/24/2021 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 11/24/2021 | Approved | SEAN HAUPT |
| Verify Sprinkler Sign Off | 11/24/2021 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 12/3/2021 | Approved | SEAN HAUPT |
| Green Building Rough | 12/3/2021 | Not Ready for Inspection | SEAN HAUPT |
| Grading Pre-Inspection | 12/7/2021 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 12/15/2021 | Approved | SEAN HAUPT |
| Insulation | 12/22/2021 | Approved | JUSTIN HAWLEY |
| Drywall Nailing | 1/7/2022 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 1/19/2022 | Approved | SEAN HAUPT |
| Shower Pan | 1/19/2022 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 8/4/2022 | Approved | SEAN HAUPT |
| ELECTRICAL-Final | 8/4/2022 | Approved | SEAN HAUPT |
| Final | 8/4/2022 | Corrections Issued | SEAN HAUPT |
| Green Building Final | 8/4/2022 | Approved | SEAN HAUPT |
| Green Building Rough | 8/4/2022 | Approved | SEAN HAUPT |
| HVAC-Final | 8/4/2022 | Approved | SEAN HAUPT |
| PLUMBING-Final | 8/4/2022 | Approved | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 8/4/2022 | SGSOV Not Ready | SEAN HAUPT |
| Service/Power Release | 8/4/2022 | Not Ready for Inspection | SEAN HAUPT |
| Smoke Detectors | 8/4/2022 | Approved | SEAN HAUPT |
| Final | 8/18/2022 | OK to Issue CofO | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 8/18/2022 | SGSOV Approved | SEAN HAUPT |
| Service/Power Release | 8/18/2022 | Approved | SEAN HAUPT |