3520 W MARATHON ST 90026

Certificate Information: 3520 W MARATHON ST 90026

Application / Permit
20010-10000-04110
Plan Check / Job No.
B20LA20475
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
(N) 3 STORY 9 UNIT APARTMENT BUILDING TYPE V-B OVER 1 LEVEL OF TYPE 1-B PARKING
Permit Issued
Issued on 1/4/2022
Issuing Office
Current Status
CofO Issued on 4/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/6/2020 APPLICANT
Assigned to Plan Check Engineer 11/20/2020 LAMAR DAVIS
Disabled Access Plans Picked Up 12/2/2020 APPLICANT
Corrections Issued 12/22/2020 LAMAR DAVIS
Quality Review Completed 1/13/2021 GARO TELMI
Green Plans Picked Up 4/6/2021 APPLICANT
Applicant returned to address corrections 4/9/2021 LAMAR DAVIS
Applicant returned to address corrections 6/30/2021 LAMAR DAVIS
Plan Check Approved 12/17/2021 LAMAR DAVIS
Issued 1/4/2022 APPLICANT
Building Plans Picked Up 1/12/2022 APPLICANT
CofO Issued 4/12/2024 ERNESTO CORRAL
Permit Finaled 4/12/2024 ERNESTO CORRAL

Permit Application Clearance Information

Hydrant and Access approval Cleared 12/17/2020 MATTHEW CRAIG
Eng Process Fee Ord 176,300 Cleared 2/3/2021 RENZ SORIANO
Address approval Cleared 2/25/2021 RENZ SORIANO
Building over 36-ft Cleared 4/9/2021 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 4/9/2021 CALOSHA APPROVED
Grading Pre-Inspection Cleared 4/20/2021 BRIAN MILLER
Green Code Cleared 5/7/2021 NEGAR NEJAD
Frnt yard landscape/Water mgmt Cleared 5/13/2021 MAXFIELD VERMY
Opn space landscape/Water mgmt Cleared 5/13/2021 MAXFIELD VERMY
DAS Clearance Cleared 6/3/2021 CHOI YAN
Trees in Parkway Cleared 6/8/2021 JOHN KIM
GPI Written Notices Cleared 6/22/2021 BRIAN MILLER
Highway dedication Cleared 7/14/2021 RENZ SORIANO
Permit Cleared 7/14/2021 RENZ SORIANO
Fire Marshal Fire Life Safety Cleared 8/25/2021 VIDAL GARCIA
Sewer availability Cleared 8/25/2021 RENZ SORIANO
Low Impact Development Cleared 11/23/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 12/2/2021 TREVOR QUAN

Contact Information

Architect Driscoll,, Christopher; Lic. No.: C36073 2826 8TH AVE      LOS ANGELES, CA 90018
Contractor Hy-Max Building Corp; Lic. No.: 702339-B 425 W BROADWAY #410      GLENDALE, CA 91204
Engineer Knur,, Reinard Thomas; Lic. No.: GE2755 1435 MONCADO DR      GLENDALE, CA 91207
Engineer Timmers,, Matthew Allan; Lic. No.: S5560 950 S. GRAND AVE 4TH FLR      LOS ANGELES, CA 90015
Geologist Knur,, Reinard Thomas; Lic. No.: EG1547 1435 MONCADO DRIVE      GLENDALE, CA 91207

