NEW 3-STORY SFD WITH ATTACHED GARAGE, NEW ROOF DECK, LOWER FLOOR BALCONY, SECOND FLOOR BALCONY, THIRD FLOOR BALCONY 1 OF 3
Permit Issued
Issued on 8/16/2024
Issuing Office
Metro
Current Status
Issued on 8/16/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/2/2020 APPLICANT
Assigned to Plan Check Engineer 11/12/2020 ALBERT SERVIN
Corrections Issued 11/24/2020 ALBERT SERVIN
Quality Review Completed 12/4/2020 PETER KIM
Building Plans Picked Up 12/14/2020 APPLICANT
Applicant returned to address corrections 1/21/2021 ALBERT SERVIN
Applicant returned to address corrections 2/9/2021 ALBERT SERVIN
Applicant returned to address corrections 3/9/2022 ALBERT SERVIN
Applicant returned to address corrections 3/10/2022 ALBERT SERVIN
Plan Check Approved 5/19/2022 ALBERT SERVIN
Issued 8/16/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 3/8/2021 WALLIE JONG
BHO/Hillside ordinance Cleared 3/26/2021 WALLIE JONG
BHO/Hillside ordinance Cleared 3/26/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 3/31/2021 WALLIE JONG
Sewer availability Cleared 3/31/2021 WALLIE JONG
Hydrant and Access approval Cleared 9/18/2021 ROBERT DUFF
Excavation more than 5-ft deep Cleared 10/1/2021 CALOSHA APPROVED
Disturb/Remove Protected Trees Cleared 10/28/2021 ADALBERTO VERA
"D" conditions Cleared 11/5/2021 DANIEL CORONADO
"Q" conditions Cleared 11/5/2021 DANIEL CORONADO
Miscellaneous Cleared 11/5/2021 DANIEL CORONADO
Low Impact Development Cleared 12/9/2021 TA ANH
Roof/Waste drainage to street Cleared 12/14/2021 AMAAN MALIK
BHO/Hillside ordinance Cleared 12/20/2021 WALLIE JONG
BHO/Hillside ordinance Cleared 12/20/2021 WALLIE JONG
BHO/Hillside ordinance Cleared 12/20/2021 WALLIE JONG
Encroachment in public way Cleared 2/22/2022 MSTAFA AL-MSARI
Miscellaneous Cleared 2/24/2022 STEVE MELGAR
Green Code Cleared 5/19/2022 ALBERT SERVIN

Contact Information

Architect Mizuki,, Steve Massanori; Lic. No.: C22676 2155 VERDUGO BLVD # 330      MONTROSE, CA 91020
Contractor D F L Group Llc; Lic. No.: 1046215-B 8209 DUARTE ROAD      SAN GABRIEL, CA 91775
Engineer Chang,, Paul Pao-Lin; Lic. No.: GE2181 1529 ELKWOOD DR      WEST COVINA, CA 91791
Engineer Chiu,, Ivan Wai-Kuen; Lic. No.: C44672 2160 PARNELL WY      ALTADENA, CA 91001
Engineer Erdelyi,, Peter Tibor; Lic. No.: C26962 1950 SAWTELLE BLVD STE 175      LOS ANGELES, CA 90025

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/3/2024 Not Ready for Inspection LILIANA PORTILLO
Piling/Pier/Caisson 10/3/2024 Not Ready for Inspection LILIANA PORTILLO
Deputy Reinf. Concrete 10/4/2024 Conditional Approval THOMAS LOGRASSO
Piling/Pier/Caisson 10/8/2024 Partial Approval LILIANA PORTILLO
Deputy Reinf. Concrete 10/10/2024 Conditional Approval JOHN QUINTANILLA
Piling/Pier/Caisson 10/10/2024 Approved LILIANA PORTILLO
Deputy Reinf. Concrete 10/11/2024 Conditional Approval LILIANA PORTILLO
Deputy Reinf. Concrete 11/21/2024 Conditional Approval LILIANA PORTILLO
Excavation/Setback/Form/Re-Bar 11/26/2024 Corrections Issued JOHN QUINTANILLA
Footing/Foundation/Slab 11/26/2024 Corrections Issued JOHN QUINTANILLA
Excavation/Setback/Form/Re-Bar 12/2/2024 Corrections Issued LILIANA PORTILLO
Deputy Reinf. Concrete 12/3/2024 Conditional Approval LILIANA PORTILLO
Excavation/Setback/Form/Re-Bar 1/10/2025 Corrections Issued LILIANA PORTILLO
Deputy Reinf. Concrete 1/23/2025 Approved LILIANA PORTILLO
Deputy Drilled-In Anchors 4/23/2025 Conditional Approval NICHOLAS LOPEZ
Wood Frame 5/8/2025 Corrections Issued LILIANA PORTILLO
Deputy Wood Construction 6/23/2025 Conditional Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 6/25/2025 Corrections Issued LILIANA PORTILLO
Special/Order Compliance 7/17/2025 Partial Inspection LILIANA PORTILLO
BUILDING-Rough-Frame 8/19/2025 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Rough 8/19/2025 Corrections Issued LILIANA PORTILLO
HVAC-Rough 8/19/2025 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Rough 8/19/2025 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 8/21/2025 Approved LILIANA PORTILLO
PLUMBING-Rough 8/21/2025 Approved LILIANA PORTILLO
HVAC-Rough 8/22/2025 Conditional Approval LILIANA PORTILLO
BUILDING-Rough-Frame 8/25/2025 No Access for Inspection LILIANA PORTILLO
HVAC-Rough 8/25/2025 No Access for Inspection LILIANA PORTILLO
Verify Sprinkler Sign Off 8/25/2025 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 8/28/2025 Approved LILIANA PORTILLO
Green Building Rough 8/28/2025 Not Ready for Inspection LILIANA PORTILLO
Insulation 9/16/2025 Partial Approval REGINA MENDEZ
Interior/Exterior Lathing 9/16/2025 Approved REGINA MENDEZ
Drywall Nailing 9/22/2025 Approved GEM DE OCAMPO
Insulation 9/24/2025 Approved REGINA MENDEZ
Shower Pan 10/2/2025 Approved REGINA MENDEZ
Deputy Reinf. Concrete 2/6/2026 Conditional Approval GEM DE OCAMPO
ELECTRICAL-Final 2/13/2026 Not Ready for Inspection LILIANA PORTILLO
HVAC-Final 2/13/2026 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Final 2/13/2026 Not Ready for Inspection LILIANA PORTILLO
Service/Power Release 2/13/2026 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Final 4/1/2026 Not Ready for Inspection LILIANA PORTILLO
Final 4/1/2026 Corrections Issued LILIANA PORTILLO
HVAC-Final 4/1/2026 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Final 4/1/2026 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Final 4/17/2026 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 5/5/2026 Approved LILIANA PORTILLO
Final 5/5/2026 Not Ready for Inspection LILIANA PORTILLO
Footing/Foundation/Slab 5/5/2026 Approved LILIANA PORTILLO
Green Building Final 5/5/2026 Approved LILIANA PORTILLO
Green Building Rough 5/5/2026 Approved LILIANA PORTILLO
Reinforced Masonry Frame 5/5/2026 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 5/5/2026 SGSOV No Gas LILIANA PORTILLO
Service/Power Release 5/5/2026 Not Ready for Inspection LILIANA PORTILLO
Smoke Detectors 5/5/2026 Approved LILIANA PORTILLO
Service/Power Release 5/20/2026 Approved LILIANA PORTILLO