Inspector Information

DAVID BURKHEAD, (213) 482-7294 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/28/2022 Partial Inspection DANIEL MC AULIFFE
Piling/Pier/Caisson 2/4/2022 Partial Approval DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 2/15/2022 Partial Inspection DANIEL MC AULIFFE
Footing/Foundation/Slab 2/22/2022 Not Ready for Inspection DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 2/25/2022 Not Ready for Inspection DANIEL MC AULIFFE
Footing/Foundation/Slab 2/28/2022 Partial Approval DANIEL MC AULIFFE
Green Building Rough 2/28/2022 Not Ready for Inspection DANIEL MC AULIFFE
Reinforced Concrete Frame 2/28/2022 Partial Approval DANIEL MC AULIFFE
Verify Sprinkler Sign Off 2/28/2022 Not Ready for Inspection DANIEL MC AULIFFE
Deputy Reinf. Concrete 3/1/2022 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 3/3/2022 Approved DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 3/3/2022 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 3/4/2022 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 3/11/2022 Approved DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 3/11/2022 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 3/16/2022 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 4/1/2022 Approved DANIEL MC AULIFFE
Deputy Reinf. Concrete 4/4/2022 Approved DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 4/4/2022 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 4/8/2022 Conditional Approval DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 4/8/2022 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 4/11/2022 Conditional Approval DANIEL MC AULIFFE
Deputy Shotcrete 4/12/2022 Conditional Approval DANIEL MC AULIFFE
Deputy Shotcrete 4/13/2022 Approved DANIEL MC AULIFFE
Deputy Shotcrete 4/14/2022 Conditional Approval JONATHAN QUACH
Excavation/Setback/Form/Re-Bar 4/14/2022 Partial Approval JONATHAN QUACH
Deputy Shotcrete 4/15/2022 Conditional Approval DANIEL MC AULIFFE
Deputy Shotcrete 4/18/2022 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 4/25/2022 Approved DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 4/25/2022 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 4/28/2022 Approved DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 5/6/2022 Not Ready for Inspection DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 5/20/2022 Partial Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 5/21/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 5/23/2022 Conditional Approval ERNESTO CORRAL
Deputy Shotcrete 6/28/2022 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 6/28/2022 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 7/1/2022 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 7/1/2022 Partial Approval DAVID BURKHEAD
Deputy Reinf. Concrete 7/5/2022 Conditional Approval ERNESTO CORRAL
Deputy Wood Construction 8/5/2022 Conditional Approval ERNESTO CORRAL
Green Building Rough 8/10/2022 Not Ready for Inspection GREGORY POMISH
Verify Sprinkler Sign Off 8/10/2022 Not Ready for Inspection GREGORY POMISH
Wood Frame 8/10/2022 Partial Approval GREGORY POMISH
Deputy Wood Construction 8/11/2022 Conditional Approval DAVID BURKHEAD
Green Building Rough 8/19/2022 Not Ready for Inspection GREGORY POMISH
Verify Sprinkler Sign Off 8/19/2022 Not Ready for Inspection GREGORY POMISH
Wood Frame 8/19/2022 Partial Approval GREGORY POMISH
Green Building Rough 9/9/2022 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 9/9/2022 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 9/9/2022 Partial Approval DAVID BURKHEAD
Deputy Wood Construction 10/20/2022 Conditional Approval DAVID BURKHEAD
Green Building Rough 10/26/2022 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 10/26/2022 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 10/26/2022 Partial Inspection DAVID BURKHEAD
Green Building Rough 11/22/2022 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 11/22/2022 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 11/22/2022 Partial Approval DAVID BURKHEAD
Deputy Wood Construction 12/13/2022 Conditional Approval MICHAEL ROSENBERG
Drywall Nailing 1/4/2023 Not Ready for Inspection DAVID BURKHEAD
Green Building Rough 1/4/2023 Not Ready for Inspection DAVID BURKHEAD
Green Building Rough 1/20/2023 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 1/20/2023 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 1/20/2023 Partial Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 1/23/2023 Partial Approval DAVID BURKHEAD
Green Building Rough 1/31/2023 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 1/31/2023 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 1/31/2023 Partial Approval DAVID BURKHEAD
Deputy Wood Construction 2/8/2023 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 2/8/2023 Partial Approval DAVID BURKHEAD
Deputy Drilled-In Anchors 3/9/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 3/9/2023 Conditional Approval MICHAEL ROSENBERG
Green Building Rough 3/13/2023 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 3/13/2023 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 3/13/2023 Not Ready for Inspection DAVID BURKHEAD
Deputy Wood Construction 3/14/2023 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 3/15/2023 Partial Approval DAVID BURKHEAD
Insulation 3/16/2023 Partial Approval JEROME BLACKWOOD
Insulation 3/22/2023 Partial Approval ALFREDO LOPEZ
Deputy Reinf. Masonry 3/29/2023 Conditional Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 3/29/2023 Partial Approval DAVID BURKHEAD
Insulation 3/29/2023 Partial Approval DAVID BURKHEAD
Deputy Reinf. Masonry 4/3/2023 Conditional Approval DAVID BURKHEAD
Deputy Wood Construction 4/3/2023 Conditional Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 4/3/2023 Partial Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 4/25/2023 Partial Approval DAVID BURKHEAD
Deputy Wood Construction 4/26/2023 Conditional Approval MICHAEL ROSENBERG
Drywall Nailing 5/3/2023 Partial Approval RAFAEL ESPINOZA
Green Building Rough 5/3/2023 Approved RAFAEL ESPINOZA
T-Bar Ceiling 5/5/2023 Partial Approval GREGORY POMISH
Drywall Nailing 5/15/2023 Partial Approval DAVID BURKHEAD
Interior/Exterior Lathing 6/20/2023 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 8/23/2023 Conditional Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 8/23/2023 Partial Approval DAVID BURKHEAD
Special/Order Compliance 10/16/2023 Not Ready for Inspection RAFAEL ESPINOZA
Special/Order Compliance 10/19/2023 Partial Inspection GREGORY POMISH
Special/Order Compliance 11/8/2023 Approved DAVID BURKHEAD
Light Gage Steel Frame 11/28/2023 Partial Approval JACOB MYERS
Drywall Nailing 12/5/2023 Partial Approval RONALD JIMENEZ
Special/Order Compliance 12/21/2023 Approved DAVID BURKHEAD
Drywall Nailing 2/2/2024 Approved DAVID BURKHEAD
Footing/Foundation/Slab 2/2/2024 Approved DAVID BURKHEAD
Green Building Final 2/2/2024 Approved DAVID BURKHEAD
Reinforced Concrete Frame 2/2/2024 Approved DAVID BURKHEAD
SGSOV-Seismic Gas S/O Valve 2/2/2024 SGSOV No Gas DAVID BURKHEAD
Smoke Detectors 2/2/2024 Approved DAVID BURKHEAD
Verify Sprinkler Sign Off 2/2/2024 Approved DAVID BURKHEAD
Wood Frame 2/2/2024 Approved DAVID BURKHEAD
Final 2/6/2024 Conditional Approval DAVID BURKHEAD
Final 3/12/2024 Partial Inspection DAVID BURKHEAD